PRESUPUESTO ANALITICO (S/.) PROYECTO:"MEJORAMIENTO DE LAS VIAS AV. 24 DE DICIEMBRE, CANIPACO, 24 DE SETIEMBRE Región : Junín. Provincia: Huancayo Distrito: Chacapampa RUBRO: FERRETERIA COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO. PART. PARCIAL TOTAL Materiales: 46,972.52 1 LUBRICANTE PARA TUBERIA PVC gln 0.50 38.00 19.00 2 ALAMBRE NEGRO # 16 kg 33.00 4.50 148.50 3 ALAMBRE NEGRO # 8 kg 147.00 4.50 661.50 4 CLAVOS PARA MADERA C/C 3" kg 15.00 5.50 82.50 5 CLAVOS PARA MADERA kg 97.00 5.50 533.50 6 CLAVOS DE ALAMBRE PARA MADERA C/C DE 1" kg 28.00 4.50 126.00 7 ACERO DE REFUERZO FY=4200 GRADO 60 kg 583.00 4.50 2,623.50 8 ACERO LISO DE 1/2 m 782.46 4.50 3,521.07 9 ADOQUINES RECTANGULARES DE CEMENTO m2 255.00 36.00 9,180.00 10 CABLE TW # 2 AWG - 35 MM2. m 5.00 16.00 80.00 11 CACHIMBA DE PVC 10" CON ANILLO und 7.00 60.00 420.00 12 GLOBO PHILLIPS 70W-220 O SIMILAR und 24.00 45.00 1,080.00 13 TABLERO GABINETE METAL BARRA BRONCE 12 POLOS pza 1.00 120.00 120.00 14 CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 und 24.00 3.00 72.00 15 INTERRUPTOR AUTOMATICO pza 24.00 45.00 1,080.00 16 TUBERIA PVC SEL PARA INSTALACIONES ELECTRICAS DE 1" und 24.00 8.00 192.00 17 ASFALTO RC-250 gln 79.00 18.50 1,461.50 18 PINTURA ESMALTE PARA TRAFICO gln 5.50 38.50 211.75 19 CABLE ELECT NYY 2 X 4 MM2 m ### 8.00 9,024.00 20 CINTA AISLANTE rll 2.40 4.50 10.80 21 OCRE kg 42.00 12.00 504.00 22 THINNER CORRIENTE gln 6.00 24.00 144.00 23 VARILLA DE COBRE DE 1/2" x 2.40m und 1.00 250.00 250.00 24 PEGAMENTO PARA PVC gln 0.50 38.00 19.00 25 LIJA DISCO ASALITE SR 24 und 10.00 9.00 90.00 26 LIJA DISCO ASALITE SR 80 und 10.00 12.00 120.00 27 HIPOCLORITO DE CALCIO AL 70% kg 1.00 12.00 12.00 28 BROCHA und 1.00 23.00 23.00 29 MARMOLINA kg 262.00 0.50 131.00 30 PINTURA ESMALTE gln 20.00 34.50 690.00 31 GRANALLA ROJO CLARO kg 262.00 1.00 262.00 32 MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" und 1.00 28.00 28.00 33 TUBO PVC SAP 1" X 5 M und 82.00 8.00 656.00 34 TUB. PVC SAP P/INST. ELECT. DE 1" m 5.00 10.00 50.00 35 CURVA PESADO PVC SAP P/INST. ELECT. 1" und 1.00 0.80 0.80 36 UNION SIMPLE PVC SAP 1" pza 24.00 0.80 19.20 37 TUBERIA PVC PARA DESAGUE DE 10" CON ANILLO m 136.00 48.00 6,528.00 38 TUBERIA PVC PARA DESAGUE DE 8" CON ANILLO m 55.00 35.00 1,925.00 39 TUBO PVC SAP (LUZ) (E/C) 1" X 3 M. pza 188.00 10.00 1,880.00 40 CURVA PVC 1" pza 24.00 0.80 19.20 41 COMBA DE 16 LBS und 4.00 38.00 152.00 42 Buguie Unid. 8.00 220.00 1,760.00 43 Martillo Unid. 4.00 12.00 48.00 44 Serrucho Unid. 4.00 45.00 180.00 45 Picos incluyen mango Unid. 10.00 24.00 240.00 46 Lampa tipo cuchara Unid. 10.00 24.00 240.00 47 Cemento blanco bls. 50 KG BOL 3.9300 90.00 353.70 Y LA MERCED EN EL PARQUE ANTACOCHA, DISTRITO DE CHACAPAMPA-HUANCAYO"

description

analisis

Transcript of Analitico Mej. Vias Chacapampa

Page 1: Analitico Mej. Vias Chacapampa

PRESUPUESTO ANALITICO (S/.)PROYECTO:"MEJORAMIENTO DE LAS VIAS AV. 24 DE DICIEMBRE, CANIPACO, 24 DE SETIEMBRE

Región : Junín. Provincia: Huancayo Distrito: Chacapampa

RUBRO: FERRETERIA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

Materiales: 46,972.52

1 LUBRICANTE PARA TUBERIA PVC gln 0.50 38.00 19.00

2 ALAMBRE NEGRO # 16 kg 33.00 4.50 148.50

3 ALAMBRE NEGRO # 8 kg 147.00 4.50 661.50

4 CLAVOS PARA MADERA C/C 3" kg 15.00 5.50 82.50

5 CLAVOS PARA MADERA kg 97.00 5.50 533.50

6 CLAVOS DE ALAMBRE PARA MADERA C/C DE 1" kg 28.00 4.50 126.00

7 ACERO DE REFUERZO FY=4200 GRADO 60 kg 583.00 4.50 2,623.50

8 ACERO LISO DE 1/2 m 782.46 4.50 3,521.07

9 ADOQUINES RECTANGULARES DE CEMENTO m2 255.00 36.00 9,180.00

10 CABLE TW # 2 AWG - 35 MM2. m 5.00 16.00 80.00

11 CACHIMBA DE PVC 10" CON ANILLO und 7.00 60.00 420.00

12 GLOBO PHILLIPS 70W-220 O SIMILAR und 24.00 45.00 1,080.00

13 TABLERO GABINETE METAL BARRA BRONCE 12 POLOS pza 1.00 120.00 120.00

14 CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 und 24.00 3.00 72.00

15 INTERRUPTOR AUTOMATICO pza 24.00 45.00 1,080.00

16 TUBERIA PVC SEL PARA INSTALACIONES ELECTRICAS DE 1" und 24.00 8.00 192.00

17 ASFALTO RC-250 gln 79.00 18.50 1,461.50

18 PINTURA ESMALTE PARA TRAFICO gln 5.50 38.50 211.75

19 CABLE ELECT NYY 2 X 4 MM2 m 1,128.00 8.00 9,024.00

20 CINTA AISLANTE rll 2.40 4.50 10.80

21 OCRE kg 42.00 12.00 504.00

22 THINNER CORRIENTE gln 6.00 24.00 144.00

23 VARILLA DE COBRE DE 1/2" x 2.40m und 1.00 250.00 250.00

24 PEGAMENTO PARA PVC gln 0.50 38.00 19.00

25 LIJA DISCO ASALITE SR 24 und 10.00 9.00 90.00

26 LIJA DISCO ASALITE SR 80 und 10.00 12.00 120.00

27 HIPOCLORITO DE CALCIO AL 70% kg 1.00 12.00 12.00

28 BROCHA und 1.00 23.00 23.00

29 MARMOLINA kg 262.00 0.50 131.00

30 PINTURA ESMALTE gln 20.00 34.50 690.00

31 GRANALLA ROJO CLARO kg 262.00 1.00 262.00

32 MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" und 1.00 28.00 28.00

33 TUBO PVC SAP 1" X 5 M und 82.00 8.00 656.00

34 TUB. PVC SAP P/INST. ELECT. DE 1" m 5.00 10.00 50.00

35 CURVA PESADO PVC SAP P/INST. ELECT. 1" und 1.00 0.80 0.80

36 UNION SIMPLE PVC SAP 1" pza 24.00 0.80 19.20

37 TUBERIA PVC PARA DESAGUE DE 10" CON ANILLO m 136.00 48.00 6,528.00

38 TUBERIA PVC PARA DESAGUE DE 8" CON ANILLO m 55.00 35.00 1,925.00

39 TUBO PVC SAP (LUZ) (E/C) 1" X 3 M. pza 188.00 10.00 1,880.00

40 CURVA PVC 1" pza 24.00 0.80 19.20

41 COMBA DE 16 LBS und 4.00 38.00 152.00

42 Buguie Unid. 8.00 220.00 1,760.00

43 Martillo Unid. 4.00 12.00 48.00

44 Serrucho Unid. 4.00 45.00 180.00

45 Picos incluyen mango Unid. 10.00 24.00 240.00

46 Lampa tipo cuchara Unid. 10.00 24.00 240.00

47 Cemento blanco bls. 50 KG BOL 3.9300 90.00 353.70

Y LA MERCED EN EL PARQUE ANTACOCHA, DISTRITO DE CHACAPAMPA-HUANCAYO"

Page 2: Analitico Mej. Vias Chacapampa

RUBRO: MADERA Y OTROS

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

Maderas:1 Madera Roble corriente de 1"x8"x10´ Unid. 250.00 16.00 4,000.00 8,243.00

2 Madera Roble corriente de 1"x4"x10´ Unid. 210.00 8.00 1,680.00

3 Madera Roble corriente de 4"x4"x10´ Unid. 24.00 36.00 864.00

4 Madera Roble corriente de 2"x2"x10´ Unid. 210.00 8.00 1,680.00

5 Regla de madera Und. 1.00 19.00 19.00

RUBRO: AGREGADOS

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

1 ARENA FINA m3 17.00 110.00 1,870.00 58,638.00

2 TIERRA DE CHACRA O VEGETAL m3 40.00 40.00 1,600.00

3 PIEDRA GRANDE DE 8" m3 1.00 60.00 60.00

4 ARENA GRUESA m3 12.00 84.00 1,008.00

5 MATERIAL DE RELLENO m3 72.00 20.00 1,440.00

6 MATERIAL SELECCIONADO m3 423.00 60.00 25,380.00

7 PIEDRA LAJA m3 14.00 120.00 1,680.00

8 HORMIGON m3 320.00 80.00 25,600.00

RUBRO: PUBLICIDAD

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

1 Gigantografia de 3.00 x 2.20 m Unid. 1.00 450.00 450.00 670.00

2 Placa Recordatoria Unid. 1.00 220.00 220.00

RUBRO: SERVICIOS DE TERCEROS

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

16,052.00

1 Sub contrato rejilla c/perfil 1 1/4"x1/4"+L 1 1/4" m2 14.70 60.00 882.00

2 Sub contrato farola tipo I según diseño und 24.00 280.00 6,720.00

3 Sub contrato tacho de basura según diseño und 5.00 220.00 1,100.00

4 Sub contrato banca tipo colonial según diseño und 3.00 220.00 660.00

5 Sub contrato señal de cruce peatonal und 4.00 220.00 880.00

6 Sub contrato tobogan und 2.00 1,800.00 3,600.00

7 Sub contrato columpio und 2.00 675.00 1,350.00

8 Sub contrato balancín metalico tubo F° 4" und 1.00 860.00 860.00

RUBRO: SERVICIOS DE TERCEROS FLETE

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

Flete terrestre 13,758.72

1 SUB CONTRATO DE FLETE TERRESTRE kg 137,587.17 0.10 13,758.72

Page 3: Analitico Mej. Vias Chacapampa

RUBRO: SERVICIOS DE TERCEROS TRANSPORTE MAQUINARIA PESADA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

Flete terrestre 1,440.00

1 CAMION PLATAFORMA 4x2 122 HP 8 TON. hm 8.00 180.00 1,440.00

RUBRO: SERVICIOS DE TERCEROS ALQUILER MAQUINARIA PESADA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

9,792.90

1 CAMION VOLQUETE 4x2 140-210 HP 6 M3. hm 31.47 90.00 2,832.30

2 RODILLO LISO VIBR AUTOP 70-100 HP 7-9 T. hm 6.91 180.00 1,243.80

3 CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3 hm 9.02 180.00 1,623.60

4 RETROEXCAVADOR S/ORUGA 80-110HP 0.5-1.3Y hm 9.77 180.00 1,758.60

5 TRACTOR DE ORUGAS DE 190-240 HP hm 7.04 180.00 1,267.20

6 MOTONIVELADORA DE 125 HP hm 5.93 180.00 1,067.40

RUBRO: SERVICIOS DE TERCEROS ALQUILER MAQUINARIA LIGERA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

10,742.74

1 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 142.52 35.00 4,988.20

2 TEODOLITO hm 69.19 12.00 830.28

3 NIVEL TOPOGRAFICO hm 63.19 9.00 568.71

4 CEPILLADORA ELECTRICA hm 46.61 10.08 469.83

5 BALDE PRUEBA-TAPON -ABRAZ. Y ACCESORIOS hm 6.78 12.00 81.36

6 MOTOBOMBA 3.5 HP 2" hm 6.78 12.00 81.36

7 ANDAMIO METAL TABLAS-ALQUILER est 15.94 60.00 956.40

8 CIZALLA P/CORTE DE FIERRO hm 10.98 6.00 65.88

9 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP hm 162.53 12.00 1,950.36

10 VIBRADOR DE 3/4" - 2" CONCRETO hm 62.53 12.00 750.36

RUBRO: CEMENTO

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.PART. PARCIAL TOTAL

Cemento 44,460.00

1 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2,280.00 19.50 44,460.00

RUBRO: MANO DE OBRA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTALMano de obra: 64,452.38

1 Topografo H-H 69.19 12.00 830.28

2 Capataz H-H 296.76 13.90 4,124.96

3 Operario H-H 2,264.50 11.90 26,947.55

4 Oficial H-H 1,842.83 8.90 16,401.19

5 Peon H-H 3,670.09 4.40 16,148.40

Page 4: Analitico Mej. Vias Chacapampa

RUBRO: JARDINERIA Y OTROS

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

2,905.00

1 GRASS NATURAL m2 190.00 12.00 2,280.00

2 PLANTA DE SAUCO pza 8.00 30.00 240.00

3 PLANTA DE ACACIA pza 3.00 45.00 135.00

4 PLANTA DE PINO ARAUCARIA pza 2.00 90.00 180.00

5 PLANTA DE ALAMO CAROLINO pza 2.00 35.00 70.00

RUBRO: GASTOS GENERALES

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

27,847.50

GASTOS DE ADMINISTRACION DE OBRA

1 Residente de Obra Mes 3.50 3,000.00 10,500.00

2 Maestro de Obra Mes 3.00 1,800.00 5,400.00

3 Asistente administrativo Mes 3.00 900.00 2,700.00

4 Secretaria Mes 3.00 600.00 1,800.00

CONTROL DE CALIDAD

1 Diseño de mezcla Und 3.00 200.00 600.00

2 Rotura de testigos de concreto Und 12.00 20.00 240.00

3 Pruebas de compactacion Und 4.00 120.00 480.00

INPLEMENTOS DE SEGURIDAD

1 Cascos de seguridad Und 20.00 22.00 440.00

2 Guantes de jebe Und 10.00 12.00 120.00

3 Guantes de cuero Und 10.00 14.00 140.00

4 Botas de jebe Par 20.00 20.00 400.00

PAPELERIA UTILES DE ESCRITORIO

1 Papel Bond T-A4 75gr. Millar 5.00 28.00 140.00

2 Lapicero color azul Und 6.00 1.50 9.00

3 Portaminas Und 6.00 18.00 108.00

4 Papel carbon Und 25.00 0.50 12.50

5 Engrampador tipo tijera Und 1.00 50.00 50.00

6 Folder manila T-A4 Und 50.00 0.70 35.00

7 Fastener Und 50.00 0.50 25.00

8 Cuaderno de obra 100 folios Und 1.00 65.00 65.00

9 Cuaderno A-4 espiral Und 2.00 9.00 18.00

10 Cuaderno T-oficio espiral Und 2.00 15.00 30.00

11 Correctores Und 2.00 5.00 10.00

12 Tampon azul Und 2.00 6.50 13.00

13 Memoria USB 16 GB Und 2.00 120.00 240.00

14 Archivadores tamaño grande Und 4.00 8.00 32.00

BIENES PERMANENTES

1 Lap Top Core I5 DR 4GB, HD 650 GB Und 1.00 3,450.00 3,450.00

2 Camara Digital 12 MP Und 1.00 790.00 790.00

RUBRO: CAJA CHICA

COD. DESCRIPCION UNID. METRADO P. U. PPTO. PPTO.

PART. PARCIAL TOTAL

Cemento 421.40

1 Varios glo 1.00 421.40 421.40

PRESUPUESTO TOTAL 306,396.15

SUPERVISOR 10,584.59

Page 5: Analitico Mej. Vias Chacapampa

PRESUPUESTO DE OBRA 316,980.74

Page 6: Analitico Mej. Vias Chacapampa

DESAGREGADO DE PRESUPUESTO ANALITICO

PROYECTO : " MEJORAMIENTO CANAL DE RIEGO PACHA - USIBAMBA"Distrito : San José de Quero

Cadena Mod. Especificación del Gasto Unid. Numero Cant. Presupuesto

de Meses Pers. P. P. Sub

Gasto Aplic. Unit. Parc. Total

APLICACIONES DIRECTAS

10 Retribuciones y Compromisos a Plazo Fijo 18600.00Personal de ObraOperarios mes 2.00 3.000 1200.000 7200.000Oficiales mes 2.00 3.000 900.000 5400.000Peones mes 2.00 5.000 600.000 6000.000

BIENES Y SERVICIOS29 Materiales de Construcción 73879.20

Pintura Esmalte Gln. 1.000 35.000 35.000Yeso Bls. 10.000 3.500 35.000Alambre N° 16 Kg. 30.000 5.500 165.000Alambre N° 8 Kg. 60.000 5.500 330.000Clavos de 2" Kg. 45.000 5.500 247.500Clavos de a 3" Kg. 30.000 5.500 165.000Clavos de 4" Kg. 10.000 6.500 65.000Cemento Portland tipo I Bls. 220.000 18.300 4026.000Fierro corrugado de 3/8" varil 80.000 41.000 3280.000Valvulas de compuerta con acce de 4" Unid. 8.000 135.000 1080.000Cachimba de de 16" con salida de 4" Unid. 8.000 50.000 400.000Impermeabilizante Gln. 6.000 20.000 120.000Cinta Teflon Unid. 10.000 1.500 15.000Hoja de Sierra Sanflex Unid. 10.000 4.500 45.000Tubo de PVC D=16" C-7,5 S PRESION (uf) Tub. 65.000 752.720 48926.800Lubricante para tuberia Gln. 4.000 40.000 160.000Codo de 45º PVC S-25 de 16" incluye anillo Unid. 8.000 350.000 2800.000Codo de 90º PVC S-25 de 16" incluye anillo Unid. 9.000 350.000 3150.000Madera cedro de 1"x8"x10´ Unid. 150.000 14.670 2200.500Madera cedro de 2"x2"x10´ Unid. 30.000 7.330 219.900Madera cedro de 2"x3"x10´ Unid. 30.000 11.000 330.000Madera cedro de 1"x2"x10´ Unid. 50.000 3.670 183.500Madera Rollizo de 3.5 m de 20 cm de diametro Unid. 3.000 25.000 75.000Hormigon Confitillado m3 55.000 95.000 5225.000Arena Fina m3 4.000 150.000 600.000

30 Bienes de consumoHerramientas 479.00Balde de de plastico de 5 galones Unid. 10.000 5.000 50.000Plastico de 1 m. de ancho m. 50.000 3.000 150.000Wincha de 50 m. de fibra de vidrio Unid. 1.000 70.000 70.000Flexometro de 5 m. Unid. 2.000 8.000 16.000Cordel de algodón Madeja 3.000 8.000 24.000Cordel Nylon (hilo de pescar) de 8 mm. Carret 3.000 8.000 24.000Bruña de Canto Unid. 4.000 10.000 40.000Nivel de mano Unid. 2.000 30.000 60.000Hoja de Sierra Sanflex Unid. 10.000 4.500 45.000

BIENES Y SERVICIOS22 Vestuario 870.00

Botas de Jebe Par 15.000 18.000 270.000Zapato de seguridad Par 2.000 300.000 600.000

Page 7: Analitico Mej. Vias Chacapampa

DESAGREGADO DE PRESUPUESTO ANALITICO

PROYECTO : " MEJORAMIENTO CANAL DE RIEGO PACHA - USIBAMBA"Distrito : San José de Quero

Cadena Mod. Especificación del Gasto Unid. Numero Cant. Presupuesto

de Meses Pers. P. P. Sub

Gasto Aplic. Unit. Parc. Total

39 Otros Servicios de Terceros. 7030.00Trazo y Replanteo Glob. 1.000 1000.000 1000.000Prueba de Calidad del concreto Unid. 5.000 40.000 200.000Diseño de Mezcla de concreto Unid. 1.000 350.000 350.000Flete Terrestre Glob. 1.000 1600.000 1600.000Flete Rural Glob. 1.000 1350.000 1350.000Gigantografia de 3.00 x 2.20 m Unid. 1.000 450.000 450.000Placa Recordatoria Unid. 1.000 250.000 250.000Rejilla de Acero Corrugado de 1/4" Unid. 2.000 35.000 70.000Compuerta Metalica con Sistemade Izaje de 1/8" x 0.25 x 0,40 m. Unid. 2.000 280.000 560.000Compuerta tipo tarjeta planchametalica 1/8" 0.30x0.25 m. Unid. 2.000 180.000 360.000Tapa Metalica de 1,20 x 0.70 Unid. 4.000 150.000 600.000Tapa Metalica de 0,50 x 0.50 Unid. 4.000 60.000 240.000

27 Servicios no personales 17350Maestro de Obra Mes 2.00 1800.00 3600Supervisor de Obra Mes 2.50 3000.00 7500Residente de Obra Mes 2.50 2500.00 6250

30 Bienes de consumo 791.8Papel Bond millar 3.00 23.50 70.5Cuaderno de Obra Unid. 1.00 30.00 30Cuaderno A-4 Unid. 2.00 2.50 5Lapicero Tinta Seca Unid. 10.00 1.50 15Folder Manila A-4 C/Faster Ciento 0.50 8.00 4Archivador A-4 Unid. 4.00 12.80 51.2Archivadores Pequeños Unid. 1.00 12.80 12.8Corectores Unid. 4.00 2.80 11.2

Memoria USB de 8 GB Unid. 2.00 160.00 320

Dvd Regrabable Unid. 12.00 1.55 18.6

Tampon Unid. 1.00 3.50 3.5

Toner de impresora laser Unid. 1.00 250.00 250

TOTAL 119000