ANALISIS DE COSTO UNITARIO PROYECTO: EXAMEN PARCIAL DESCRIPCION: SOLADO DE 2" MEZCLA 1:12 CEMENTO HORMIGON RENDIMIENTO EN 8 HRS: 100 m2 APORTE: 12.5000 h/m2 MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL CAPATAZ hh 0.0160 18.14 0.29 OPERARIO hh 0.1600 15.12 2.42 OFICIAL hh 0.0800 13.14 1.05 PEON hh 0.6400 11.84 7.58 OPERADOR EQUIPO hh 0.0800 17.39 1.39 TOTAL 12.73 MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL HORMIGON m3 0.6500 22.50 14.63 CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 0.1515 14.45 2.19 AGUA m3 0.0081 5.70 0.05 TOTAL 16.86 COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.0300 11.70 0.35 ACEITE MOTOR GASOLINA SAE 30W gal 0.0010 57.00 0.06 GRASA MULTIPLE EP lb 0.0020 5.65 0.01 TOTAL 0.42 EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0800 30.50 30.50 HERRAMIENTA MANUAL % MO 0.0500 12.73 0.64 TOTAL 31.14 TOTAL P.U. 61.15

Transcript of ANALISIS DE COSTO UNITARIO.pdf

Page 1: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SOLADO DE 2" MEZCLA 1:12 CEMENTO

HORMIGON

RENDIMIENTO EN 8 HRS: 100 m2

APORTE: 12.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0160 18.14 0.29

OPERARIO hh 0.1600 15.12 2.42

OFICIAL hh 0.0800 13.14 1.05

PEON hh 0.6400 11.84 7.58

OPERADOR EQUIPO hh 0.0800 17.39 1.39

TOTAL 12.73

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

HORMIGON m3 0.6500 22.50 14.63

CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 0.1515 14.45 2.19

AGUA m3 0.0081 5.70 0.05

TOTAL 16.86

COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL

GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.0300 11.70 0.35

ACEITE MOTOR GASOLINA SAE 30W gal 0.0010 57.00 0.06

GRASA MULTIPLE EP lb 0.0020 5.65 0.01

TOTAL 0.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0800 30.50 30.50

HERRAMIENTA MANUAL % MO 0.0500 12.73 0.64

TOTAL 31.14

TOTAL P.U. 61.15

Page 2: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PREMEZCLADO F'c=100 Kg/cm2 PARA

CIMIENTOS

RENDIMIENTO EN 8 HRS: 25.00 m3

APORTE: 3.1250 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0320 18.14 0.58

OPERARIO hh 0.6400 15.12 9.68

OFICIAL hh 0.3200 13.14 4.20

PEON hh 1.2800 11.84 15.16

OPERADOR EQUIPO LIVIANO hh 0.3200 16.33 5.23

TOTAL 34.84

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO PREMEZCLADO TIPO I F´C=100Kg/cm2 m3 1.0300 185.00 190.55

TOTAL 190.55

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.3200 5.53 1.77

HERRAMIENTA MANUAL % MO 0.0300 34.84 1.05

TOTAL 2.81

TOTAL P.U. 228.21

Page 3: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ENCOF. Y DESENCOF. PARA SOBRECIMIENTOS

RENDIMIENTO EN 8 HRS: 16.00 m2

APORTE: 2.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0500 18.14 0.91

OPERARIO hh 0.5000 15.12 7.56

OFICIAL hh 0.5000 13.14 6.57

TOTAL 15.04

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO RECOCIDO BWG N 8 KG 0.2600 2.96 0.77

CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.1600 3.02 0.48

MADERA TORNILLO p2 3.3500 5.40 18.09

TOTAL 19.34

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0300 15.04 0.90

TOTAL 0.90

TOTAL P.U. 35.28

Page 4: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO EN FALSOPISO MEZCLA 1:8 E=4"

RENDIMIENTO EN 8 HRS: 110 m2

APORTE: 13.7500 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0218 18.14 0.40

OPERARIO hh 0.2182 15.12 3.30

PEON hh 0.5818 11.84 6.89

OPERADOR EQUIPO hh 0.0727 17.39 1.26

TOTAL 11.85

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

HORMIGON m3 0.1450 22.50 3.26

REGLA DE MADERA p2 0.0600 5.20 0.31

AGUA m3 0.0160 5.70 0.09

TOTAL 3.67

COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL

GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.0273 11.70 0.32

ACEITE MOTOR GASOLINA SAE 30W gal 0.0009 57.00 0.05

GRASA MULTIPLE EP lb 0.0018 5.65 0.01

TOTAL 0.38

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0727 30.50 30.49

HERRAMIENTA MANUAL % MO 0.0300 11.85 4.89

TOTAL 35.38

TOTAL P.U. 51.27

Page 5: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: EXCAVACION DE ZANJAS

RENDIMIENTO EN 8 HRS: 4.00 m3

APORTE: 0.5000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.2000 18.14 3.63

OPERARIO hh 2.0000 15.12 30.24

TOTAL 33.87

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0500 33.87 1.69

TOTAL 1.69

TOTAL P.U. 35.56

Page 6: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CORTE MANUAL DE TERRENO

RENDIMIENTO EN 8 HRS: 40.00 m2

APORTE: 5.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.2000 18.14 3.63

OPERARIO hh 0.2000 15.12 3.02

TOTAL 6.65

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0500 6.65 0.33

TOTAL 0.33

TOTAL P.U. 6.98

Page 7: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ELIMINACION DESMONTE CON EQUIPO

RENDIMIENTO EN 8 HRS: 345.00 m3

APORTE: 43.1250 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0023 18.14 0.04

PEON hh 0.0464 11.84 0.55

TOTAL 0.59

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CAMION VOLQUETE 4 X 2 140-210 HP 6 M3 hm 0.0928 195.15 18.11

CARGADOR S/LLANTA 125 HP, 2.5 Y3 hm 0.0232 153.62 3.56

TOTAL 21.67

TOTAL P.U. 22.27

Page 8: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: RELLENO CON MATERIAL PROPIO

RENDIMIENTO EN 8 HRS: 7.00 m3

APORTE: 0.8750 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.1143 18.14 2.07

PEON hh 1.1429 11.84 13.53

TOTAL 15.61

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0500 15.61 0.78

TOTAL 0.78

TOTAL P.U. 16.39

Page 9: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TRAZO Y REPLANTEO

RENDIMIENTO EN 8 HRS: 300.00 m2

APORTE: 37.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0027 18.14 0.05

OPERARIO hh 0.0267 15.12 0.40

PEON hh 0.0533 11.84 0.63

TOTAL 1.08

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

YESO EN BOLSA DE 20 KG bls 0.0250 30.52 0.76

CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.0050 3.02 0.02

MADERA TORNILLO P2 0.0264 5.40 0.14

TOTAL 0.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CORDEL ROLLO DE 50m pza 0.0001 13.5 0.00

WINCHA DE 30m pza 0.0005 44.80 0.02

HERRAMIENTA MANUAL % MO 0.0300 1.08 0.03

TOTAL 0.06

TOTAL P.U. 2.06

Page 10: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TRAZO DE NIVELES Y REPLANTEO DURANTE EL

PROCESO

RENDIMIENTO EN 8 HRS: 300.00 m2

APORTE: 37.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0027 18.14 0.05

OPERARIO hh 0.0267 15.12 0.40

PEON hh 0.0533 11.84 0.63

TOTAL 1.08

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

YESO EN BOLSA DE 20 KG bls 0.0250 30.52 0.76

CLAVO C/CABEZA P/CONSTRUCCION D. PROMEDIO KG 0.0050 3.02 0.02

TOTAL 0.78

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CORDEL ROLLO DE 50m pza 0.0001 13.5 0.00

WINCHA DE 30m pza 0.0005 44.80 0.02

HERRAMIENTA MANUAL % MO 0.0300 1.08 0.03

TOTAL 0.06

TOTAL P.U. 1.92

Page 11: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ZOCALO DE CERAMICO 20X20

RENDIMIENTO EN 8 HRS: 4.00 m2

APORTE: 0.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 0.660000 11.84 7.81

TOTAL 41.68

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ARENA GRUESA m3 0.025000 35.00 0.88

FRAGUA BLANCA kg 0.200000 8.00 1.60

CERAMICO 20x20 m2 1.050000 19.95 20.95

TOTAL 23.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0500 41.68 2.08

TOTAL 2.08

TOTAL P.U. 67.19

Page 12: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ZOCALO DE CEMENTO SIMPLE MEZCLA CEMENTO-

ARENA

RENDIMIENTO EN 8 HRS: 14.00 m2

APORTE: 1.7500 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.057100 18.14 1.04

OPERARIO hh 0.571400 15.12 8.64

PEON hh 0.382900 11.84 4.53

TOTAL 14.21

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ARENA FINA m3 0.021000 35.00 0.74

CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 0.186900 14.45 2.70

CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO kg 0.030000 3.02 0.09

MADERA ANDAMIAJE p2 0.520000 5.40 2.81

AGUA m3 0.005600 5.70 0.03

TOTAL 6.37

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 14.21 0.43

TOTAL 0.43

TOTAL P.U. 21.00

Page 13: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PUERTA POSTERIOR CONTRAPLACADA DE 0.65 M DE

ANCHO

RENDIMIENTO EN 8 HRS: 3.00 m2

APORTE: 0.3750 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.666700 18.14 12.09

OPERARIO hh 2.666700 15.12 40.32

OFICIAL hh 2.666700 13.14 35.04

TOTAL 87.45

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.066900 3.02 0.20

MADERA CEDRO p2 10.290000 8.60 88.49

TRIPLAY LUPUNA 4X 8 X 6mm pza 1.000000 33.00 33.00

LIJA P/MADERA hja 1.100000 1.00 1.10

COLA SINTETICA gal 0.102800 22.70 2.33

TOTAL 125.13

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CEPILLADORA ELECTRICA hm 0.533300 4.29 6.86

SIERRA CIRCULAR hm 0.533300 3.91 0.78

HERRAMIENTA MANUAL % MO 0.030000 87.45 0.98

TOTAL 8.63

TOTAL P.U. 221.21

Page 14: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PUERTAS CONTRAPLACADAS DE 0.65 M DE ANCHO

RENDIMIENTO EN 8 HRS: 3.00 m2

APORTE: 0.3750 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.666700 18.14 12.09

OPERARIO hh 2.666700 15.12 40.32

OFICIAL hh 2.666700 13.14 35.04

TOTAL 87.45

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.066900 3.02 0.20

MADERA CEDRO p2 10.290000 8.60 88.49

TRIPLAY LUPUNA 4X 8 X 4mm pza 1.000000 21.75 21.75

LIJA P/MADERA hja 1.100000 1.00 1.10

COLA SINTETICA gal 0.102800 22.70 2.33

TOTAL 113.88

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CEPILLADORA ELECTRICA hm 0.533300 4.29 2.29

SIERRA CIRCULAR hm 0.533300 3.91 2.09

HERRAMIENTA MANUAL % MO 0.030000 87.45 2.62

TOTAL 7.00

TOTAL P.U. 208.33

Page 15: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP

RENDIMIENTO EN 8 HRS: 25.00 pza

APORTE: 3.1250 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.032000 18.14 0.58

OPERARIO hh 0.320000 15.12 4.84

OFICIAL hh 0.320000 13.14 4.20

TOTAL 9.62

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37

TUBO PVC AGUA S.P CLASE 10 ½" X 5m pza 0.210000 6.19 1.30

TOTAL 2.67

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 9.62 0.29

TOTAL 0.29

TOTAL P.U. 12.58

Page 16: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE AGUA FRIA DE 1/2"

RENDIMIENTO EN 8 HRS: 3.00 Pto

APORTE: 0.3750 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.266700 18.14 4.84

OPERARIO hh 2.666700 15.12 40.32

OFICIAL hh 1.333333 13.14 17.52

TOTAL 62.68

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.030000 139.92 4.20

TUBO PVC AGUA S.P CLASE 10 ½" X 5m pza 0.412000 6.19 2.55

CODO PVC AGUA DOBLE CAMPAÑA S.P. ½" X 90˚ pza 2.000000 0.96 1.92

TEE PVC AGUA S.P. ½" pza 1.000000 1.23 1.23

TOTAL 9.90

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 62.68 1.88

TOTAL 1.88

TOTAL P.U. 74.46

Page 17: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: VALVULAS DE COMPUERTA DE BRONCE DE

1/2"

RENDIMIENTO EN 8 HRS: 6.00 pza

APORTE: 0.7500 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.133300 18.14 2.42

OPERARIO hh 1.333300 15.12 20.16

OFICIAL hh 0.666700 13.14 8.76

TOTAL 31.34

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CINTA TEFLON pza 0.100000 1.16 0.12

UNION UNIVERSAL ACERO GALV. ½" pza 2.000000 7.64 15.28

NIPLE ACERO GALV. TIPO ISO -½" X 1¼" pza 2.000000 1.40 2.80

VALVULA COMPUERTA PESADA BRONCE 250 LB ½" pza 1.000000 22.76 22.76

TOTAL 40.96

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 31.34 0.71

TOTAL 0.71

TOTAL P.U. 73.00

Page 18: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: RED DE DESAGUE DE 4" EN PVC

RENDIMIENTO EN 8 HRS: 20.00 m

APORTE: 2.5000 h/m

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.040000 18.14 0.73

OPERARIO hh 0.400000 15.12 6.05

PEON hh 0.800000 11.86 9.49

TOTAL 16.26

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37

TUBO PVC DESAGUE SAL 4" X 3m pza 0.350000 19.11 6.69

TOTAL 8.06

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49

TOTAL 0.49

TOTAL P.U. 24.81

Page 19: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TUBERIA DE DESAGUE PVC SAL DE 2" PARA VENTILACION

RENDIMIENTO EN 8 HRS: 20.00 m

APORTE: 2.5000 h/m

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.040000 18.14 0.73

OPERARIO hh 0.400000 15.12 6.05

PEON hh 0.800000 11.86 9.49

TOTAL 16.26

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37

TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62

TOTAL 3.99

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49

TOTAL 0.49

TOTAL P.U. 20.74

Page 20: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: RED DE DESAGUE DE 2" EN PVC

RENDIMIENTO EN 8 HRS: 20.00 m

APORTE: 2.5000 h/m

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.040000 18.14 0.73

OPERARIO hh 0.400000 15.12 6.05

PEON hh 0.800000 11.86 9.49

TOTAL 16.26

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.010000 137.10 1.37

TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62

TOTAL 3.99

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 16.26 0.49

TOTAL 0.49

TOTAL P.U. 20.74

Page 21: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE DESAGUE DE 4"

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.86 23.72

TOTAL 57.59

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.030000 137.10 4.11

TUBO PVC DESAGUE SAL 4" X 3m pza 0.350000 19.11 6.69

CODO PVC DESAGUE SAL 4" X 90" pza 1.030000 5.33 5.49

TRAMPA P PVC DESAGUE SAL 4" pza 1.030000 34.21 35.24

YEE PVC DESAGUE SAL 4" pza 1.030000 8.61 8.87

TOTAL 60.40

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73

TOTAL 1.73

TOTAL P.U. 119.71

Page 22: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE DESAGUE DE 2"

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.86 23.72

TOTAL 57.59

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PEGAMENTO P/TUBO PVC gal 0.030000 137.10 4.11

TUBO PVC DESAGUE SAL 2" X 3m pza 0.350000 7.48 2.62

CODO PVC DESAGUE SAL 2" X 90" pza 1.030000 1.31 1.35

TRAMPA P PVC DESAGUE SAL 2" pza 1.030000 5.80 5.97

YEE PVC DESAGUE SAL 2" pza 1.030000 2.44 2.51

TOTAL 16.57

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73

TOTAL 1.73

TOTAL P.U. 75.88

Page 23: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CAJA DE REGISTRO DE ALBAÑILERIA DE 10" X

20"

RENDIMIENTO EN 8 HRS: 4.00 pza

APORTE: 0.5000 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.86 23.72

TOTAL 57.59

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ARENA FINA m3 0.030000 38.00 1.14

ARENA GRUESA m3 0.060000 35.00 2.10

PIEDRA CHANCADA DE ½" - ¾" HUSO 67 m3 0.250000 41.00 10.25

CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 1.500000 14.45 21.68

ACERO LISO GDO. 60 PRECIO PROM. P/Kg kg 10.000000 4.35 43.50

CLAVO C/CABEZA P/CONSTRUCCION DE PROMEDIO kg 0.860000 3.02 2.60

LADRILLO ARCILLA KING KONG 18 HUECOS mll 0.035000 571.43 20.00

AGUA m3 0.010000 5.70 0.06

TOTAL 101.32

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.59 1.73

TOTAL 1.73

TOTAL P.U. 160.63

Page 24: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: REGISTRO ROSCADO DE BRONCE DE 2"

RENDIMIENTO EN 8 HRS: 8.00 pza

APORTE: 1.0000 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.100000 18.14 1.81

OPERARIO hh 1.000000 15.12 15.12

TOTAL 16.93

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

REGISTRO ROSCADO DE BRONCE 2" pza 1.000000 8.55 8.55

CODO PVC DESAGUE SAL 2" X 90˚ pza 1.000000 3.18 3.18

TEE SANITARIA PVC DESAGUE SAL 2" pza 1.000000 12.68 12.68

TOTAL 24.41

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 16.93 0.51

TOTAL 0.51

TOTAL P.U. 30.12

Page 25: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: REGISTRO ROSCADO DE BRONCE DE 4"

RENDIMIENTO EN 8 HRS: 6.00 pza

APORTE: 0.7500 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.133300 18.14 2.42

OPERARIO hh 1.333300 15.12 20.16

PEON hh 0.666700 11.84 7.89

TOTAL 30.47

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

REGISTRO ROSCADO DE BRONCE CROMADO 4" pza 1.000000 26.14 26.14

CODO PVC DESAGUE SAL 4" X 90˚ pza 1.000000 5.30 5.30

TEE SANITARIA PVC DESAGUE SAL 4" pza 1.000000 11.84 11.84

TOTAL 43.28

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 30.47 0.91

TOTAL 0.91

TOTAL P.U. 74.67

Page 26: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CENTRO DE LUZ

RENDIMIENTO EN 8 HRS: 5.00 pto

APORTE: 0.6250 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.160000 18.14 2.90

OPERARIO hh 1.600000 15.12 24.19

PEON hh 1.600000 11.84 18.94

TOTAL 46.04

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CABLE TW 12 AWG m 9.000000 1.29 11.61

CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 3.90 3.90

CINTA AISLANTE ELECTRICA pza 0.100000 2.45 0.25

TUBO PVC ELECTRICO SEL ¾" X 3M pza 1.500000 2.35 3.53

CONEXIÓN A CAJA PVC ELECTRICA SEL ¾" pza 1.000000 0.16 0.16

CURVA PVC ELECTRICA SEL ¾" X 45˚ pza 3.000000 0.54 1.62

UNION PVC ELECTRICA SEL ¾" pza 1.000000 0.27 0.27

TOTAL 21.33

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.050000 46.04 2.30

TOTAL 2.30

TOTAL P.U. 69.67

Page 27: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA PARA BRAQUETES

RENDIMIENTO EN 8 HRS: 4.00 pza

APORTE: 0.5000 h/pza

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 1.000000 11.84 11.84

TOTAL 45.71

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ARTFAC. ALUMB. INTERIOR BRAQUETE ECONOMICO BE. 220 AF pza 1.000000 81.97 81.97

TOTAL 81.97

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 45.71 0.69

TOTAL 0.69

TOTAL P.U. 128.36

Page 28: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA PARA TOMACORRIENTE BIPOLAR

DOBLE

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.84 23.68

TOTAL 57.55

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CABLE TW 12 AWG m 16.000000 1.29 20.64

TOMACORRIENTE DOBLE UNIVERSAL pza 1.050000 7.80 8.19

CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42

TUBO PVC ELECTRICO SEL ¾" X 3M pza 1.500000 4.89 7.34

CONEXIÓN A CAJA PVC ELECTRICA SEL ¾" pza 2.000000 0.37 0.74

CURVA PVC ELECTRICA SEL ¾" X 45˚ pza 3.000000 1.71 5.13

UNION PVC ELECTRICA SEL ¾" pza 1.000000 0.61 0.61

TOTAL 44.06

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.050000 57.55 1.44

TOTAL 1.44

TOTAL P.U. 103.05

Page 29: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE TIMBRE

RENDIMIENTO EN 8 HRS: 2.00 pto

APORTE: 0.2500 h/pto

MANO DE OBRA UNIDA

D CANTIDA

D COST

O SUBTOTA

L

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

MATERIALES UNIDA

D CANTIDA

D COST

O SUBTOTA

L

CAJA DE PASE CUADRADA F.G. 100 X 100 X 40mm pza 1.000000 4.50 4.50

TUBO PVC ELECTRICO SAP ¾" X 3M pza 6.000000 4.89 29.34

CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74

CURVA PVC ELECTRICA SAP ¾" X 90˚ pza 2.000000 1.71 3.42

UNION PVC ELECTRICA SAP ¾" pza 2.000000 0.61 1.22

TOTAL 39.22

EQUIPOS UNIDA

D CANTIDA

D COST

O SUBTOTA

L

HERRAMIENTA MANUAL % MO 0.050000 91.42 1.14

TOTAL 1.14

TOTAL P.U. 131.78

Page 30: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TABLERO DE DISTRIBUCION 24 POLOS

RENDIMIENTO EN 8 HRS: 1.00 pza

APORTE: 0.1250 h/pza

MANO DE OBRA UNIDA

D CANTIDA

D COST

O SUBTOTA

L

CAPATAZ hh 8.000000 18.14 145.12

OPERARIO hh 8.000000 15.12 120.96

PEON hh 4.000000 11.84 47.36

TOTAL 313.44

MATERIALES UNIDA

D CANTIDA

D COST

O SUBTOTA

L

TABLEROS ELECTRICO GABINETE METAL BARRA BRONCE 24 POLOS - TRIFASICO

pza 1.000000

314.00 314.00

TOTAL 314.00

EQUIPOS UNIDA

D CANTIDA

D COST

O SUBTOTA

L

HERRAMIENTA MANUAL % MO

0.050000 313.4

4 15.67

TOTAL 15.67

TOTAL P.U. 643.11

Page 31: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS

RENDIMIENTO EN 8 HRS: 11.00 m2

APORTE: 1.3750 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.110000 18.14 2.00

OPERARIO hh 1.090000 15.12 16.48

OFICIAL hh 1.310000 13.14 17.21

PEON hh 0.440000 11.84 5.21

TOTAL 40.90

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

MADERA TONILLO pza 6.710000 5.40 36.23

CLAVOS DE 3¨ kg 0.240000 3.02 0.72

ALAMBRE Nº 8 kg 0.210000 2.96 0.62

TOTAL 37.58

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 40.90 1.23

TOTAL 1.23

TOTAL P.U. 79.71

Page 32: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PREMEZCLADO F'c = 175 Kg/CM2

RENDIMIENTO EN 8 HRS: 100.00 m3

APORTE: 12.5000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.081000 18.14 1.47

OPERARIO hh 0.320000 15.12 4.84

PEON hh 0.720000 13.14 9.46

OPERADOR DE EQUIPO LIVIANO hh 0.160000 17.39 2.78

TOTAL 18.55

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO PREMEZCLADO F'c = 175 Kg/CM2 m3 1.000000 208.80 208.80

TOTAL 208.80

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

BOMBA hm 0.080000 412.8 33.02

VIBRADORES DE 2" hm 0.160000 5.53 0.88

HERRAMIENTA MANUAL % MO 0.030000 18.55 0.56

TOTAL 34.47

TOTAL P.U. 261.82

Page 33: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACARREO DE MATERIAL EXCEDENTE

RENDIMIENTO EN 8 HRS: 6.00 m3

APORTE: 0.7500 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.130000 18.14 2.36

PEON hh 1.330000 11.84 15.75

TOTAL 18.11

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 18.11 0.54

TOTAL 0.54

TOTAL P.U. 18.65

Page 34: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ENCOFRADO Y DESENCOFRADO

RENDIMIENTO EN 8 HRS: 14.00 m2

APORTE: 1.7500 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.080000 18.14 1.45

OPERARIO hh 0.770000 15.12 11.64

OFICIAL hh 0.990000 13.14 13.01

PEON hh 0.990000 11.84 11.72

TOTAL 37.82

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

MADERA TONILLO p2 5.150000 5.40 27.81

CLAVOS DE 2 ½ kg 0.110000 3.02 0.33

ALAMBRE NEGRO Nº 16 kg 0.100000 2.96 0.30

TOTAL 28.44

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 37.82 1.13

TOTAL 1.13

TOTAL P.U. 67.40

Page 35: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ENCOFRADO Y DESENCOF. NORMAL EN LOSAS MACIZAS

RENDIMIENTO EN 8 HRS: 17.00 m2

APORTE: 2.1250 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.070000 18.14 1.27

OPERARIO hh 0.670000 15.12 10.13

OFICIAL hh 0.850000 13.14 11.17

PEON hh 0.360000 11.84 4.26

TOTAL 26.83

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

MADERA TONILLO p2 5.930000 5.40 32.02

CLAVOS DE 2 ½ kg 0.140000 3.02 0.42

ALAMBRE NEGRO Nº 16 kg 0.100000 2.96 0.30

TOTAL 32.74

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 26.83 0.80

TOTAL 0.80

TOTAL P.U. 60.38

Page 36: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 175 KG/CM2

RENDIMIENTO EN 8 HRS: 10.00 m3

APORTE: 1.2500 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.230000 18.14 4.17

OPERARIO hh 2.000000 15.12 30.24

OFICIAL hh 2.000000 13.14 26.28

PEON hh 10.270000 11.84 121.60

OPERADOR EQUIPO LIVIANO hh 3.000000 17.35 52.05

TOTAL 234.34

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 8.430000 14.45 121.81

ARENA GRUESA m3 0.540000 35.00 18.90

PIEDRA CHANCADA ½" m3 0.550000 41.00 22.55

TOTAL 163.26

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE 9-11 P3 hm 1.000000 30.5 30.50

VIBRADOR DE 2.0" 4HP hm 1.000000 5.53 5.53

WINCHE ELECTRICO hm 1.000000 5.53 5.53

HERRAMIENTA MANUAL % MO 0.030000 234.34 7.03

TOTAL 48.59

TOTAL P.U. 446.19

Page 37: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO EN MUROS F'c=175 KG/m2 , CON 10 CM

RENDIMIENTO EN 8 HRS: 27.00 m3

APORTE: 3.3750 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.120000 18.14 2.18

OPERARIO hh 0.960000 15.12 14.52

OFICIAL hh 0.640000 13.14 8.41

PEON hh 3.680000 11.84 43.57

OPERADOR EQUIPO LIVIANO hh 0.960000 17.35 16.66

TOTAL 85.33

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 8.430000 14.45 121.81

ARENA GRUESA m3 0.540000 35.00 18.90

PIEDRA CHANCADA ½" m3 0.550000 41.00 22.55

TOTAL 163.26

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE 9-11 P3 hm 0.320000 30.5 9.76

VIBRADOR DE 2.0" 4HP hm 0.320000 5.53 1.77

WINCHE ELECTRICO DE 2 TAMBORES hm 0.320000 5.53 1.77

HERRAMIENTA MANUAL % MO 0.300000 85.33 25.60

TOTAL 38.90

TOTAL P.U. 287.49

Page 38: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: MURO CON LADRILLO PANDERETA DE CUELLO

RENDIMIENTO EN 8 HRS: 9.00 m2

APORTE: 1.1250 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.112000 18.14 2.03

OPERARIO hh 1.120000 15.12 16.93

PEON hh 0.784000 11.84 9.28

TOTAL 28.25

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.124000 14.45 1.79

ARENA GRUESA m3 0.018000 35.00 0.63

CLAVOS DE 3" kg 0.022000 3.02 0.07

LADRILLO PANDERETA pz 30.000000 0.56 16.80

TOTAL 19.29

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

ANDAMIO DE MADERA P2 0.580000 5.4 3.13

HERRAMIENTA MANUAL % MO 0.030000 28.25 0.85

TOTAL 3.98

TOTAL P.U. 51.52

Page 39: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: MURO DE LADRILLO PANDERETA DE SOGA

RENDIMIENTO EN 8 HRS: 12.00 m2

APORTE: 1.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.073000 18.14 1.32

OPERARIO hh 1.734000 15.12 26.22

PEON hh 0.631000 11.84 7.47

TOTAL 35.01

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.163000 14.45 2.36

ARENA GRUESA m3 0.023000 35.00 0.81

CLAVOS DE 3" kg 0.022000 3.02 0.07

LADRILLO PANDERETA pz 35.000000 0.56 19.60

TOTAL 22.83

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

ANDAMIO DE MADERA P2 0.580000 5.4 3.13

HERRAMIENTA MANUAL % MO 0.030000 35.01 1.05

TOTAL 4.18

TOTAL P.U. 62.02

Page 40: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TARRAJEO PRIMARIO O RAYADO

RENDIMIENTO EN 8 HRS: 17.00 m2

APORTE: 2.1250 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.057000 18.14 1.03

OPERARIO hh 0.571000 15.12 8.63

PEON hh 0.286000 11.84 3.39

TOTAL 13.05

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.117000 14.45 1.69

CLAVOS DE 3" kg 0.022000 3.02 0.07

ARENA FINA m3 0.016000 38.00 0.61

TOTAL 2.37

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

ANDAMIO DE MADERA P2 0.580000 5.4 3.13

REGLA DE MADERA P2 0.025000 5.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 13.05 0.39

TOTAL 3.65

TOTAL P.U. 19.07

Page 41: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: TARRAJEO EN INTERIORES

RENDIMIENTO EN 8 HRS: 34.00 m2

APORTE: 4.2500 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.063000 18.14 1.14

OPERARIO hh 0.635000 15.12 9.60

PEON hh 0.278000 11.84 3.29

TOTAL 14.04

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.117000 14.45 1.69

CLAVOS DE 3" kg 0.022000 3.02 0.07

ARENA FINA m3 0.016000 38.00 0.61

TOTAL 2.37

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

ANDAMIO DE MADERA P2 0.580000 5.4 3.13

REGLA DE MADERA P2 0.025000 5.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 14.04 0.42

TOTAL 3.68

TOTAL P.U. 20.08

Page 42: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONTRAZOCALO CEMENTO H = 20 cm PULIDO

RENDIMIENTO EN 8 HRS: 22.00 ml

APORTE: 2.7500 h/ml

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 0.400000 15.12 6.05

PEON hh 0.132000 11.84 1.56

TOTAL 14.87

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.031000 14.45 0.45

ARENA FINA m3 0.004000 38.00 0.15

TOTAL 0.60

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 14.87 0.45

TOTAL 0.45

TOTAL P.U. 15.91

Page 43: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: COLOCACION INODORO

RENDIMIENTO EN 8 HRS: 4.00 pz

APORTE: 0.5000 h/pz

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74

TOTAL 2.74

TOTAL P.U. 94.16

Page 44: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: RELLENO COMPACTADO CON MATERIAL DE PRESTAMO

RENDIMIENTO EN 8 HRS: 7.00 m3

APORTE: 0.8750 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.110000 18.14 2.00

PEON hh 1.140000 11.84 13.50

TOTAL 15.49

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

MATERIAL PARA RELLENO m3 1.300000 30.00 39.00

TOTAL 39.00

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 15.49 0.46

TOTAL 0.46

TOTAL P.U. 54.96

Page 45: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: NIVELACION INTERIOR Y COMPACTACION

RENDIMIENTO EN 8 HRS: 120.00 m2

APORTE: 15.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.007000 18.14 0.13

OPERARIO hh 0.067000 15.12 1.01

PEON hh 0.067000 11.84 0.79

TOTAL 1.93

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CLAVOS DE 3" kg 0.010000 3.02 0.03

TOTAL 0.03

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

REGLA DE MADERA P2 0.030000 5.2 0.16

HERRAMIENTA MANUAL % MO 0.030000 1.93 0.06

TOTAL 0.21

TOTAL P.U. 2.18

Page 46: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO EN SOBRECIMIENTO REFORZADO GRADO 60

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 47: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 48: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO GRADO 60 EN VIGAS

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 49: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO GRADO 60 EN LOSAS ALIGERADAS

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 50: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO GRADO 60 EN LOSAS MACIZAS

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 51: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ACERO EN MURO DE ALBANILERIA ARMADA

RENDIMIENTO EN 8 HRS: 280.00 kg

APORTE: 35.0000 h/kg

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.004000 18.14 0.07

OPERARIO hh 0.032000 15.12 0.48

OFICIAL hh 0.032000 13.14 0.42

TOTAL 0.98

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE NEGRO Nº 16 kg 0.060000 2.96 0.18

FIERRO CORRUGADO kg 1.070000 3.50 3.75

TOTAL 3.92

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CIZALLA hm 0.032000 4.2 0.13

HERRAMIENTA MANUAL % MO 0.030000 0.98 0.03

TOTAL 0.16

TOTAL P.U. 5.06

Page 52: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: ENCOF. Y DESENCOF. EN MUROS TABIQUES Y PLACAS

RENDIMIENTO EN 8 HRS: 12.00 m2

APORTE: 1.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.100000 18.14 1.81

OPERARIO hh 1.000000 15.12 15.12

OFICIAL hh 1.200000 13.14 15.77

PEON hh 0.400000 11.84 4.74

TOTAL 37.44

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

MADERA TORNILLO P2 5.160000 5.4 27.86

ALAMBRE NEGRO Nº 8 kg 0.300000 2.96 0.89

CLAVO 3" kg 0.170000 3.02 0.51

TOTAL 29.27

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 37.44 1.12

TOTAL 1.12

TOTAL P.U. 67.83

Page 53: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: MURO DE LADRILLO DE SOGA KING KONG

RENDIMIENTO EN 8 HRS: 12.00 m2

APORTE: 1.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.085000 18.14 1.54

OPERARIO hh 0.846000 15.12 12.79

PEON hh 0.719000 11.84 8.51

TOTAL 22.85

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.218000 14.45 3.15

ARENA GRUESA m3 0.031000 35.00 1.09

CLAVOS DE 3" kg 0.022000 3.02 0.07

LADRILLO KIN KONG 18 HUECOS mll 0.050000 571.43 28.57

TOTAL 32.87

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

ANDAMIO DE MADERA P2 0.580000 5.4 3.13

HERRAMIENTA MANUAL % MO 0.030000 22.85 0.69

TOTAL 3.82

TOTAL P.U. 59.54

Page 54: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: FALSO CIMIENTO

RENDIMIENTO EN 8 HRS: 25.00 m3

APORTE: 3.1250 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0640 18.14 1.16

OPERARIO hh 0.6400 15.12 9.68

OFICIAL hh 0.3200 13.14 4.20

PEON hh 2.5600 11.84 30.31

OPERADOR EQUIPO hh 0.3200 17.35 5.55

TOTAL 50.90

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

PIEDRA GRANDE m3 0.5200 30.00 15.60

HORMIGON m3 0.7800 22.50 17.55

AGUA m3 0.1620 5.70 0.92

CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 2.9000 14.45 41.91

TOTAL 75.98

COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL

GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.1200 11.70 1.40

ACEITE MOTOR GASOLINA SAE 30W gal 0.0040 57.00 0.23

GRASA MULTIPLE EP lb 0.0080 5.80 0.05

TOTAL 1.68

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.3200 30.5 9.76

HERRAMIENTA MANUAL % MO 0.030000 50.90 1.53

TOTAL 11.29

TOTAL P.U. 139.85

Page 55: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PREMEZCLADO F'c=100

SOBRECIMIENTOS

RENDIMIENTO EN 8 HRS: 60.00 m3

APORTE: 7.5000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0133 18.14 0.24

OPERARIO hh 0.2667 15.12 4.03

OFICIAL hh 0.1333 13.14 1.75

PEON hh 0.5333 11.84 6.31

OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31

TOTAL 14.65

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO PREMEZCLADO TIPO I F´C=100Kg/cm2 m3 1.0300 185.00 190.55

TOTAL 190.55

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72

HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44

TOTAL 1.16

TOTAL P.U. 206.36

Page 56: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PARA VIGAS DE F'c= 280 KG/m2

RENDIMIENTO EN 8 HRS: 25.00 m3

APORTE: 3.1250 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0640 18.14 1.16

OPERARIO hh 0.6400 15.12 9.68

OFICIAL hh 0.3200 13.14 4.20

PEON hh 2.5600 11.84 30.31

OPERADOR EQUIPO hh 0.6400 17.35 11.10

TOTAL 56.46

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ARENA GRUESA m3 0.5000 35 17.50

PIEDRA CHANCADA DE ½" - ¾" HUSO 67 m3 0.8000 41 32.80

CEMENTO PORTLAND TIPO I (BLS.:42.5 KG) bls 8.4000 14.45 121.38

AGUA m3 0.1800 0.00

TOTAL 171.68

COMB. Y LUB. UNIDAD CANTIDAD COSTO SUBTOTAL

GASOLINA 84 OCTANOS (GRIFO LIMA) gal 0.1200 11.70 1.40

ACEITE MOTOR GASOLINA SAE 30W gal 0.0040 57.00 0.23

GRASA MULTIPLE EP lb 0.0080 5.80 0.05

TOTAL 1.68

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.3200 30.5 9.76

VIBRADOR DE CONCRETO 4HP 2.40 plg hm 0.3200 5.38 1.72

HERRAMIENTA MANUAL % MO 0.0500 56.46 2.82

TOTAL 14.30

TOTAL P.U. 244.12

Page 57: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PREMEZCLADO F'c = 175 Kg/CM2

RENDIMIENTO EN 8 HRS: 60.00 m3

APORTE: 7.5000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0133 18.14 0.24

OPERARIO hh 0.2667 15.12 4.03

OFICIAL hh 0.1333 13.14 1.75

PEON hh 0.5333 11.84 6.31

OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31

TOTAL 14.65

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO PREMEZCLADO TIPO I F´C=175Kg/cm2 m3 1.0200 208.8 212.98

TOTAL 212.98

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72

HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44

TOTAL 1.16

TOTAL P.U. 228.79

Page 58: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO PREMEZCLADO F'C=175 kg/cm2 LOSA

MASIZA

RENDIMIENTO EN 8 HRS: 100.00 m3

APORTE: 12.5000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0133 18.14 0.24

OPERARIO hh 0.2667 15.12 4.03

OFICIAL hh 0.1333 13.14 1.75

PEON hh 0.5333 11.84 6.31

OPERADOR EQUIPO LIVIANO hh 0.1333 17.35 2.31

TOTAL 14.65

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO PREMEZCLADO TIPO I F´C=175Kg/cm2 m3 1.0200 208.8 212.98

TOTAL 212.98

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

VIBRADOR DE CONCRETO 4HP 1.50 plg hm 0.1333 5.38 0.72

HERRAMIENTA MANUAL % MO 0.0300 14.65 0.44

TOTAL 1.16

TOTAL P.U. 228.79

Page 59: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: COLOCACION LAVATORIO DE PARED BLANCO

RENDIMIENTO EN 8 HRS: 4.00 pz

APORTE: 0.5000 h/pz

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74

TOTAL 2.74

TOTAL P.U. 94.16

Page 60: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: COLOCACION DE LAVADERO DE ACERO INOXIDABLE

RENDIMIENTO EN 8 HRS: 4.00 pz

APORTE: 0.5000 h/pz

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74

TOTAL 2.74

TOTAL P.U. 94.16

Page 61: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: COLOCACION LAVADERO DE GRANITO

RENDIMIENTO EN 8 HRS: 4.00 pz

APORTE: 0.5000 h/pz

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74

TOTAL 2.74

TOTAL P.U. 94.16

Page 62: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: COLOCACION DUCHA SIMPLE

RENDIMIENTO EN 8 HRS: 4.00 pz

APORTE: 0.5000 h/pz

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

PEON hh 2.000000 11.84 23.68

TOTAL 91.42

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 91.42 2.74

TOTAL 2.74

TOTAL P.U. 94.16

Page 63: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONTRAPISO DE 50 mm

RENDIMIENTO EN 8 HRS: 80.00 m2

APORTE: 10.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.030000 18.14 0.54

OPERARIO hh 0.300000 15.12 4.54

OFICIAL hh 0.100000 13.14 1.31

PEON hh 0.600000 11.84 7.10

OPERADOR EQUIPO LIVIANO hh 0.1000 17.35 1.74

TOTAL 15.23

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.1000 30.5 3.05

REGLA DE MADERA P2 0.060000 5.2 0.31

HERRAMIENTA MANUAL % MO 0.030000 15.23 0.46

TOTAL 3.82

TOTAL P.U. 19.05

Page 64: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONTRAPISO DE 35 mm

RENDIMIENTO EN 8 HRS: 100.00 m2

APORTE: 12.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.024000 18.14 0.44

OPERARIO hh 0.240000 15.12 3.63

OFICIAL hh 0.080000 13.14 1.05

PEON hh 0.480000 11.84 5.68

OPERADOR EQUIPO LIVIANO hh 0.0800 17.35 1.39

TOTAL 12.19

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0800 30.5 2.44

REGLA DE MADERA P2 0.060000 5.2 0.31

HERRAMIENTA MANUAL % MO 0.030000 12.19 0.37

TOTAL 3.12

TOTAL P.U. 15.30

Page 65: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PISO DE CEMENTO PULIDO Y BRUÑADO

RENDIMIENTO EN 8 HRS: 120.00 m2

APORTE: 15.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.032000 18.14 0.58

OPERARIO hh 0.280000 15.12 4.23

OFICIAL hh 0.670000 13.14 8.80

PEON hh 0.520000 11.84 6.16

OPERADOR EQUIPO LIVIANO hh 0.0670 17.35 1.16

TOTAL 20.94

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.450000 14.45 6.50

ARENA GRUESA m3 0.021000 35.00 0.74

PIEDRA CHANCADA ½" m3 0.027000 41.00 1.11

ARENA FINA m3 0.009000 38.00 0.34

TOTAL 8.69

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

MEZCLADORA DE CONCRETO T.TAMBOR 23HP 11 - 12P3 hm 0.0670 30.5 2.04

REGLA DE MADERA P2 0.099000 5.2 0.51

HERRAMIENTA MANUAL % MO 0.030000 20.94 0.63

TOTAL 3.19

TOTAL P.U. 32.81

Page 66: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PISO DE CERAMICO 20 x 20

RENDIMIENTO EN 8 HRS: 12.00 m2

APORTE: 1.5000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.089000 18.14 1.61

OPERARIO hh 0.088900 15.12 1.34

PEON hh 0.444000 11.84 5.26

TOTAL 8.22

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CEMENTO PORTLAND TIPO I bls 0.262000 14.45 3.79

CERAMICO 20 X 20 m2 1.050000 16.00 16.80

ARENA FINA m3 0.027000 38.00 1.03

TOTAL 21.61

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

REGLA DE MADERA P2 0.055000 5.2 0.29

HERRAMIENTA MANUAL % MO 0.030000 8.22 0.25

TOTAL 0.53

TOTAL P.U. 30.36

Page 67: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: BRUÑAS EN MUROS

RENDIMIENTO EN 8 HRS: 25.00 ml

APORTE: 3.1250 h/ml

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.030000 18.14 0.54

OPERARIO hh 0.320000 15.12 4.84

PEON hh 0.110000 11.84 1.30

TOTAL 6.69

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 6.69 0.20

TOTAL 0.20

TOTAL P.U. 6.89

Page 68: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PUERTA PRINCIPAL DE CEDRO DE 0.80 M DE

ANCHO

RENDIMIENTO EN 8 HRS: 32.00 m²

APORTE: 4.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.400000 18.14 7.26

OPERARIO hh 4.000000 15.12 60.48

OFICIAL hh 4.000000 13.14 52.56

TOTAL 120.30

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.075000 3.02 0.23

MADERA CEDRO p2 17.000000 5.40 91.80

LIJA P/MADERA hja 1.100000 1.00 1.10

COLA SINTETICA gal 0.120000 22.70 2.72

TOTAL 95.85

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CEPILLADORA hm 0.800000 4.29 3.43

SIERRA CIRCULAR hm 0.800000 3.91 3.13

HERRAMIENTA MANUAL % MO 0.050000 120.30 6.01

TOTAL 12.57

TOTAL P.U. 228.72

Page 69: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: PUERTA CORREDIZA DE 1.80 X 1.80 M

RENDIMIENTO EN 8 HRS: 32.00 m²

APORTE: 4.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.800000 18.14 14.51

OPERARIO hh 4.000000 15.12 60.48

OFICIAL hh 2.000000 13.14 26.28

TOTAL 101.27

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CLAVO C/CABEZA P/CONSTRUCCCION D. PROMEDIO kg 0.075000 3.02 0.23

MADERA CEDRO p2 25.400000 5.40 137.16

LIJA P/MADERA hja 1.100000 1.00 1.10

COLA SINTETICA gal 0.120000 22.70 2.72

TOTAL 141.21

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

CEPILLADORA ELECTRICA hm 0.800000 4.29 3.43

SIERRA CIRCULAR hm 0.800000 3.91 3.13

HERRAMIENTA MANUAL % MO 0.030000 101.27 3.04

TOTAL 9.60

TOTAL P.U. 252.08

Page 70: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE INTERRUPTOR SIMPLE

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.84 23.68

TOTAL 57.55

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE TW 12 AWG m 8.000000 1.23 9.84

INTERRUPTOR SIMPLE pza 1.050000 5.40 5.67

CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42

CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60

CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25

TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34

CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 1.000000 0.37 0.37

CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 2.000000 1.71 3.42

UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61

TOTAL 30.51

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73

TOTAL 1.73

TOTAL P.U. 89.79

Page 71: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE INTERRUPTOR DOBLE

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.84 23.68

TOTAL 57.55

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE TW 12 AWG m 16.000000 1.23 19.68

INTERRUPTOR DOBLE pza 1.050000 5.40 5.67

CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 1.050000 1.35 1.42

CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60

CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25

TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34

CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74

CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 2.000000 1.71 3.42

UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61

TOTAL 40.72

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73

TOTAL 1.73

TOTAL P.U. 100.00

Page 72: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: SALIDA DE INTERRUPTOR DE CONMUTACION

RENDIMIENTO EN 8 HRS: 4.00 pto

APORTE: 0.5000 h/pto

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.200000 18.14 3.63

OPERARIO hh 2.000000 15.12 30.24

PEON hh 2.000000 11.84 23.68

TOTAL 57.55

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

ALAMBRE TW 12 AWG m 16.000000 1.23 19.68

INTERRUPTOR CONMUTACION pza 2.050000 5.40 11.07

CAJA DE PASE RECTANGULAR F.G. LIVIANA 50 X 100mm pza 2.050000 1.35 2.77

CAJA DE PASE OCTOGONAL F.G. LIVIANA 4" pza 1.000000 1.60 1.60

CINTA AISLANTE ELECTRICA pza 0.100000 2.50 0.25

TUBO PVC ELECTRICO SAP ¾" X 3M pza 1.500000 4.89 7.34

CONEXIÓN A CAJA PVC ELECTRICA SAP ¾" pza 2.000000 0.37 0.74

CURVA PVC ELECTRICA SAP ¾" X 45˚ pza 3.000000 1.71 5.13

UNION PVC ELECTRICA SAP ¾" pza 1.000000 0.61 0.61

TOTAL 49.18

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 57.55 1.73

TOTAL 1.73

TOTAL P.U. 108.46

Page 73: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: LIMPIEZA GENERAL DE OBRA

RENDIMIENTO EN 8 HRS: 40.00 m2

APORTE: 5.0000 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

OPERARIO hh 0.020000 15.12 0.30

PEON hh 0.200000 11.84 2.37

TOTAL 2.67

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.050000 2.67 0.13

TOTAL 0.13

TOTAL P.U. 2.80

Page 74: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: CONCRETO LIQUIDO PREMEZCLADO EN MUROS

RENDIMIENTO EN 8 HRS: 8.00 m3

APORTE: 1.0000 h/m3

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.0133 18.14 0.24

OPERARIO hh 0.2667 15.12 4.03

OFICIAL hh 0.1333 13.14 1.75

PEON hh 0.5333 11.84 6.31

TOTAL 12.34

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

CONCRETO LIQUIDO PREMEZCLADO m3 1.0200 250.73 255.74

TOTAL 255.74

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.0300 12.34 0.37

TOTAL 0.37

TOTAL P.U. 268.45

Page 75: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: VENTANA PRINCIPAL DE 1.80 X 0.90 M DE 2

HOJAS

RENDIMIENTO EN 8 HRS: 2.50 m²

APORTE: 0.3125 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

OPERARIO hh 3.200000 15.12 48.38

PEON hh 3.200000 11.84 37.89

TOTAL 86.27

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58

ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00

TOTAL 67.58

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

EQUIPO DE SOLDAR hm 3.200000 4.50 14.40

HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31

TOTAL 18.71

TOTAL P.U. 172.57

Page 76: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: VENTANA POSTERIOR DE 1.20 X 0.90 M DE 2

HOJAS

RENDIMIENTO EN 8 HRS: 2.50 m²

APORTE: 0.3125 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

OPERARIO hh 3.200000 15.12 48.38

PEON hh 3.200000 11.84 37.89

TOTAL 86.27

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58

ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00

TOTAL 66.00

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

EQUIPO DE SOLDAR hm 3.200000 4.50 14.40

HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31

TOTAL 4.31

TOTAL P.U. 156.59

Page 77: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: VENTANAS EN DORMITORIOS DE 1.50 X .90 M DE 2

HOJAS

RENDIMIENTO EN 8 HRS: 2.50 m²

APORTE: 0.3125 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

OPERARIO hh 3.200000 15.12 48.38

PEON hh 3.200000 11.84 37.89

TOTAL 86.27

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58

ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00

TOTAL 66.00

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

EQUIPO DE SOLDAR hm 3.200000 4.50 14.40

HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31

TOTAL 4.31

TOTAL P.U. 156.59

Page 78: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: VENTANA CORREDIZA DE 1.55 X .90 M DE 2 HOJAS

RENDIMIENTO EN 8 HRS: 2.50 m²

APORTE: 0.3125 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

OPERARIO hh 3.200000 15.12 48.38

PEON hh 3.200000 11.84 37.89

TOTAL 86.27

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

SOLDADURA CELLOCORD P ⅛ E6010 kg 0.124400 12.71 1.58

ANGULO ACERO NEGRO IGUAL 1" X 1" X ¼" X 6m pza 1.650000 40 66.00

TOTAL 66.00

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

EQUIPO DE SOLDAR hm 3.200000 4.50 14.40

HERRAMIENTA MANUAL % MO 0.050000 86.27 4.31

TOTAL 4.31

TOTAL P.U. 156.59

Page 79: ANALISIS DE COSTO UNITARIO.pdf

ANALISIS DE COSTO UNITARIO

PROYECTO: EXAMEN PARCIAL

DESCRIPCION: MURO DE LADRILLO SILICO CALCAREO

RENDIMIENTO EN 8 HRS: 7.50 m2

APORTE: 0.9375 h/m2

MANO DE OBRA UNIDAD CANTIDAD COSTO SUBTOTAL

CAPATAZ hh 0.085000 18.14 1.54

OPERARIO hh 0.846000 15.12 12.79

PEON hh 0.719000 11.84 8.51

TOTAL 22.85

MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL

LADRILLO SILICO CALCAREO m2 1.030000 48.42 49.87

TOTAL 49.87

EQUIPOS UNIDAD CANTIDAD COSTO SUBTOTAL

HERRAMIENTA MANUAL % MO 0.030000 22.85 0.69

TOTAL 0.69

TOTAL P.U. 73.40