Post on 22-Jul-2016
description
LATIHAN INDUSTRI (INTERNSHIP) SESI DIS 2012
NAME : VIVIEN LAI MEI YEN
COURSE: CIVIL ENGINEERING MATRIC NO. : 01DKA10F1005
8/3/2013
LECTURER’S NAME :PN FARIDAH BT MOHD ZINPN HANIZA BT MOHAMED
COMPANY PROFILEGAINTREND SDN BHD
MANAGEMENT TEAM Mr. Nelson Tan ( Managing Director)
Mr. Yap Biaw Thiang (General Manager/ Project Head)
Ms. Tan BH (Accounts Department/ Human Resource Department Manager)
Ms. Lee LL (QSM Manager)
Mr. Abdul Rahman Ismail (Site Supervisor)
Mr. Mohd Najib B. Halim (Ass. Site Supervisor)
COMPLETED PROJECTProject Cadangan Membina Rumah Teres
3 Tingkat ( 4 Unit) & Rumah Teres 2 Tingkat ( 25Unit) Di Atas Lot 319, Sek. 1, Bandar Jelutong, DTL, Jalan Jelutong, Pulau Pinang.
Name of Architect/Consultant
Jurucita Consultant Sdn Bhd
Date of Start 2 August 2011Date of Completed 27 Jun 2012
CURRENT PROJECTProject Commencement Date Completion
DateCadangan Skim Perumahan Di Atas Lot 144, 1418, 1419, 1420 Dan 1421 Mk14, S.P.T, Di Jalan Kota Permai, Bukit Mertajam, Pulau Pinang For Messers Pacific Treasure Land Sdn. Bhd.
-Structural, Masonry, Ceiling and Metal Works-
17/6/2012 16/6/2013
Organization Chart on siteGaintrend Sdn Bhd
Project Head
Mr. Yap Biaw Tiang
Contract
Mr. Loh P.G
Ms Sow A.T
Site Head
Mr. Mohd Fauzi Shari
Site Supervisor
Mr. Abdul Rahman Ismail
Asst. Site Supervisor
Mr. Mohd Najib B. Halim
PRO (FAC)
Mr Teoh S.C
Site Safety Supervisor
Mr. Mohd Hazri B. Hashim
CONSTRUCTION PROGRESSOF
DOUBLE STOREY SEMI-DETACH(DSSD)
BUILDING ELEMENTS OF DSSD Foundation Ground Beam Ground Floor Slab (non suspended) Ground Columns 1st Floor Slab & Beam 1st Floor Column Staircase Roof beam & T-beam
FOUNDATION
Foundation is the most important part of the building.
(a)Distribute the load from the structure to soil evenly and safely.
(b)To anchor the building to the ground so that under lateral loads building will not move.
(c) Prevents the building from overtuning due to lateral forces.
(d)Gives level surface for the construction of super structure.
GROUND BEAM
1) Erection of formwork
2) Reinforcement works are in progress.
3) At last, Concrete Casting is carried out.
GROUND FLOOR SLAB (NON-SUSPENDED)
-Slabs are important components of a building.
-Classified on two types of slab:(a)One-way slab(b)Two-way slab
GROUND FLOOR COLUMNS
Transfer load of structure vertically downwards .
1ST FLOOR SLAB&BEAM
1ST FLOOR COLUMN
STAIRCASE
All steps shall have nonskid covering, and skid resistant edging can be fastened at the forefront of the steps.
The forefront of the steps can also be marked with a color edging.
ROOF BEAM & T-BEAM
T-Beam
LASTLY….