    OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO

    UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC

    1 QUINCENA 2 QUINCENA 1 QU

    5.65 % 7.04 %

    BOCATOMA

    01 OBRAS PROVISIONALES

    01.01 CARTEL DE IDENTIFICACION DE OBRA 100.00 %

    01.02 ALMACEN DE OBRA Y GUARDIANIA 100.00 %

    01.03 TRANSPORTE DE MAT. Y AGREGADOS 30.00 % 30.00 % 2

    01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO 50.00 %

    02 MUROS DE ENCAUZAMIENTO

    02.01 TRABAJOS PRELIMINARES 50.00 % 20.00 % 2

    02.02 MOVIMIENTO DE TIERRAS 20.00 % 40.00 % 4

    02.03 OBRAS DE CONCRETO SIMPLE 30.00 % 402.04 OBRAS DE CONCRETO ARMADO 5

    02.05 REVOQUES Y ENLUCIDOS

    03 PRESA DERIVADORA

    03.01 TRABAJOS PRELIMINARES 50.00 % 5

    03.02 MOVIMIENTO DE TIERRAS 75.00 % 2

    03.03 OBRAS DE CONCRETO SIMPLE 50.00 % 5

    03.04 OBRAS DE CONCRETO ARMADO 4

    03.05 REVOQUES Y ENLUCIDOS

    03.06 VARIOS

    04 TOMA O CAPTACION

    04.01 TRABAJOS PRELIMINARES

    04.02 MOVIMIENTO DE TIERRAS

    04.03 OBRAS DE CONCRETO SIMPLE

    04.04 OBRAS DE CONCRETO ARMADO

    04.05 REVOQUES Y ENLUCIDOS

    04.06 VARIOS

    05 LINEA DE CONDUCCION

    05.01 TRABAJOS PRELIMINARES 40.00 % 50.00 % 1

    05.02 MOVIMIENTO DE TIERRAS 5.00 % 20.00 % 2

    05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION 10.00 % 2

    05.04 ACCESORIOS PARA TUBERIAS

    05.05 PRUEBA HIDRAULICA

    01 RESERVORIO DE GEOMENBRANA N 01

    01.01 TRABAJOS PRELIMINARES

    01.02 MOVIMIENTO DE TIERRAS

    01.03 GEOMENBRANA

    100 CAJA PARA VALVULAS

    01.05 ACCESORIOS DE RESERVORIO

    01.06 CERCO PERIMETRICO

    02 RESERVORIO DE GEOMENBRANA N 02

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 GEOMENBRANA

    02.04 CAJA PARA VALVULAS

    02.05 ACCESORIOS DE RESERVORIO

    02.06 CERCO PERIMETRICO3 RESERVORIO DE GEOMENBRANA N 03

    02.01 TRABAJOS PRELIMINARES

    ITEM DESCRIPCIN DE PARTIDAS

    PLAZO D

    1 MES

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    2/18

    CRONOGR

    OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE

    UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC

    1 QUINCENA 2 QUINCENA 1 QUIN

    5.65 % 7.04 % 9

    ITEM DESCRIPCIN DE PARTIDAS

    PLAZO DE

    1 MES

    08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)

    08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)

    08.08 CAMARA PARA HIDRANTE (75 UNID)

    09 RED DE DISTRIBUCION

    09.01 TRABAJOS PRELIMINARES 30

    09.02 MOVIMIENTO DE TIERRAS

    09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION

    09.04 ACCESORIOS PARA TUBERIAS

    09.05 PRUEBA HIDRAULICA

    10 PLAN DE MANEJO AMBIENTAL

    10.01 ACTIVIDADES DE PREVENCION 10.00 % 10.00 % 1010.02 ACTIVIDADES DE MITIGACION 5.00 % 5.00 % 10

    10.03 ACTIVIDADES DE MONITOREO 5.00 % 5.00 % 1010.04 FLETE 50.00 % 50.00 %11 CAPACITACION TECNICA

    11.01 TRABAJOS DE CAMPO 50.00 % 50.00 %11.02 CONVOCATORIA 50.00 % 5011.03 DE LA CAPACITACION 5

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    3/18

    OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE COLPAS.

    UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC

    1 QUINCENA 2 QUINCENA 1

    15 30

    BOCATOMA

    01 OBRAS PROVISIONALES S/. 0.00 S/. 0.00

    01.01 CARTEL DE IDENTIFICACION DE OBRA S/. 871.45 S/. 0.00

    01.02 ALMACEN DE OBRA Y GUARDIANIA S/. 1,096.46 S/. 0.00

    01.03 TRANSPORTE DE MAT. Y AGREGADOS S/. 35,209.34 S/. 35,209.34 S

    01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 529.41 S/. 0.00

    02 MUROS DE ENCAUZAMIENTO

    02.01 TRABAJOS PRELIMINARES S/. 230.98 S/. 92.39

    02.02 MOVIMIENTO DE TIERRAS S/. 5,874.15 S/. 11,748.31 S

    02.03 OBRAS DE CONCRETO SIMPLE S/. 0.00 S/. 347.93

    02.04 OBRAS DE CONCRETO ARMADO S/. 0.00 S/. 0.00 S

    02.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00

    03 PRESA DERIVADORA S/. 0.00 S/. 0.00

    03.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 102.26

    03.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 86.66

    03.03 OBRAS DE CONCRETO SIMPLE S/. 0.00 S/. 3,745.97

    03.04 OBRAS DE CONCRETO ARMADO S/. 0.00 S/. 0.00

    03.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00

    03.06 VARIOS

    04 TOMA O CAPTACION

    04.01 TRABAJOS PRELIMINARES

    04.02 MOVIMIENTO DE TIERRAS

    04.03 OBRAS DE CONCRETO SIMPLE

    04.04 OBRAS DE CONCRETO ARMADO

    04.05 REVOQUES Y ENLUCIDOS S/. 0.00 S/. 0.00

    04.06 VARIOS S/. 0.00 S/. 0.00

    05 LINEA DE CONDUCCION S/. 0.00 S/. 0.00

    05.01 TRABAJOS PRELIMINARES S/. 3,993.60 S/. 4,992.00

    05.02 MOVIMIENTO DE TIERRAS S/. 8,138.33 S/. 32,553.32 S

    05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION S/. 0.00 S/. 12,958.40 S

    05.04 ACCESORIOS PARA TUBERIAS S/. 0.00 S/. 0.00

    05.05 PRUEBA HIDRAULICA S/. 0.00 S/. 0.00

    01 RESERVORIO DE GEOMENBRANA N 01 S/. 0.00 S/. 0.00

    01.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00

    01.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00

    01.03 GEOMENBRANA S/. 0.00 S/. 0.00

    100 CAJA PARA VALVULAS S/. 0.00 S/. 0.00

    01.05 ACCESORIOS DE RESERVORIO S/. 0.00 S/. 0.00

    01.06 CERCO PERIMETRICO S/. 0.00 S/. 0.00

    02 RESERVORIO DE GEOMENBRANA N 02 S/. 0.00 S/. 0.00

    02.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00

    02.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00

    ITEM DESCRIPCIN DE PARTIDAS1 MES

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    4/18

    OBRA : INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO, EN LA LOCALIDAD DE YAPAC, DISTRITO DE COLPAS.

    UBICACIN : Departamento: HUNUCO Provincia: AMBO Distrito: COLPAS Localidad: YAPAC

    1 QUINCENA 2 QUINCENA 1 Q

    15 30

    ITEM DESCRIPCIN DE PARTIDAS1 MES

    02.02 MOVIMIEN TO DE TIERRAS S/. 0.00 S/. 0.00

    02.03 GEOMENBRANA S/. 0.00 S/. 0.00

    02.04 CAJA PARA VALVULAS S/. 0.00 S/. 0.00

    02.05 ACCESORIOS DE RESERVORIO S/. 0.00 S/. 0.00

    02.06 CERCO PERIMETRICO S/. 0.00 S/. 0.00

    08 OBRAS DE ESTRUCTURAS HIDRAULICAS S/. 0.00 S/. 0.00

    08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID) S/. 0.00 S/. 0.00

    08.04 CAMARA ROMPE PRESION (11 UNID) S/. 0.00 S/. 0.00

    08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.) S/. 0.00 S/. 0.00

    08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID) S/. 0.00 S/. 0.00

    08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID) S/. 0.00 S/. 0.00

    08.08 CAMARA PARA HIDRANTE (75 UNID) S/. 0.00 S/. 0.00

    09 RED DE DISTRIBUCION S/. 0.00 S/. 0.00

    09.01 TRABAJOS PRELIMINARES S/. 0.00 S/. 0.00

    09.02 MOVIMIENTO DE TIERRAS S/. 0.00 S/. 0.00

    09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION S/. 0.00 S/. 0.00

    09.04 ACCESORIOS PARA TUBERIAS S/. 0.00 S/. 0.00

    09.05 PRUEBA HIDRAULICA S/. 0.00 S/. 0.00

    10 PLAN DE MANEJO AMBIENTAL S/. 0.00 S/. 0.00

    10.01 ACTIVIDADES DE PREVENCION S/. 1,169.51 S/. 1,169.51

    10.02 ACTIVIDADES DE MITIGACION S/. 938.65 S/. 938.65

    10.03 ACTIVIDADES DE MONITOREO S/. 32.44 S/. 32.44

    10.04 FLETE S/. 500.00 S/. 500.00

    11 CAPACITACION TECNICA S/. 0.00 S/. 0.00

    11.01 TRABAJOS DE CAMPO S/. 600.00 S/. 600.00

    11.02 CONVOCATORIA S/. 0.00 S/. 450.00

    11.03 DE LA CAPACITACION S/. 0.00 S/. 0.00

    COSTO DIRECTO DEL PROYECTO (A) S/. 59,184.33 S/. 105,527.17

    GASTOS GENERALES (10 %) (B) S/. 5,918.43 S/. 10,552.72

    GASTOS DE UTILIDAD (10%) ( C) S/. 5,918.43 S/. 10,552.72

    COSTO SUB TOTAL DEL PROYECTO (A+B+C) S/. 71,021.20 S/. 126,632.60 S/

    IGV (18 %) D= (A+B+C)*0.18 S/. 12,783.82 S/. 22,793.87

    COSTO DE LA OBRA (CO=D+A+B+C) S/. 83,805.02 S/. 149,426.47 S/

    GASTOS DE SUPERVISIN ( E) S/. 1,775.53 S/. 3,165.82

    COSTO DE ELABORACION DE EXPEDIENTE DEFINITIVO S/. 36,853.52

    COSTO TOTAL DEL PROYECTO (CO + E) S/. 122,434.06 S/. 152,592.29

    AVANCE POR QUINCENA 5.65 % 7.04 % 9AVANCE POR MES

    AVANCE ACUMULADO 12.68 %

    12.68 %

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    5/18

    MONTO TOTAL DEL PPPTO.PLAZO DE EJECUCIN : 180 DAS CALENDARIO

    2 QUINCENA 1 QUINCENA 2 QUINCENA

    150 165 180 120 Das

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 120,391.21

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 871.45

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,096.46

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 117,364.48

    S/. 0.00 S/. 0.00 S/. 529.41 S/. 1,058.82S/. 54,570.99

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 461.96

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 29,370.77

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,159.76

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 22,073.16

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,505.34

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 21,444.94

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 204.52

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 115.54

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 7,491.93

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 12,527.60

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 727.92

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 377.43

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 17,278.98

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 126.24

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 402.64

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,464.83

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,055.13

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,284.34

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,945.80

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 316,012.96

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 9,984.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 162,766.58

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 129,584.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,731.18

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,947.20

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 58,567.64

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,588.77

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 25,899.41

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 19,458.98

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,601.77S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,556.61

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,462.10

    2,168,461.01S/.

    PRESUPUESTO

    PROGRAMADOES 6 MES

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    6/18

    MONTO TOTAL DEL PPPTO.

    PLAZO DE EJECUCIN : 180 DAS CALENDARIO

    2 QUINCENA 1 QUINCENA 2 QUINCENA

    150 165 180 120 Das

    2,168,461.01S/.

    PRESUPUESTO

    PROGRAMADOES 6 MES

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,017.70

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,376.19

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,601.77

    S/. 5,556.61 S/. 0.00 S/. 0.00 S/. 5,556.61

    S/. 1,326.70 S/. 0.00 S/. 0.00 S/. 1,326.70

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 242,550.52

    S/. 2,462.30 S/. 820.77 S/. 0.00 S/. 8,207.68

    S/. 7,372.83 S/. 0.00 S/. 0.00 S/. 73,728.27

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 7,565.33

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 14,247.72

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 18,317.21

    S/. 36,145.29 S/. 48,193.72 S/. 0.00 S/. 120,484.31

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 467,026.68

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 30,088.80

    S/. 17,189.70 S/. 0.00 S/. 0.00 S/. 171,896.99

    S/. 46,734.30 S/. 46,734.30 S/. 11,683.57 S/. 233,671.48

    S/. 1,147.73 S/. 765.16 S/. 382.58 S/. 3,825.78S/. 8,263.09 S/. 11,017.45 S/. 5,508.73 S/. 27,543.63

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 32,116.92

    S/. 1,169.51 S/. 0.00 S/. 0.00 S/. 11,695.13

    S/. 1,877.30 S/. 938.65 S/. 938.65 S/. 18,772.99

    S/. 64.88 S/. 32.44 S/. 32.44 S/. 648.80

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,000.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 8,500.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,200.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 900.00

    S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,400.00

    S/. 136,396.65 S/. 108,502.49 S/. 19,075.38 S/. 1,474,140.73

    S/. 13,639.67 S/. 10,850.25 S/. 1,907.54 S/. 147,414.07

    S/. 13,639.67 S/. 10,850.25 S/. 1,907.54 S/. 147,414.07

    S/. 163,675.98 S/. 130,202.98 S/. 22,890.45 S/. 1,768,968.88

    S/. 29,461.68 S/. 23,436.54 S/. 4,120.28 S/. 318,414.40

    S/. 193,137.66 S/. 153,639.52 S/. 27,010.73 S/. 2,087,383.27

    S/. 4,091.90 S/. 3,255.07 S/. 572.26 S/. 44,224.22

    S/. 36,853.52

    S/. 197,229.56 S/. 156,894.59 S/. 27,582.99 S/. 2,168,461.01

    9.10 % 7.24 % 1.27 %

    1 % 8.51 %91.49 % 100.00 %

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    7/18

    Item Descripcin UndMetr

    ado

    Precio

    (S/.)Parcial (S/.)

    BOCATOMA

    01 OBRAS PROVISIONALES

    01.01 CARTEL DE IDENTIFICACION DE OBRA01.02 ALMACEN DE OBRA Y GUARDIANIA

    01.03 TRANSPORTE DE MAT. Y AGREGADOS

    01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO

    02 MUROS DE ENCAUZAMIENTO

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 OBRAS DE CONCRETO SIMPLE

    02.04 OBRAS DE CONCRETO ARMADO

    02.05 REVOQUES Y ENLUCIDOS

    03 PRESA DERIVADORA

    03.01 TRABAJOS PRELIMINARES

    03.02 MOVIMIENTO DE TIERRAS

    03.03 OBRAS DE CONCRETO SIMPLE

    03.04 OBRAS DE CONCRETO ARMADO03.05 REVOQUES Y ENLUCIDOS

    03.06 VARIOS

    04 TOMA O CAPTACION

    04.01 TRABAJOS PRELIMINARES

    04.02 MOVIMIENTO DE TIERRAS

    04.03 OBRAS DE CONCRETO SIMPLE

    04.04 OBRAS DE CONCRETO ARMADO

    04.05 REVOQUES Y ENLUCIDOS

    04.06 VARIOS

    05 LINEA DE CONDUCCION

    05.01 TRABAJOS PRELIMINARES

    05.02 MOVIMIENTO DE TIERRAS

    05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION

    05.04 ACCESORIOS PARA TUBERIAS05.05 PRUEBA HIDRAULICA

    01 RESERVORIO DE GEOMENBRANA N 01

    01.01 TRABAJOS PRELIMINARES

    01.02 MOVIMIENTO DE TIERRAS

    01.03 GEOMENBRANA

    01.04 CAJA PARA VALVULAS

    01.05 ACCESORIOS DE RESERVORIO

    01.06 CERCO PERIMETRICO

    02 RESERVORIO DE GEOMENBRANA N 02

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 GEOMENBRANA

    02.04 CAJA PARA VALVULAS

    02.05 ACCESORIOS DE RESERVORIO02.06 CERCO PERIMETRICO

    3 RESERVORIO DE GEOMENBRANA N 03

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 GEOMENBRANA

    02.04 CAJA PARA VALVULAS

    02.05 ACCESORIOS DE RESERVORIO

    02.06 CERCO PERIMETRICO

    08 OBRAS DE ESTRUCTURAS HIDRAULICAS

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    8/18

    08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID)

    08.04 CAMARA ROMPE PRESION (11 UNID)

    08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.)

    08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)

    08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)

    08.08 CAMARA PARA HIDRANTE (75 UNID)

    09 RED DE DISTRIBUCION

    09.01 TRABAJOS PRELIMINARES

    09.02 MOVIMIENTO DE TIERRAS

    09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION

    09.04 ACCESORIOS PARA TUBERIAS

    09.05 PRUEBA HIDRAULICA

    10 PLAN DE MANEJO AMBIENTAL

    10.01 ACTIVIDADES DE PREVENCION

    10.02 ACTIVIDADES DE MITIGACION

    10.03 ACTIVIDADES DE MONITOREO

    10.04 FLETE

    11 CAPACITACION TECNICA

    11.01 TRABAJOS DE CAMPO

    11.02 CONVOCATORIA

    11.03 DE LA CAPACITACION

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    9/18

    SUB PRES. PRES. TOTAL

    213,686.12

    120,391.21 120,391.21

    871.451,096.46

    117,364.48

    1,058.82

    54,570.99 54,570.99

    461.96

    29,370.77

    1,159.76

    22,073.16

    1,505.34

    21,444.94 21,444.94

    204.52

    115.54

    7,491.93

    12,527.60727.92

    377.43

    17,278.98 17,278.98

    126.24

    402.64

    1,464.83

    11,055.13

    1,284.34

    2,945.80

    316,012.96 316,012.96

    9,984.00

    162,766.58

    129,584.00

    6,731.186,947.20

    58,567.64 58,567.64

    2,588.77

    25,899.41

    19,458.98

    3,601.77

    5,556.61

    1,462.10

    62,691.56 62,691.56

    2,056.32

    21,396.18

    28,550.88

    3,601.77

    5,556.611,529.80

    72,988.33 72,988.33

    2,109.36

    30,017.70

    30,376.19

    3,601.77

    5,556.61

    1,326.70

    242,550.52 242,550.52

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    10/18

    8,207.68

    73,728.27

    7,565.33

    14,247.72

    18,317.21

    120,484.31

    467,026.68 467,026.68

    30,088.80

    171,896.99

    233,671.48

    3,825.78

    27,543.63

    32,116.92 32,116.92

    11,695.13

    18,772.99

    648.80

    1,000.00

    8,500.00 8,500.00

    1,200.00

    900.00

    6,400.00

    1,474,140.73 1,474,140.73 1,474,140.73

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    11/18

    Item Descripcin Und Metrado Precio (S/.)

    BOCATOMA

    01 OBRAS PROVISIONALES

    01.01 CARTEL DE IDENTIFICACION DE OBRA

    01.02 ALMACEN DE OBRA Y GUARDIANIA

    01.03 TRANSPORTE DE MAT. Y AGREGADOS

    01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO

    02 MUROS DE ENCAUZAMIENTO

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 OBRAS DE CONCRETO SIMPLE

    02.04 OBRAS DE CONCRETO ARMADO

    02.05 REVOQUES Y ENLUCIDOS

    03 PRESA DERIVADORA

    03.01 TRABAJOS PRELIMINARES

    03.02 MOVIMIENTO DE TIERRAS

    03.03 OBRAS DE CONCRETO SIMPLE

    03.04 OBRAS DE CONCRETO ARMADO

    03.05 REVOQUES Y ENLUCIDOS

    03.06 VARIOS04 TOMA O CAPTACION

    04.01 TRABAJOS PRELIMINARES

    04.02 MOVIMIENTO DE TIERRAS

    04.03 OBRAS DE CONCRETO SIMPLE

    04.04 OBRAS DE CONCRETO ARMADO

    04.05 REVOQUES Y ENLUCIDOS

    04.06 VARIOS

    05 LINEA DE CONDUCCION

    05.01 TRABAJOS PRELIMINARES

    05.02 MOVIMIENTO DE TIERRAS

    05.03 TENDIDO DE TUBERIAS EN LINEA DE CONDUCCION

    05.04 ACCESORIOS PARA TUBERIAS

    05.05 PRUEBA HIDRAULICA

    01 RESERVORIO DE GEOMENBRANA N 0101.01 TRABAJOS PRELIMINARES

    01.02 MOVIMIENTO DE TIERRAS

    01.03 GEOMENBRANA

    01.04 CAJA PARA VALVULAS

    01.05 ACCESORIOS DE RESERVORIO

    01.06 CERCO PERIMETRICO

    02 RESERVORIO DE GEOMENBRANA N 02

    02.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 GEOMENBRANA

    02.04 CAJA PARA VALVULAS

    02.05 ACCESORIOS DE RESERVORIO

    02.06 CERCO PERIMETRICO

    3 RESERVORIO DE GEOMENBRANA N 0302.01 TRABAJOS PRELIMINARES

    02.02 MOVIMIENTO DE TIERRAS

    02.03 GEOMENBRANA

    02.04 CAJA PARA VALVULAS

    02.05 ACCESORIOS DE RESERVORIO

    02.06 CERCO PERIMETRICO

    08 OBRAS DE ESTRUCTURAS HIDRAULICAS

    08.01 CAJA PARA VALVULAS DE CONTROL TIPO I (06 UNID)

    08.04 CAMARA ROMPE PRESION (11 UNID)

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    12/18

    08.05 CAMARA DISTRIBUIDORA DE CAUDALES ( 05 UNID.)

    08.06 CAMARA PARA VALVULA REGULADORA DE PRESION TIPO I (08 UNID)

    08.07 CAMARA PARA VALVULA DE PURGA TIPO I (12 UNID)

    08.08 CAMARA PARA HIDRANTE (75 UNID)

    09 RED DE DISTRIBUCION

    09.01 TRABAJOS PRELIMINARES

    09.02 MOVIMIENTO DE TIERRAS

    09.03 TENDIDO DE TUBERIAS EN LINEA DE DISTRIBUCION09.04 ACCESORIOS PARA TUBERIAS

    09.05 PRUEBA HIDRAULICA

    10 PLAN DE MANEJO AMBIENTAL

    10.01 ACTIVIDADES DE PREVENCION

    10.02 ACTIVIDADES DE MITIGACION

    10.03 ACTIVIDADES DE MONITOREO

    10.04 FLETE

    11 CAPACITACION TECNICA

    11.01 TRABAJOS DE CAMPO

    11.02 CONVOCATORIA

    11.03 DE LA CAPACITACION

    #REF!

    COSTO DIRECTO 1,474,140.73

    GASTOS GENERALES 10% 147,414.07

    UTLIDAD 10% 147,414.07

    =============

    SUB TOTAL DEL PROYECTO 1,768,968.88

    IGV 18% 318,414.40

    =============

    COSTO SUB TOTAL DEL PROYECTO 2,087,383.27

    EXPEDIENTE TECNICO 2.5% 36,853.52

    SUPERVISION 3% 44,224.22

    =============

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    13/18

    PRESUPUESTO TOTAL DEL PROYECTO 2,168,461.01

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    14/18

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    15/18

    Parcial (S/.) SUB PRES. PRES. TOTAL

    213,686.12

    120,391.21 120,391.21

    871.45

    1,096.46

    117,364.48

    1,058.82

    54,570.99 54,570.99

    461.96

    29,370.77

    1,159.76

    22,073.16

    1,505.34

    21,444.94 21,444.94

    204.52

    115.54

    7,491.93

    12,527.60

    727.92

    377.43

    17,278.98 17,278.98

    126.24

    402.64

    1,464.83

    11,055.13

    1,284.34

    2,945.80

    316,012.96 316,012.96

    9,984.00

    162,766.58

    129,584.00

    6,731.18

    6,947.20

    58,567.64 58,567.64

    2,588.77

    25,899.41

    19,458.98

    3,601.77

    5,556.61

    1,462.10

    62,691.56 62,691.56

    2,056.32

    21,396.18

    28,550.88

    3,601.77

    5,556.61

    1,529.80

    72,988.33 72,988.33

    2,109.36

    30,017.70

    30,376.19

    3,601.77

    5,556.61

    1,326.70

    242,550.52 242,550.52

    8,207.68

    73,728.27

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    16/18

    7,565.33

    14,247.72

    18,317.21

    120,484.31

    467,026.68 467,026.68

    30,088.80

    171,896.99

    233,671.48

    3,825.78

    27,543.63

    32,116.92 32,116.92

    11,695.13

    18,772.99

    648.80

    1,000.00

    8,500.00 8,500.00

    1,200.00

    900.00

    6,400.00

    1,474,140.73 1,474,140.73 1,474,140.73

    #REF! #REF!

    1,474,140.73

    147,414.07

    147,414.07

    =============

    1,768,968.88

    318,414.40

    =============

    2,087,383.27

    36,853.52

    44,224.22

    =============

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    17/18

    2,168,461.01

    Regin : Hunuco

    Provincia : Ambo

    Distrito : Colpas

    Lugar : Yapac

    COSTO DIRECTO 1,474,140.73

    GASTOS

    GENERALES

    10%

    147,414.07

    UTLIDAD 10% 147,414.07

    SUB TOTAL DEL

    PROYECTO

    1,768,968.88

    IGV 18% 318,414.40

    COSTO SUB

    TOTAL DEL

    PROYECTO

    2,087,383.27

    DESCRIPSION DEL COSTO

    RESUMEN DE INVERSION

    OBRA: INSTALACION DEL SERVICIO DE AGUA DEL SISTEMA

    DE RIEGO EN LA

    LOCALIDAD YAPAC-DISTRITO DE COLPAS, PROVINCIAAMBO, REGION HUANUCO

    RESUMEN DE GASTOS DE INVERSION

  • 7/28/2019 CRONOGRAMA CANAL YAPAC - ALTERNATIVA N O1

    18/18

    EXPEDIENTE

    TECNICO 2.5%

    36,853.52

    SUPERVISION

    3%

    44,224.22

    PRESUPUESTO

    TOTAL DEL

    PROYECTO

    2,168,461.01