    CALCULO DE FLETE

    OBRA: "MERCADO MUNICIPAL PAZOS

    1- DATOS GENERALESTRANSPORTE TERRESTRE DE MATERIALES DESDE HUANCAYO HASTA PZOS

    A- POR PESOMATERIALES UNIDAD CANTIDAD PESO UNIT.PESO TOTAL

    CEMENTO BL. 2,280.00 42.50 96,900.00FIERRO, CLAVOS KG 9,483.10 1.00 9,483.10MADERA P2 2,214.25 1.50 3,321.38Soldadura Kg 700.25 1.00 700.25LADRILLO KG 3,802.00 3.00 11,406.00LADRILLO/TECHO KG 542.00 8.00 4,336.00Perfiles/planchas de acero KG 12,642.21 1.00 12,642.21

    Calaminas Pln 876.71 3.58 3,138.62OTROS KG 2,500.00 1.00 2,500.00

    PESO TOTAL 144,427.56

    B-POR VOLUMENDESCRIPCION UNIDAD CANTIDAD SIN IGV

    ARENA FINA M3 67.00ARENA GRUESA M3 16.00PIEDRA M3 4.25HORMIGN M3 336.00PIEDRA CHANCADA M3 10.00

    VOLUMEN TOTAL 346.00CAPACIDAD DEL CAMION (M3) 6.00

    NUMERO DE VIAJES

    REDONDEO

    EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.CAPACIDAD DEL CAMION EN TUBOS / VIAJE Cantidad MlNo de tubos o VIAJE

    Tub. 1" Und 3,360.00Tub. 1 1/2" Und 1,690.00 8.75 1.75 0.00Tub. 2" Und 994.00 2.67 0.53 0.00Tub. 3" Und 470.00 84.00 16.80 0.04Tub. 4" Und 259.00 9.45 1.89 0.01Tub. 6"; U-PVC Und 110.00Tub. 8" U-PVC Und 65.00Tub. 6"; CSN Und 160.00Tub. 8"; CSN Und 80.00

    NUMERO TOTAL DE VIAJ 0.05REDONDEO 0.00