Valoriza. Precios Unitarios

Post on 04-Oct-2015

7 views 0 download

description

EJEMPLO DE VALORIZACIÓN A PRECIOS UNITARIOS

Transcript of Valoriza. Precios Unitarios

  • COMPONENTE: INFRAESTRUCTURA

    CONTRATISTA: ZORRILLA HUAMN ANTONIO - INGENIERO CORRESPONDIENTE A: OCTUBRE - 07

    RESIDENTE : ING. JUAN ANTONIO CIFR PAREDES PERODO: 01/10/07 AL 31/10/07

    SUPERVISOR : ING. ORLANDO AGUILAR ALIAGA FECHA : 30/10/200708/11/2007

    P. UNIT.

    S/. METRADO PARCIAL (S/.) ( % ) METRADO PARCIAL (S/.) ( % ) METRADO S/. ( % ) METRADO S/. ( % )

    01.00 OBRAS PRELIMINARES 247.01 247.01 0.00 247.01 0.00

    01.01 CARTEL DE OBRA UND 1.00 247.01 247.01 1.00 247.01 100.00 0.00 0.00 0.00 1.00 247.01 100.00 0.00 0.00 0.00

    05.00 CAMBIO DE TAPAS DE INSPECCIN EN ESTRUCTURAS 320.00 0.00 0.00 0.00 320.00

    01.00 TRABAJOS PRELIMINARES

    01.01 PICADO DE LOSA (TECHO) EN ESTRUCTURAS M2 0.24 67.62 16.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.24 16.23 100.00

    02.00 CONCRETO SIMPLE

    02.01 CONCRETO F'C=175 KG/CM2 M3 0.15 257.73 38.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.15 38.66 100.00

    03.00 CAMBIO DE TAPA DE INSPECCIN

    03.01 TAPA METLICA SANITARIA 0.60 X 0.60, e=1/8" UND 3.00 88.37 265.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 265.11 100.00

    06.00 RED DE DISTRIBUCIN 77,210.54 13,459.93 26,939.92 40,399.85 36,810.69

    01.00 TRABAJOS PRELIMINARES

    01.01 TRAZO, NIVELACIN Y REPLANTEO ML 1,083.22 0.39 422.46 1,069.23 417.00 98.71 0.00 0.00 0.00 1,069.23 417.00 98.71 13.99 5.46 1.29

    02.00 MOVIMIENTO DE TIERRAS

    02.01 CORTE DE PAVIMENTO ML 2,166.44 2.76 5,979.37 2,138.46 5,902.15 98.71 0.00 0.00 0.00 2,138.46 5,902.15 98.71 27.98 77.22 1.29

    02.02 DEMOLICIN DE PAVIMENTO RGIDO ML 1,083.22 5.88 6,369.33 816.38 4,800.31 75.37 249.10 1,464.71 23.00 1,065.48 6,265.02 98.36 17.74 104.31 1.64

    02.03 EXCAVACIN MANUAL DE ZANJAS 0.60 x 1.10 m ML 1,083.22 1.58 1,711.49 289.77 457.84 26.75 777.90 1,229.08 71.81 1,067.67 1,686.92 98.56 15.55 24.57 1.44

    02.04 RETIRO DE TUBERA ANTIGUA ML 1,083.22 0.27 292.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,083.22 292.47 100.00

    02.05 CARGUO Y ELIMINACIN DE MATERIAL EXCEDENTE M3 165.08 4.45 734.61 0.00 0.00 0.00 49.16 218.76 29.78 49.16 218.76 29.78 115.92 515.85 70.22

    02.06 REFINE Y NIVELACIN DE FONDOS ML 1,083.22 0.20 216.64 290.02 58.00 26.77 777.90 155.58 71.81 1,067.92 213.58 98.59 15.30 3.06 1.41

    02.07 CAMA DE APOYO PARA TUBERAS, e=0.10 m. ML 1,083.22 1.30 1,408.19 290.02 377.03 26.77 680.80 885.04 62.85 970.82 1,262.07 89.62 112.40 146.12 10.38

    02.08 RELLENO Y COMPACTACIN DE ZANJAS CON MATERIAL PROPIO ML 1,083.22 2.49 2,697.22 0.00 0.00 0.00 673.62 1,677.31 62.19 673.62 1,677.31 62.19 409.60 1019.91 37.81

    03.00 REEMPLAZO DE TUBERA 0.00

    03.01 TUBERA PVC SAP CLASE 7.5 - 2" ML 61.83 4.05 250.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.83 250.41 100.00

    03.02 TUBERA PVC SAP CLASE 7.5 - 4" ML 1,021.39 13.16 13,441.49 110.00 1,447.60 10.77 684.95 9,013.94 67.06 794.95 10,461.54 77.83 226.44 2,979.95 22.17

    04.00 PRUEBA HIDRULICA

    04.01 PRUEBA HIDRULICA Y DESINFECCIN EN REDES DE AGUA ML 1,083.22 0.16 173.32 0.00 0.00 0.00 498.60 79.78 46.03 498.60 79.78 46.03 584.62 93.54 53.97

    05.00 REPOSICIN DE PAVIMENTO

    05.01 RELLENO Y COMPACTACIN DE BASE ML 1,083.22 3.74 4,051.24 0.00 0.00 0.00 326.25 1,220.18 30.12 326.25 1,220.18 30.12 756.97 2,831.06 69.88

    05.02 REPOSICIN DE PAVIMENTO RGIDO F'C=210 KG/CM2 M3 129.99 292.98 38,084.47 0.00 0.00 0.00 37.53 10,995.54 28.87 37.53 10,995.54 28.87 92.46 27,088.93 71.13

    05.03 JUNTAS DE DILATACIN EN LOSA ML 216.64 6.36 1,377.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 216.64 1,377.83 100.00

    07.00 FLETE 6,377.33 3,188.67 2,550.93 5,739.60 637.73

    07.01 FLETE TERRESTRE GLB 1.00 6,377.33 6,377.33 0.50 3,188.67 50.00 0.40 2,550.93 40.00 0.90 5,739.60 90.00 0.10 637.73 10.00

    08.00 INSTALACIN DE MEDIDORES (142 UND) 26,720.74 21.34 0.00 21.34 26,699.40

    01.01 TRAZO Y REPLANTEO M2 62.48 0.47 29.37 45.40 21.34 72.66 0.00 0.00 0.00 45.40 21.34 72.66 17.08 8.03 27.34

    01.02 DEMOLICIN DE VEREDA (e=0.10 M) M2 44.00 3.99 175.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44.00 175.56 100.00

    01.03 EXCAVACIN MANUAL M3 37.49 10.62 398.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.49 398.14 100.00

    01.04 CARGUO Y ELIMINACIN DE MATERIAL EXCEDENTE M3 22.72 4.45 101.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.72 101.10 100.00

    01.05 BASE MEDIDOR DE PIEDRA PEQUEA (CONFITILLO) M2 29.82 10.71 319.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29.82 319.37 100.00

    01.06 INSTALACIN DE MEDIDOR UND 142.00 170.53 24,215.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 142.00 24,215.26 100.00

    01.07 RELLENO Y COMPACTACIN MANUAL M3 19.88 5.56 110.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.88 110.53 100.00

    01.08 REPOSICIN DE VEREDA DE CONCRETO 4" M2 61.06 22.46 1,371.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.06 1,371.41 100.00

    09.00 ACOMETIDAS E INSTALACIN DE MEDIDORES (116 UND) 55,075.76 1,425.56 3,741.08 5,166.64 49,909.12

    01.00 ACOMETIDAS (LONGITUD PROMEDIO = 5 MTS)

    01.01 TRAZO Y REPLANTEO ML 580.00 0.35 203.00 299.55 104.84 51.65 10.73 3.76 1.85 310.28 108.60 53.50 269.72 94.40 46.50

    01.02 CORTE DE PAVIMENTO RGIDO ML 1,160.00 2.76 3,201.60 478.52 1,320.72 41.25 19.32 53.32 1.67 497.84 1,374.04 42.92 662.16 1,827.56 57.08

    01.03 DEMOLICIN DE PAVIMENTO RGIDO ML 580.00 4.07 2,360.60 0.00 0.00 0.00 252.02 1,025.72 43.45 252.02 1,025.72 43.45 327.98 1,334.88 56.55

    01.04 CARGUO Y ELIMINACIN DE MATERIAL EXCEDENTE M3 55.25 4.38 242.00 0.00 0.00 0.00 6.15 26.94 11.13 6.15 26.94 11.13 49.10 215.06 88.87

    01.05 EXCAVACIN MANUAL DE ZANJAS ML 580.00 1.58 916.40 0.00 0.00 0.00 126.81 200.36 21.86 126.81 200.36 21.86 453.19 716.04 78.14

    01.06 REFINE Y NIVELACIN DE FONDOS ML 580.00 0.20 116.00 0.00 0.00 0.00 126.81 25.36 21.86 126.81 25.36 21.86 453.19 90.64 78.14

    01.07 CAMA DE APOYO PARA TUBERAS ML 580.00 1.30 754.00 0.00 0.00 0.00 126.81 164.85 21.86 126.81 164.85 21.86 453.19 589.15 78.14

    01.08 RELLENO Y COMPACTACIN DE ZANJAS CON MAT. PROPIO ML 580.00 2.41 1,397.80 0.00 0.00 0.00 126.81 305.61 21.86 126.81 305.61 21.86 453.19 1,092.19 78.14

    01.09 RELLENO Y COMPACTACIN DE BASE ML 580.00 3.74 2,169.20 0.00 0.00 0.00 49.59 185.47 8.55 49.59 185.47 8.55 530.41 1,983.73 91.45

    01.10 REPOSICIN DE PAVIMENTO RGIDO F'C=210 KG/CM2 M3 58.00 293.35 17,014.30 0.00 0.00 0.00 4.96 1,455.02 8.55 4.96 1,455.02 8.55 53.04 15,559.28 91.45

    02.00 INSTALACIN DE MEDIDORES 0.00 0.00

    02.01 TRAZO Y REPLANTEO M2 51.04 0.65 33.18 0.00 0.00 0.00 1.92 1.25 3.77 1.92 1.25 192.31 49.12 31.93 96.23

    02.02 DEMOLICIN DE VEREDA (e=0.10 m) M2 51.04 3.99 203.65 0.00 0.00 0.00 41.68 166.30 81.66 41.68 166.30 4,167.92 9.36 37.35 18.34

    02.03 EXCAVACIN MANUAL M3 30.62 10.62 325.18 0.00 0.00 0.00 11.97 127.12 39.09 11.97 127.12 1,196.99 18.65 198.06 60.91

    02.04 CARGUO Y ELIMINACIN DE MATERIAL EXCEDENTE M3 18.55 4.38 81.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.55 81.25 100.00

    02.05 BASE MEDIDOR DE PIEDRA PEQUEA (CONFITILLO) M2 24.36 10.71 260.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.36 260.90 100.00

    02.06 INSTALACIN DE MEDIDOR - ACOMETIDA UND 116.00 211.35 24,516.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 116.00 24,516.60 100.00

    02.07 RELLENO Y COMPACTACIN MANUAL M3 16.24 9.84 159.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.24 159.80 100.00

    02.08 REPOSICIN DE VEREDA DE CONCRETO 4" M2 49.88 22.46 1,120.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.88 1,120.30 100.00

    23.00 MEJORAMIENTO CASETA DE VLVULA (01 UND) 2,178.54 0.00 0.00 0.00 2,178.54

    01.00 PICADO EN ESTRUCTURAS

    01.01 PICADO DE MURO Y LOSA EN ESTRUCTURAS M2 0.29 39.26 11.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.29 11.39 100.00

    02.00 CONCRETO SIMPLE

    02.01 RESANE EN ESTRUCTURAS M2 0.29 8.49 2.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.29 2.46 100.00

    03.00 REEMPLAZO DE TUBERA

    03.01 ACCESORIOS DE INGRESO 4" UND 2.00 437.47 874.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 874.94 100.00

    03.02 ACCESORIOS DE SALIDA 6" UND 1.00 879.20 879.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 879.20 100.00

    03.03 ACCESORIOS DE REBOSE Y LIMPIEZA 4" UND 1.00 410.55 410.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 410.55 100.00

    TOTAL COSTO DIRECTO 168,129.92 18,342.51 33,231.93 51,574.44 116,555.48

    FACTOR DE RELACIN F.R. = 0.92777 155,985.37 17,017.57 30,831.48 47,849.06 108,136.31

    GASTOS GENERALES (9% C.D.) 14,038.68 1,531.58 2,774.83 4,306.41 9,732.27

    UTILIDAD (3% C.D.) 4,679.56 510.53 924.94 1,435.47 3,244.09

    SUB TOTAL 174,703.61 19,059.68 34,531.25 53,590.93 121,112.68

    I.G.V. (19%) 33193.68

    TOTAL PRESUPUESTO VALORIZADO 207897.29

    PARA EL PERODO QUE SE VALORIZA:

    PORCENTAJE DE AVANCE DE OBRA PROGRAMADO (%) 12.42% 24.94% 37.36% 62.64%

    AVANCE DE OBRA PROGRAMADO (S/.) 19378.59 38909.12 58287.71 97697.66

    PORCENTAJE DE AVANCE DE OBRA EJECUTADO (%) 10.91% 19.77% 30.68% 69.32%

    PORCENTAJE DE AVANCE VS PROGRAMADO 87.84% 79.25% 82.11%

    PORCENTAJE DE ATRASO RESPECTO AL OFICIAL 17.89%

    ITEM.SALDO POR VALORIZARPRESUPUESTO

    BASE

    ACUMULADO ANTERIOR ACTUAL ACUMULADO ACTUALUND. METRADODESCRIPCION DE PARTIDA