PRESUSPUESTO: CONSTRUCCION DE CERCO PERIMETRICO EN LA I.E ANTONIO RAYMONDI-DISTRITO DE CASMA

CLIENTE: MUNICIPALIDAD DISTRITAL DE CASMA

LUGAR: ANCASH - CASMA- CASMA

ITEM DESCRIPCION UNDCANTIDA

D PUSUB

TOTALTOTAL

1 OBRAS PROVISIONALES          

1.1 CARTEL DE OBRA DE 7.20 X 6.00M 1.00 757.18 757.18  

1.2 CASETA PARA GUARDIANIA Y ALMACEN 1

2,500.00 2,500.00

 

          3,257.18 3,257.182 OBRAS PRELIMINARES        

2.1 LIMPIEZA DE TERRENO - Manual m2 346.51 2.47 855.88  

2.2 TRAZO, NIVELES Y REPLANTEO m2 207.91 0.64 133.06  

  SUB TOTAL       988.94 988.94

3 MOVIMIENTO DE TIERRAS          

3.1 EXCAVACIÓN DE ZANJAS PARA CIMIENTOS m3 150.10 25.01 3,754.00  

3.2ELIMINACIÓN DE MATERIAL EXCEDENTE -Distancia 5.00 km m3 195.12 1.25 243.90  

  SUB TOTAL       3,997.90 3,997.90

4 CIMIENTO CORRIDO          

4.1 CIMIENTOS          

4.1.1 CONCRETO CICLÓPEO FC = 140 KG/CM2 + 70 % PG. m3 150.1 438.1065,758.8

1  

4.2 SOBRECIMIENTOS          

4.2.1 CONCRETO CICLÓPEO FC=140KG/CM2 + 30% PM m3 14.31 372.10 5,324.75  

4.2.2 ENCOFRADO Y DESENCOFRADO - SOBRECIMIENTO m2 190.80 31.09 5,931.97  

  SUB TOTAL      77,015.5

3 77015.533

5 CONCRETO ARMADO        

5.1 COLUMNAS          

5.1.1 CONCRETO f'c = 175Kg/Cm2 m3 32.43 341.0511,060.2

5  

5.1.2 ENCOFRADO Y DESENCOFRADO - Columnas m2 324 66.9521,691.8

0  

5.1.3 ACERO GRADO60 - Columnas Kg 1146.74 3.83 4,392.01  

  SUB TOTAL      37,144.0

7 37,144.076 ALBAÑILERIA        

6.1 MURO DE SOGA - Ladrillo KK ARTESANAL m2 699.50 42.1329,469.9

4  

  SUB TOTAL      29,469.9

4 29,469.94

7 CARPINTERÍA DE METÁLICA        

7.1 PORTON DE FERRO 3.00 X 2.50 M Und 2.001,500.0

0 3,000.00  

  SUB TOTAL       3,000.00 3,000.00

8 FLETE TERRESTRE        

8.1 FLETE TERRESTRE Kg 150,218.96 0.0812,017.5

2  

  SUB TOTAL      12,017.5

2 12,017.52

   TOTA

L      166,891.0

7

ITEM RESUMEN PARTIDASSUB TOTAL

TOTAL

1.00 OBRAS PROVISIONALES 3,257.18  

2.00 OBRAS PRELIMINARES 988.94  

3.00 MOVIMIENTO DE TIERRAS 3,997.90  

4.00 CIMIENTO CORRIDO 77,015.53  

5.00 CONCRETO ARMADO 37,144.07  

6.00 ALBAÑILERIA 29,469.94  

7.00 CARPINTERIA METALICA 3,000.00  

8.00 FLETE TERRESTRE 12,017.52  

  COSTO DIRECTO DE OBRA S/. 166,891.07

  GASTOS GENERALES (10 % CD) S/. 16,689.11

  UTILIDAD(10 %) S/. 16,689.11

  SUB TOTAL S/. 200,269.29

  IGV(18%) S/. 36,048.47

  TOTAL COSTOS DE INFRAESTRUCTURA S/. 236,317.76