Acometida Media Tension

7
CAMARA 1 TIEMPO TAREA % AVA 1 MOLDAJE EXTERIOR 6% 1 ENFIERRADURA 6% 2 HORMIGONADO LOZA 13 1 MOLDAJE INTERIOR 6% 3 HORMIGONADO TOTAL 19 3 CONFECCION LOZA SUPERIOR 19 5 CONFECCION DE ACCESO 31 TOTAL 16 TOTAL DE AVANCES 100 TOTAL DE AVANCE REAL 13 TOTAL FALTANTE 88 DIAS FALTANTES 14 CAMARA 1 13% SUMA DIAS CAMARA 2 6% CAMARA 3 0% TOTAL 6%

description

construccion e instalacion de camaras de media tencion

Transcript of Acometida Media Tension

Page 1: Acometida Media Tension

CAMARA 1

TIEMPO TAREA % AVANCE1 MOLDAJE EXTERIOR 6%1 ENFIERRADURA 6%2 HORMIGONADO LOZA 13%1 MOLDAJE INTERIOR 6%3 HORMIGONADO TOTAL 19%3 CONFECCION LOZA SUPERIOR 19%5 CONFECCION DE ACCESO 31%

TOTAL 16 TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 13%

TOTAL FALTANTE 88%DIAS FALTANTES 14

CAMARA 1 13% SUMA DIAS FALTANTESCAMARA 2 6%CAMARA 3 0%

TOTAL 6%

Page 2: Acometida Media Tension

CAMARA 1

PORCENTAJE DE AVANCE TOTAL POR TAREA

100% 6%100% 6%

0% 0%0% 0%0% 0%0% 0%0% 0%

TOTAL

45

Page 3: Acometida Media Tension

CAMARA 2

TIEMPO TAREA % AVANCE1 MOLDAJE EXTERIOR 6% 0%1 ENFIERRADURA 6% 100%2 HORMIGONADO LOZA 13% 0%1 MOLDAJE INTERIOR 6% 0%3 HORMIGONADO TOTAL 19% 0%3 CONFECCION LOZA SUPERIOR 19% 0%5 CONFECCION DE ACCESO 31% 0%

16 TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 6%

TOTAL FALTANTE 94%DIAS FALTANTES 15

Page 4: Acometida Media Tension

CAMARA 2

PORCENTAJE DE AVANCE TOTAL POR TAREA TIEMPO0% 0% 1

100% 6% 10% 0% 20% 0% 10% 0% 30% 0% 30% 0% 5

TOTAL 16

Page 5: Acometida Media Tension

CAMARA 3

TAREA % AVANCEMOLDAJE EXTERIOR 6% 0%

ENFIERRADURA 6% 0%HORMIGONADO LOZA 13% 0%

MOLDAJE INTERIOR 6% 0%HORMIGONADO TOTAL 19% 0%

CONFECCION LOZA SUPERIOR 19% 0%CONFECCION DE ACCESO 31% 0%

TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 0%

TOTAL FALTANTE 100%DIAS FALTANTES 16

Page 6: Acometida Media Tension

PORCENTAJE DE AVANCE TOTAL POR TAREA

0%0%0%0%0%0%0%