CRONOGRAMA DE OBRA ACTUALIZADO-17-03-15.xlsx
-
Upload
cesar-jhonny-alvarado-romero -
Category
Documents
-
view
138 -
download
5
Transcript of CRONOGRAMA DE OBRA ACTUALIZADO-17-03-15.xlsx
CALENDARIO DE AVANCE DE OBRA ACELERADO
PROYECTO: INSTALACION DE LA REPRESA SUYARIDA EN EL DISTRITO DE SANTIAGO DE CHUCO, PROVINCIA DE SANTIAGO DE CHUCO - LA LIBERTAD
TIEMPO DE EJECUCION: 240 dias .
COSTO DIRECTO S/. 6,244,507.20
Sub Presupuesto MES
PART. PARTIDAS PTO MARZO 2014 ABRIL 2014 MAYO 2014 JUNIO 2014 JULIO 2014 AGOSTO 2014 SEPTIEMBRE 2014 OCTUBRE 2014NOVIEMBRE 201401 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 342,285.83 14,372.29 80,161.41 57,484.21 44,401.31 28,161.20 28,161.20 27,252.77 28,161.20 34,130.2302 CONSTRUCCION DE CAMPAMENTO PERMANENTE 35,055.00 0.00 0.00 0.00 0.00 0.00 35,055.00 0.00 0.00 0.0003 CONSTRUCCION DE LA PRESA 3,623,625.96 0.00 0.00 91,953.57 397,150.65 1,006,303.99 987,379.61 1,140,838.15 0.00 0.0003.01 ATAGUIA 35,425.80 0.00 0.00 6,523.72 28,902.08 0.00 0.00 0.00 0.00 0.0003.02 CIMENTACION DE PRESA 669,483.34 0.00 0.00 85,429.85 314,475.06 262,422.87 7,155.56 0.00 0.00 0.0003.03 CONFORMACION DE TERRAPLEN 2,702,200.56 0.00 0.00 0.00 0.00 620,606.61 980,224.04 1,101,369.91 0.00 0.0003.04 SISTEMA DE DRENAJE 39,468.24 0.00 0.00 0.00 0.00 0.00 0.00 39,468.24 0.00 0.0003.05 PANTALLA IMPERMEABLE 177,048.02 0.00 0.00 0.00 53,773.51 123,274.51 0.00 0.00 0.00 0.0004 DESCARGA DE FONDO 871,828.72 0.00 0.00 0.00 0.00 301,152.93 64,804.50 308,871.29 197,000.00 0.0004.01 CABEZAL DE ENTRADA 49,275.83 0.00 0.00 0.00 0.00 49,275.83 0.00 0.00 0.00 0.0004.02 TOMA DE TUBERIA - ESTRUCTURA DE INGRESO 407,218.03 0.00 0.00 0.00 0.00 210,218.03 0.00 0.00 197,000.00 0.0004.03 ALERONES EN PRESA 68,057.44 0.00 0.00 0.00 0.00 41,659.07 26,398.37 0.00 0.00 0.0004.04 CASETA DE VALVULAS - ENTREGA A LA QUEBRADA 235,528.93 0.00 0.00 0.00 0.00 0.00 38,406.13 197,122.80 0.00 0.0004.05 CAMARA ROMPEPRESION 111,748.49 0.00 0.00 0.00 0.00 0.00 0.00 111,748.49 0.00 0.0005 ALIVIADERO DE DEMASIAS - RAPIDA 1,300,945.85 0.00 0.00 0.00 0.00 0.00 0.00 21,886.71 698,569.93 580,489.2106 PLAN DE MANEJO AMBIENTAL 70,765.84 1,150.98 9,565.19 11,352.19 10,803.41 8,742.19 5,542.19 6,563.41 5,542.19 11,504.10
X Total Mensual 15,523.27 89,726.60 160,789.97 452,355.37 1,344,360.30 1,120,942.50 1,505,412.33 929,273.31 626,123.55
X % Avance Mensual 0.25% 1.44% 2.57% 7.24% 21.53% 17.95% 24.11% 14.88% 10.03%
X % Avance Mensual Acumulado 0.25% 1.69% 4.26% 11.50% 33.03% 50.98% 75.09% 89.97% 100.00%
CALENDARIO DE AVANCE DE OBRA ENERO - 2015PROYECTO: INSTALACION DE LA REPRESA SUYARIDA EN EL DISTRITO DE SANTIAGO DE CHUCO, PROVINCIA DE SANTIAGO DE CHUCO - LA LIBERTAD
TIEMPO DE EJECUCION: 240 dias . DEPARTAMENTO: LA LIBERTAD PROVINCIA: SANTIAGO DE CHUCO DISTRITO: SANTIAGO DE CHUCO LOCALIDAD: SUYADIRA
COSTO DIRECTO S/. 6,244,507.20 30,560.01 -5,441.37
1 2 3 4 5 6 7 8 9 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
86 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
190
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
218
219
220
221
222
223
224
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
251
252
###
###
###
###
###
###
###
###
### 1 2 3 4 5 6 7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77
Sub Presupuesto MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11
MARZO 2014 ABRIL 2014 MAYO 2014 JUNIO 2014 JULIO 2014 AGOSTO 2014 SETIEMBRE 2014 OCTUBRE 2014 NOVIEMBRE 2014 DICIEMBRE 2014 ENERO 2015
PART. PARTIDAS PTO PROG25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12 SEMANA 13 SEMANA 14 SEMANA 15 SEMANA 16 SEMANA 17 SEMANA 18 SEMANA 19 SEMANA 20 SEMANA 21 SEMANA 22 SEMANA 23 SEMANA 24 SEMANA 25 SEMANA 26 SEMANA 27 SEMANA 28 SEMANA 29 SEMANA 30 SEMANA 31 SEMANA 32 SEMANA 33 SEMANA 34 SEMANA 35 SEMANA 36 SEMANA 37 SEMANA 38 SEMANA 39 SEMANA 40 SEMANA 41 SEMANA 42 SEM.43 SEM.44
P01 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 342,285.83
E0.00 P 2,620.17 2,620.17 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
01.01 CARTEL DE IDENTIFICACION DE OBRA 3.60x2.40 (GIGFANTOGRAFIA) 5,240.34 ### ###E
22,864.72 P 5,976.38 - - - - - - - - 5,716.18 11,432.36 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 01.02 MOVILIZACION Y DESMOVILIZACION (D=210.0Km) 45,729.44 ### ### ######
E0.00 P 4,400.00 - - 8,800.00 8,800.00 4,400.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
01.03 CASETA DE GUARDIANIA, OFICINA Y ALMACEN 26,400.00 ###### ######### ###### ###E
13,856.41 P 1,346.78 2,665.86 3,817.19 3,817.19 3,817.19 3,817.19 5,766.25 3,817.19 3,817.19 3,817.19 1,908.60 1,908.60 1,908.60 1,908.60 3,817.19 3,817.19 3,817.19 4,317.19 1,908.60 1,908.60 1,908.60 1,908.60 10,740.44 1,900.37 1,900.37 1,900.37 1,900.37 271.48 2,072.37 2,417.76 2,417.76 2,417.76 1,381.58 1,574.59 3,674.05 3,674.05 3,674.05 3,149.18 524.86 3,674.05 3,674.05 1,054.29 1,054.29 301.23 753.07 1,054.29 1,054.29 1,054.29 01.04 REPLANTEO , CONTROL TOPOGRAFICO Y MONUMENTACION 125,967.36 #################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################### 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 6.67%#################################################################################### 1.09% 1.09%############ #########################################################
E28,772.04 P - - 1,200.00 11,118.33 14,531.33 12,883.33 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3,596.51
01.05 CONSTRUCCION DE CAMINOS DE ACCESO 68,504.85 ##################################################################### ###E
9,451.22 P - - - - 1,815.56 - 1,270.90 2,270.90 2,270.90 1,270.90 2,541.79 1,541.79 1,541.79 2,708.26 2,541.79 2,541.79 2,541.79 3,341.79 1,270.90 1,270.90 1,270.90 1,270.90 1,270.90 2,125.46 2,125.46 2,125.46 2,125.46 303.64 1,704.29 1,988.33 1,988.33 1,988.33 1,136.19 742.60 1,732.72 1,732.72 1,732.72 1,485.19 146.76 1,027.31 980.64 735.09 735.09 210.03 525.07 735.09 735.09 735.09 01.06 MANTENIMIENTO DE CAMINOS DE ACCESO 70,443.84 ############### ######################################################################################################################################################################################################################################################################################################################################################################################################################################################### 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 6.67%#################################################################################### 1.11% 1.11%############ #########################################################
EP
02 CONSTRUCCION DE CAMPAMENTO PERMANENTE 35,055.00
E2,220.15 P - 1,091.00 2,091.00 2,091.00 2,091.00 3,166.00 - - - - - - - - - - - - 200.00 500.00 500.00 1,000.00 1,800.00 2,657.22 2,657.22 2,657.22 2,657.22 379.60 1,190.32 1,388.71 1,388.71 1,388.71 793.55 214.64 500.82 500.82 500.82 429.27 - - - - - - 188.15 263.41 263.41 263.41
02.01 CONSTRUCCION DE CAMPAMENTO PERMANENTE 35,055.00 ######################################################################################################### ########################################################################################## ####################################################################################### 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### ############ #########################################################EP
03 CONSTRUCCION DE LA PRESA 3,623,625.96
EP
03.01 ATAGUIA 35,425.80
E0.00 P - - - - - - - 697.74 837.29 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.01.01 DESBROCE Y LIMPIEZA 1,535.03 #################################E
0.00 P - - - - - - - 461.65 1,384.94 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.01.02 EXCAVACION DE MATERIAL SUELTO C/EQUIPO 1,846.59 ########################
E0.00 P - - - - - - - - - - 8,641.14 7,200.95 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.01.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO 15,842.09 #################################E
0.00 P - - - - - - - - - - 9,439.77 1,573.29 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.01.04 TRANSPORTE DE MATERIAL GRANULAR 120 M < D <1.0 KM 11,013.06 #####################
E0.00 P - - - - - - - - - - 1,754.51 292.42 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.01.05 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM 2,046.93 #####################E
0.00 P - - - - - - - 349.12 2,443.86 349.12 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.01.06 ELIMINACION DE MATERIAL EXCEDENTE (D = 0.5 Km) 3,142.10 ###########################
EP
03.02 CIMENTACION DE PRESA 669,483.34
E614.01 P - - - - - - 3,947.22 964.88 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 19.81 - - -
03.02.01 DESBROCE Y LIMPIEZA 5,526.11 ##################### ###E
766.48 P - - - - - - 2,372.98 4,152.72 4,152.72 1,013.27 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.02.02 EXCAVACION DE MATERIAL SUELTO C/EQUIPO 12,458.17 ###############################################################
E6,622.90 P - - - - - - - - 16,614.44 20,433.68 15,433.68 14,410.78 18,933.68 15,433.68 5,433.68 5,333.68 409.64 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.02.03 EXCAVACION DE ROCA SUELTA C/EQUIPO 119,059.84 ##################################################################################################################################################################E
47,425.87 P - - - - - - - - - 45,855.01 57,247.51 56,953.01 58,821.64 55,247.51 3,247.51 13,747.51 13,247.51 1,462.54 - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.02.04 EXCAVACION DE ROCA FIJA C/EQUIPO 353,550.12 ####################################################################################################################################################################################
E9,565.73 P - - - - - - - - 35,200.00 22,181.00 28,106.40 25,469.00 25,469.00 5,515.32 5,620.00 2,988.50 2,125.00 1,350.00 1,350.00 1,350.00 1,350.00 3,000.00 2,353.45 2,353.45 2,353.45 2,353.45 336.21 - - - - - - - - - - - - - - - - - - - -
03.02.05 ELIMINACION DE MATERIAL EXCEDENTE (D = 0.5 Km) 178,889.10 ########################################################################################################################################################################################################################################################################################################################################################################################## 3.45%EP - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03 CONFORMACION DE TERRAPLEN 2,702,200.56
E1,043,918.54 P - - - - - - - - - - - - - - - 6,028.45 6,028.45 6,028.45 6,028.45 861.21 11,601.29 13,534.84 13,534.84 13,534.84 7,734.19 7,477.82 17,448.24 17,448.24 17,448.24 14,955.63 5,631.33 39,419.31 34,781.74 85,969.76 -101,365.46 24,562.79 61,406.97 85,969.76 85,969.76 85,969.76
03.03.01 RELLENO CON MATERIAL GRAVO - ARCILLOSO 1,288,081.63 #################################################################################### 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 6.67%#################################################################################### 1.18% 1.18%############ #########################################################E
61,335.80 P - - - - - - - - - - - - - - - - - - - - - - - - - - - 360.59 2,524.14 2,524.14 3,833.49 6,227.57 1,533.40 3,833.49 4,506.19 5,366.88 5,366.88 03.03.02 RELLENO CON FILTRO DE ARENA 66,744.67 6.67%########################################## #################################### 1.25% 1.25%############ #########################################################
E19,718.98 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO 19,718.98
E183,966.56 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.04 RELLENO CON GRAVA GRUESA PARA PROTECCION 183,966.56
E239,452.66 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.05 ENROCADO DE PROTECCION Dmax = 0.50M 239,452.66
E2,475.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.06 RELLENO COMPACTADO CON MATERIAL DE AFIRMADO 2,475.00
E58,877.66 P - - - - - - - - - - - - - - - 37,388.70 37,499.00 53,226.00 31,499.03 31,961.20 24,676.00 20,650.00 20,235.00 2,766.21 2,766.21 2,766.21 2,766.21 395.17 27,356.13 31,915.48 31,915.48 31,915.48 18,237.42 3,056.00 7,130.67 7,130.67 7,130.67 6,112.00 - - - - - -21,422.46 4,205.55 5,887.77 5,887.77 5,887.77
03.03.07 TRANSPORTE DE MATERIAL GRANULAR 120 M < D <1.0 KM 506,833.78 ###################################################################################################################################################################################################################################################### 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 1.43% 1.43%############ #########################################################E
159.75 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - 34.95 34.95 9.98 24.96 34.95 19.97 - 03.03.08 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM 159.75 ########################################## 3.13% 3.13%############ ####################################
E50,069.54 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.09 TRANSPORTE DE ROCA 120 M < D <1.0 KM 50,069.54
E120,005.90 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.10 GEOMEMBRANA HPDE e = 1.5mm 120,005.90
E63,658.06 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.11 GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P 63,658.06
E161,034.03 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.03.12 GEOCOMPUESTO DE DRENAJE ENKADRAN TYPE B10/1-2S 161,034.03
EP
03.04 SISTEMA DE DRENAJE 39,468.24
E4,780.96 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.01 RELLENO COMPACTADO CON FILTRO DE GRAVA 4,780.96
E1,343.88 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.02 TRANSPORTE DE MATERIAL GRANULAR 120 M < D <1.0 KM 1,343.88
E2,497.50 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.03 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM 2,497.50
E14,196.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.04 TUBERIA PVC D=200mm (INCL. SUMINISTRO Y COLOCACION) 14,196.00
E15,281.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.05 TUBERIA PVC PERFORADA D=200mm (INCL. SUMINISTRO Y COLOCACION) 15,281.00
E1,368.90 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.04.06 GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P 1,368.90
EP
03.05 PANTALLA IMPERMEABLE 177,048.02
E0.00 P - - - - - - - - - - - 19,888.20 59,677.40 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.05.01 PERFORACION DIAMANTINA NQ O NX S/RECUPERACION DE TESTIGOS 79,552.80 ############E
0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.05.02 PERFORACION PARA INYECCION DE DRENES D = 2" 0.00 ###############
E0.00 P - - - - - - - - - - - 7,182.42 3,590.76 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.05.03 INYECCION DE CONSOLIDACION E IMPERMEABILIZACION 10,773.63 ##################E
0.00 P - - - - - - - - - - - 12,236.94 6,118.47 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.05.04 SUMINISTRO DE CEMENTO TIPO I 18,355.41 ##################
E0.00 P - - - - - - - - - - - 590.19 295.09 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
03.05.05 SUMINISTRO DE BENTONITA 885.28 ##################E
0.00 P - - - - - - - - - - - 542.27 271.13 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 03.05.06 SUMINISTRO DE ADITIVO PLASTIFICANTE 813.40 ##################
EP
04 DESCARGA DE FONDO 871,828.72
EP
04.01 CABEZAL DE ENTRADA 49,275.83
E8,636.55 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.01.01 CONCRETO CICLOPEO 1:10 + 30% P.G. 8,636.55
E20,142.45 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.01.02 CONCRETO 210 KG/CM2 (Dcant = 20.0 km) 20,142.45
E6,837.40 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.01.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 6,837.40
E13,659.43 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.01.04 ACERO DE REFUERZO fy=4,200 kg/cm2 13,659.43
EP
04.02 TOMA DE TUBERIA - ESTRUCTURA DE INGRESO 407,218.03
E5,314.80 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.01 CONCRETO CICLOPEO 1:10 + 30% P.G. 5,314.80
E27,432.02 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.02 CONCRETO 75 KG/CM2 (Dcant = 20.0 km) 27,432.02
E12,950.84 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 12,950.84
E6,905.89 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.04 CAMA DE APOYO PARA TUBERIAS 6,905.89
E156,324.48 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.05 TUBERIA GRP D = 700 MM (INCL. SUMINISTRO Y COLOCACION) 156,324.48
E640.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.06 CODO PARA GRP DE 135º D = 700 MM (INCL. SUMINISTRO Y COLOCACION) 640.00
E650.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.07 YEE PARA GRP D = 700 MM (INCL. SUMINISTRO Y COLOCACION) 650.00
E197,000.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.02.08 VALVULA DE 700 MM (INCL. SUMINISTRO Y COLOCACION) 197,000.00
EP
04.03 ALERONES EN PRESA 68,057.44
E62,560.08 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.03.01 CONCRETO 210 KG/CM2 (Dcant = 20.0 km) 62,560.08
E2,996.39 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.03.02 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 2,996.39
E2,500.97 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.03.03 ACERO DE REFUERZO fy=4,200 kg/cm2 2,500.97
EP
04.04 CASETA DE VALVULAS - ENTREGA A LA QUEBRADA 235,528.93
E79.02 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.01 EXCAVACION DE ROCA FIJA C/EQUIPO 79.02
E22.10 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.02 ELIMINACION DE MATERIAL EXCEDENTE (D = 0.5 Km) 22.10
E1,310.72 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.03 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 1,310.72
E13,704.77 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.04 CONCRETO 210 KG/CM2 (Dcant = 20.0 km) 13,704.77
E930.09 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.05 CONCRETO CICLOPEO 1:10 + 30% P.G. 930.09
E7,030.46 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.06 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 7,030.46
E15,328.97 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.07 ACERO DE REFUERZO fy=4,200 kg/cm2 15,328.97
E62,762.80 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.08 VALVULA MARIPOSA DE Fº Fº DE 24" 62,762.80
E70,800.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.09 VALVULA CUCHILLA DE 24" 70,800.00
E1,160.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.10 MANOMETRO DE CONTROL 1,160.00
E62,400.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.04.11 BRIDA DRESSER PARA UNION DE VALVULAS 62,400.00
EP
04.05 CAMARA ROMPEPRESION 111,748.49
E392.76 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.01 EXCAVACION DE ROCA FIJA C/EQUIPO 392.76
E109.85 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.02 ELIMINACION DE MATERIAL EXCEDENTE (D = 0.5 Km) 109.85
E151.34 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.03 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 151.34
E2,989.58 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.04 CONCRETO CICLOPEO 1:10 + 30% P.G. 2,989.58
E586.20 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.05 CONCRETO 100 KG/CM2 (Dcant = 20.0 km) 586.20
E38,317.23 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.06 CONCRETO 280 KG/CM2 (Dcant = 20.0 km) 38,317.23
E8,860.47 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.07 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 8,860.47
E58,223.54 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.08 ACERO DE REFUERZO fy=4,200 kg/cm2 58,223.54
E2,117.52 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
04.05.09 TAPA JUNTA WS 4" 2,117.52
EP
05 ALIVIADERO DE DEMASIAS - RAPIDA 1,300,945.85
E0.00 P - - - - - - - - - - - - - - - - - - - - - - - 635.31 635.31 635.31 635.31 90.76 2,235.33 2,607.89 2,607.89 2,607.89 1,490.22 - - - - - - - - - - - - - - -
05.01 EXCAVACION DE ROCA SUELTA C/EQUIPO 14,181.22 #################################################################################### 3.45%################################################################################# ### ### ### ###E
0.00 P - - - - - - - - - - - - - - - - - - - - - - - 841.45 841.45 841.45 841.45 120.21 18,713.30 21,832.18 21,832.18 21,832.18 12,475.53 - - - - - - - - - - - - - - - 05.02 EXCAVACION DE ROCA FIJA C/EQUIPO 100,171.37 #################################################################################### 3.45%################################################################################# ### ### ### ###
E0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,321.32 880.88 - - - 62.89 440.25 440.25 - - - - - - -
05.03 PERFILADO DE TALUDES 3,146.10 ### ### ######### 6.67%########################################## ######E
0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - 10,693.55 12,475.81 12,475.81 12,475.81 7,129.03 - 110.50 110.50 - - - - - - - - - - - - 05.04 ELIMINACION DE MATERIAL EXCEDENTE (D = 0.5 Km) 55,471.00 ################################################################################# ### ### ### ### ########################
E39,661.70 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
05.05 CONCRETO CICLOPEO 1:10 + 30% P.G. 39,661.70
E84,149.01 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
05.06 CONCRETO 100 KG/CM2 (Dcant = 20.0 km) 84,149.01
E464,618.88 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
05.07 CONCRETO 210 KG/CM2 (Dcant = 20.0 km) 464,619.18
E115,338.89 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
05.08 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS 115,338.89
E120,931.38 P - - - - - - - - - - - - - - - - - - - - - - - - - - - 38,932.26 45,420.97 45,420.97 45,420.97 25,954.84 - - - - - 4,470.00 31,290.00 31,290.00 - - - - - - -
05.09 ACERO DE REFUERZO fy=4,200 kg/cm2 389,131.38 ################################################################################# ### ### ### ### 6.67%##########################################E
20,881.10 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 05.10 TAPA JUNTA WS 4" 20,881.10
E14,194.90 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
05.11 JUNTA ELASTOMERICA 14,194.90
EP
06 PLAN DE MANEJO AMBIENTAL 70,765.84
EP
06.01 PROGRAMA DE MEDIDAS PREVENTIVAS CORRECTIVAS Y/O MITIGACION 30,000.00
E4,375.00 P - 208.33 437.50 437.50 875.00 875.00 437.50 437.50 875.00 875.00 437.50 437.50 437.50 437.50 875.00 875.00 875.00 875.00 437.50 437.50 437.50 437.50 1,397.00 844.83 844.83 844.83 844.83 120.69 304.84 355.65 355.65 355.65 203.23 350.00 816.67 816.67 816.67 700.00 133.00 931.00 931.00 332.88 332.88 95.11 237.77 332.88 332.88 332.88
06.01.01 ESPECIALISTA AMBIENTAL (RESIDENTE) 28,000.00 ############################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################ 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 6.67%#################################################################################### 1.09% 1.09%############ #########################################################E
0.00 P 400.00 - - - - - - - 800.00 800.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 06.01.02 SEÑALES INFORMATIVAS Y PREVENTIVAS 2,000.00 ### ############
EP
06.02 PROGRAMA DE MANEJO DE RESIDUOS 12,176.00
E800.00 P - 800.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 119.15 119.15 34.04 85.11 119.15 119.15 119.15
06.02.01 BAÑOS QUIMICOS 1,600.00 ### ########################################## 2.13% 2.13%############ #########################################################E
819.64 P 216.38 316.38 475.69 316.38 316.38 316.38 316.38 316.38 316.38 216.38 316.38 316.38 316.38 216.38 316.38 316.38 316.38 266.38 316.38 316.38 316.38 316.38 319.10 319.10 319.10 319.10 45.59 255.87 298.52 298.52 298.52 170.58 50.24 117.22 117.22 117.22 100.47 - - - 62.36 62.36 17.82 44.55 62.36 62.36 62.36 06.02.02 ACOPIO DE RESIDUOS SOLIDOS 10,576.00 ################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################## 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### ########################################## 1.09% 1.09%############ #########################################################
EP
06.03 PROGRAMA DE MONITOREO AMBIENTAL 4,800.00
E804.00 P - - - - - - 1,200.00 - - - - - - - - - - - 1,200.00 - - - - 289.66 289.66 289.66 289.66 41.38 - - - - - - - 396.00 - - - - - - - - - 201.00 - -
06.03.01 MONITOREO DEL LA CALIDAD DEL AGUA 4,800.00 ### ### #################################################################################### 3.45% ######### ###EP
06.04 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL 5,500.00
E0.00 P 998.22 1,001.78 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2,000.00 - - - - - - - - - - -
06.04.01 CAPACITACION EN MEDIO AMBIENTE AL PERSONAL DE OBRA 4,000.00 ############### #########E
0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,500.00 - - - - - - - - 06.04.02 CAPACITACION EN CONCIENTIZACION DE LA POBLACION SOBRE RIESGOS Y 1,500.00 #########
EP
06.05 PROGRAMA DE CONTINGENCIA 6,500.00
E0.00 P 1,250.00 - - - 892.86 357.14 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
06.05.01 EQUIPO DE PRIMEROS AUXILIOS 2,500.00 ##################### #####################E
0.00 P - 1,000.00 - - - 714.29 285.71 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 06.05.02 EQUIPO CONTRA INCENDIO 2,000.00 ##################### #####################
E0.00 P 60.09 60.09 60.09 50.09 60.09 60.09 60.09 60.09 50.09 60.09 60.09 60.09 50.09 60.09 60.09 60.09 50.09 40.09 60.09 60.09 59.09 50.09 30.17 30.17 30.17 30.17 4.31 45.97 53.63 53.63 53.63 30.65 15.00 35.00 35.00 35.00 30.00 15.83 110.83 110.83 - - - - - - -
06.05.03 EQUIPO DE RADIO COMUNICACIONES 2,000.00 ################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################## 3.45%################################################################################# ### ### ### ### ### ### ################################################################################# ### 6.67%##########################################EP
06.06 PROGRAMA DE RELACIONES COMUNITARIAS 3,900.00
E0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,750.00 - - - - 1,750.00 - - - - - - -
06.06.01 EDUCACION AMBIENTAL A LA POBLACION 3,500.00 ################## ############E
0.00 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 200.00 - - 200.00 - - - - - - - - 06.06.02 AFICHES INFORMATIVOS 400.00 ############ #########
EP
06.07 PROGRAMA DE CIERRE Y ABANDONO DE OBRA 7,889.84
E3,781.68 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
06.07.01 REHABILITACION DE AREAS 3,781.68
E4,108.16 P - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
06.07.02 RESTAURACION DE AREAS 4,108.16
E
Total Semanal 16,991.55 9,663.62 7,922.16 26,799.80 32,296.55 27,125.14 16,014.17 13,646.09 32,772.81 116,091.73 132,094.33 112,801.20 107,488.68 101,458.19 88,374.46 110,140.36 131,707.95 65,713.99 38,172.49 37,804.66 30,519.46 26,992.46 38,809.81 20,791.67 20,791.67 20,791.67 20,791.67 2,970.24 115,105.50 134,289.77 134,289.77 134,289.77 76,736.99 14,802.19 32,446.75 33,711.87 33,655.37 26,961.75 11,345.27 81,116.89 76,482.65 92,141.97 -92,799.17 5,341.94 71,324.50 99,166.85 99,811.56 103,388.10
Total Mensual 16,991.55 84,432.17 164,730.82 487,011.45 412,296.43 150,394.98 86,136.94 594,711.80 141,577.93 173,629.55 449,466.37
% Avance Mensual 0.27% 1.35% 2.64% 7.80% 6.60% 2.41% 1.38% 9.52% 2.27% 2.78% 7.20%
% Avance Mensual Acumulado 0.27% 1.62% 4.26% 12.06% 18.66% 21.07% 22.45% 31.98% 34.24% 37.01% 44.22%
Admin:
8 9 ###
###
###
###
###
15 16 17 ###
###
###
21 ###
###
24 ###
###
###
###
###
###
31 ###
###
###
###
###
###
38 ###
###
41 42 43 44 45 ###
###
###
###
###
###
52 ###
###
###
###
###
###
59 60
MES 11 MES 12 MES 13
ENERO 2015 FEBRERO 2015 MARZO 201524 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
SEM.44 SEM.45 SEM.46 SEM.47 SEM.48 SEM.49 SEM.50 SEM.51
- - - - - - - - - - -
- - - - - - - - - 20,006.63 2,858.09
################## ### 0.13
- - - - - - - - - - -
1,054.29 753.07 301.23 1,054.29 1,054.29 1,054.29 753.07 301.23 1,054.29 1,054.29 150.61
##################### ### 1.09% ############ 1.09%###### ##################### ##################### ######### ###### 1.09% 1.09% 1.09%################## ##################### ### 1.09%
3,596.51 4,495.63 1,798.25 6,293.88 6,293.88 6,293.88 - - - - -
##################### ### 3.13% ############ 3.13%###### ##################### ##################### ###
735.09 525.07 210.03 735.09 735.09 735.09 525.07 210.03 735.09 630.08 -
##################### ### 1.11% ############ 1.11%###### ##################### ##################### ######### ###### 1.11% 1.11% 1.11%################## #####################
263.41 188.15 75.26 263.41 263.41 263.41 188.15 - - - -
##################### ### 1.69% ############ 1.69%###### ##################### ##################### ######### ###### 1.69%
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - 537.26 76.75
################## ### 12.50%
- - - - - - - - - 670.67 95.81
################## ### 12.50%
- - - - - - - - - 15,795.04 827.86
################## ### 12.50%
- - - - - - - - - 48,697.64 5,928.23
################## ### 12.50%
- - - - - - - - - 8,370.01 1,195.72
################## ### 12.50%
85,969.76 61,406.97 ### 85,969.76 85,969.76 85,969.76 61,406.97 24,562.79 273,304.98 - -
##################### ### 1.18% ############ 1.18%###### ##################### ##################### ######### ###### 1.18% 1.18% 1.18%################## ###
5,366.88 3,833.49 1,533.40 5,366.88 5,366.88 5,366.88 3,833.49 1,533.40 3,833.49 - -
##################### ### 1.25% ############ 1.25%###### ##################### ##################### ######### ###### 1.25% 1.25% 1.25%###############
- - - - 4,182.81 4,182.81 2,987.72 1,195.09 4,182.81 2,987.72 -
################## ##################### ######### ###### 3.03% 3.03% 3.03%################## ##################
- - - 10,512.37 36,793.31 36,793.31 26,280.94 10,512.37 36,793.31 26,280.94 -
### ##################### ##################### ######### ###### 2.86% 2.86% 2.86%################## ##################
- - - - - - - 34,207.52 119,726.33 85,518.81 -
7.14% 7.14%################## ##################
- - - - - - - - - 2,475.00 -
################## ###
5,887.77 4,205.55 1,682.22 5,887.77 5,887.77 5,887.77 4,205.55 1,682.22 28,992.45 - -
##################### ### 1.43% ############ 1.43%###### ##################### ##################### ######### ###### 1.43% 1.43% 1.43%################## ###
- - - - - - - - - - -
- - - - - 16,689.85 11,921.32 4,768.53 16,689.85 - -
################## ######### ###### 4.76% 4.76% 4.76%################## ###
- - - - - - - - 120,005.90 -
############ ###
- - - - - - - - - 63,658.06 -
###############
- - - - - - - - - 161,034.03 -
###############
- - - - - - - 562.47 1,968.63 1,968.63 281.23
5.88% 5.88%################## ##################### ### 5.88%
- - - 335.97 335.97 335.97 239.98 95.99 - - -
######### 3.57%###### ##################### ##################### ######### ###### 3.57% 3.57% 3.57%
- - 178.39 624.38 624.38 624.38 445.98 - - - -
3.57% ############ 3.57%###### ##################### ##################### ######### ###### 3.57%
- - - - - - 3,226.36 1,290.55 4,516.91 4,516.91 645.27
###### ###### 4.55% 4.55% 4.55%################## ##################### ### 4.55%
- - - - - - 3,472.95 1,389.18 4,862.14 4,862.14 694.59
###### ###### 4.55% 4.55% 4.55%################## ##################### ### 4.55%
- - - - - - 311.11 124.45 435.56 435.56 62.22
###### ###### 4.55% 4.55% 4.55%################## ##################### ### 4.55%
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - 4,318.28 - - - 4,318.28 - -
### ###
- - - - - 10,071.23 - - - 10,071.23 -
### ###
- - - - 2,279.13 1,139.57 - - - 3,418.70 -
### ###### #########
- - - - 6,829.72 - - - 4,553.14 2,276.57 -
######### ### ######
- - - 3,986.10 1,328.70 - - - - - -
###### ######
- - - - - 27,432.02 - - - - -
###############
- - - - 5,755.93 7,194.91 - - - - -
######### ##################
- - - - 6,905.89 - - - - - -
############ ###
- - - 117,243.36 39,081.12 - - - - - -
###### ######
- - - 320.00 320.00 - - - - - -
######
- - - 325.00 325.00 - - - - - -
######
- - - - - - - 131,333.33 65,666.67 - -
33.33% 33.33%###
- - - - 41,706.72 20,853.36 - - - - -
### ######
- - - - 2,996.39 - - - - - -
#########
- - - 833.66 1,667.31 - - - - - -
#########
- - - - - - - 79.02 - - -
100.00%
- - - - - - - - 22.10 - -
######
- - - - - - - - 1,310.72 - -
######
- - - - - - - - - 13,704.77 -
#########
- - - - - - 930.09 - - - -
###
- - - - - - 1,171.74 1,171.74 4,101.10 585.87 -
### 8.33% 8.33% 8.33%################## ######
- - - - - - 9,580.61 3,832.24 1,916.12 - -
###### ###### 12.50% 12.50% 12.50%###
- - - - - - - - - 62,762.80 -
###### ###
- - - - - - - - - 35,400.00 35,400.00
### 50.00%
- - - - - - - - - 580.00 580.00
### 50.00%
- - - - - - - - - 31,200.00 31,200.00
### 50.00%
- - - - 130.92 261.84 - - - - -
#########
- - - - 36.62 73.23 - - - - -
#########
- - - - - 151.34 - - - - -
######
- - - - - - - 2,989.58 - - -
50.00% 50.00%
- - - - - 586.20 - - - - -
######
- - - - - - - - 8,514.94 29,802.29 -
### ##################### ###
- - - - - - - 2,215.12 6,645.35 - -
12.50% 12.50%##################
- - - - - - - 23,289.42 34,934.12 - -
20.00% 20.00%#########
- - - - - - - 529.38 1,588.14 - -
25.00%#########
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - 29,746.28 9,915.43 - - -
###### 25.00% 25.00%
- - - - - - - 28,049.67 56,099.34 - -
16.67% 16.67%############
- - - - - - - 54,661.04 191,313.66 191,313.66 27,330.52
5.88% 5.88%################## ##################### ### 5.88%
- - - - - - - 16,476.98 57,669.45 41,192.46 -
7.14% 7.14%################## ##################
- - - - - - - 20,155.23 70,543.31 30,232.85 -
8.33% 8.33%################## ############
- - - - - - - 6,960.37 13,920.73 - -
16.67% 16.67%############
- - - - - - - - 2,838.98 9,936.43 1,419.49
### ##################### ### 10.00%
332.88 237.77 95.11 332.88 332.88 332.88 237.77 95.11 332.88 332.88 47.55
##################### ### 1.09% ############ 1.09%###### ##################### ##################### ######### ###### 1.09% 1.09% 1.09%################## ##################### ### 1.09%
- - - - - - - - - - -
119.15 85.11 - - - - - - - - -
##################### ###
62.36 44.55 17.82 62.36 62.36 62.36 44.55 17.82 62.36 62.36 8.91
##################### ### 1.09% ############ 1.09%###### ##################### ##################### ######### ###### 1.09% 1.09% 1.09%################## ##################### ### 1.09%
- - - 402.00 - - - 201.00 - - -
25.00%### 25.00%
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - - - - -
- - - - - - - 756.34 2,647.18 378.17 -
10.00% 10.00%################## ######
- - - - - - - - 2,054.08 2,054.08 -
################## ##################### ###
103,388.10 75,775.36 30,454.50 240,549.16 261,584.52 232,356.34 161,509.70 385,164.64 1,028,148.49 1,034,810.44 108,802.85
449,466.37 926,454.22 2,556,926.42
7.20% 14.84% 40.95%
44.22% 59.06% 100.00%
OBRA : INSTALACION DE LA REPRESA SUYARIDA EN EL DISTRITO DE SANTIAGO DE CHUCO, PROVINCIA DE SANTIAGO DE CHUCO- LA LIBERTADPROPIETARIO : MINISTERIO DE AGRICULTURA - PROGRAMA SUBSECTORIAL DE IRRIGACIONES (PSI)UBICACIÓN : REGION LA LIBERTAD - PROVINCIA SANTIAGO DE CHUCO- DISTRITO SANTIAGO DE CHUCOCONTRATISTA : CONSORCIO COGAFE CAJAMARCASUPERVISOR : ING. LUIS RIVAS MECHATOMONTO CONTRATADO : S/. 8'584,389.20
VALORIZACION DE OBRA Nº 10 – PRIMERA QUINCENA DE DICIEMBRE DEL 201401 de Diciembre al 15 de Diciembre del 2014
Item DescripciónPRESUPUESTO OFERTADO ACUMULADO MES ANTERIOR PRESENTE VALORIZACION ACUMULADO MES ACTUAL SALDO POR VALORIZAR
Und. Metrado P.U. MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/.01 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 342,285.83 - 257,267.11 10,074.33 267,341.44 74,944.39
01.01 CARTEL DE OBRA 4.80X3.60 M. (GIGANTOGRAFÍA) und 3.00 1,746.78 5,240.34 3.00 5,240.34 - 3.00 5,240.34 - - 01.02 MOVILIZACIÓN Y DESMOVILIZACIÓN (D=210.0 Km) glb 1.00 45,729.44 45,729.44 0.50 22,864.72 - 0.50 22,864.72 0.50 22,864.72 01.03 CASETA DE GUARDIANÍA, OFICINA Y ALMACÉN m2 120.00 220.00 26,400.00 120.00 26,400.00 - 120.00 26,400.00 - - 01.04 REPLANTEO, CONTROL TOPOGRÁFICO Y MONUMENTACIÓN mes 8.00 15,745.92 125,967.36 6.62 104,237.99 0.50 7,872.96 7.12 112,110.95 0.88 13,856.41 01.05 CONSTRUCCIÓN DE CAMINOS DE ACCESO km 5.00 13,700.97 68,504.85 2.90 39,732.81 - 2.90 39,732.81 2.10 28,772.04 01.06 MANTENIMIENTO DE CAMINOS DE ACCESO KM-MES 24.00 2,935.16 70,443.84 20.03 58,791.25 0.75 2,201.37 20.78 60,992.62 3.22 9,451.22 02 CONSTRUCCION DE CAMPAMENTO PERMANENTE 35,055.00 - 32,834.85 0.00 32,834.85 2,220.15
02.01 CONSTRUCCION DE CAMPAMENTO PERMANENTE m2 57.00 615.00 35,055.00 53.39 32,834.85 - 53.39 32,834.85 3.61 2,220.15 03 CONSTRUCCIÓN DE LA PRESA 3,623,625.96 - 1,424,611.43 89,878.82 1,514,490.24 2,109,135.71
03.01 ATAGUÍA 35,425.80 - 35,425.80 0.00 35,425.80 0.00
03.01.01 DESBROCE Y LIMPIEZA ha 0.50 3,070.06 1,535.03 0.50 1,535.03 - 0.50 1,535.03 - - 03.01.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 483.40 3.82 1,846.59 483.40 1,846.59 - 483.40 1,846.59 - - 03.01.03 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 1,441.50 10.99 15,842.09 1,441.50 15,842.09 - 1,441.50 15,842.09 - - 03.01.04 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 1,441.50 7.64 11,013.06 1,441.50 11,013.06 - 1,441.50 11,013.06 - - 03.01.05 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 1,441.50 1.42 2,046.93 1,441.50 2,046.93 - 1,441.50 2,046.93 - - 03.01.06 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 483.40 6.50 3,142.10 483.40 3,142.10 - 483.40 3,142.10 - - 03.02 CIMENTACIÓN DE PRESA 669,483.34 - 604,488.34 0.00 604,488.34 64,994.99
03.02.01 DESBROCE Y LIMPIEZA ha 1.80 3,070.06 5,526.11 1.60 4,912.10 - 1.60 4,912.10 0.20 614.01 03.02.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 3,261.30 3.82 12,458.17 3,060.65 11,691.68 - 3,060.65 11,691.68 200.65 766.48 03.02.03 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 9,047.10 13.16 119,059.84 8,543.84 112,436.93 - 8,543.84 112,436.93 503.26 6,622.90 03.02.04 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 15,213.00 23.24 353,550.12 13,172.30 306,124.25 - 13,172.30 306,124.25 2,040.70 47,425.87 03.02.05 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 27,521.40 6.50 178,889.10 26,049.75 169,323.38 - 26,049.75 169,323.38 1,471.65 9,565.73 03.03 CONFORMACIÓN DE TERRAPLÉN 2,702,200.56 - 607,649.27 89,878.82 697,528.08 2,004,672.48
03.03.01 RELLENO CON MATERIAL GRAVO-ARCILLOSO m3 128,937.10 9.99 1,288,081.63 15,985.30 159,693.15 8,455.45 84,469.95 24,440.75 244,163.09 104,496.35 1,043,918.54 03.03.02 RELLENO CON FILTRO DE ARENA m3 3,629.40 18.39 66,744.67 - - 294.12 5,408.87 294.12 5,408.87 3,335.28 61,335.80 03.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,353.10 8.38 19,718.98 - - - - - 2,353.10 19,718.98 03.03.04 RELLENO CON GRAVA GRUESA PARA PROTECCIÓN m3 5,167.60 35.60 183,966.56 - - - - - 5,167.60 183,966.56 03.03.05 ENROCADO DE PROTECCIÓN Dmax.=0.50 M. m3 6,985.20 34.28 239,452.66 - - - - - 6,985.20 239,452.66 03.03.06 RELLENO COMPACTADO CON MATERIAL DE AFIRMADO m3 112.50 22.00 2,475.00 - - - - - 112.50 2,475.00 03.03.07 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 66,339.50 7.64 506,833.78 58,633.00 447,956.12 - 58,633.00 447,956.12 7,706.50 58,877.66 03.03.08 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 112.50 1.42 159.75 - - - - - 112.50 159.75 03.03.09 TRANSPORTE DE ROCA 120 M < D < 1.0 KM. m3k 6,076.40 8.24 50,069.54 - - - - - 6,076.40 50,069.54
03.03.10 m2 9,023.00 13.30 120,005.90 - - - - - 9,023.00 120,005.90
03.03.11 m2 9,068.10 7.02 63,658.06 - - - - - 9,068.10 63,658.06
03.03.12 GEOCOMPUESTO DE DRENAJE ENKANDRAIN TYPE B10/1-2S m2 6,449.10 24.97 161,034.03 - - - - - 6,449.10 161,034.03 03.04 SISTEMA DE DRENAJE 39,468.24 - 0.00 0.00 0.00 39,468.24
03.04.01 RELLENO COMPACTADO CON FILTRO DE GRAVA m3 175.90 27.18 4,780.96 - - - - - 175.90 4,780.96 03.04.02 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 175.90 7.64 1,343.88 - - - - - 175.90 1,343.88 03.04.03 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 1,758.80 1.42 2,497.50 - - - - - 1,758.80 2,497.50 03.04.04 TUBERIA PVC D=200 mm. (INC. SUMINISTRO Y COLOCACION) m 195.00 72.80 14,196.00 - - - - - 195.00 14,196.00 03.04.05 TUBERIA PVC PERFORADA D=200 mm. (INC. SUMINISTRO Y COLOCACION) m 185.00 82.60 15,281.00 - - - - - 185.00 15,281.00
03.04.06 m2 195.00 7.02 1,368.90 - - - - - 195.00 1,368.90
03.05 PANTALLA IMPERMEABLE 177,048.02 - 177,048.02 0.00 177,048.02 0.00
03.05.01 PERFORACIONES DIAMANTINA NQ O NX S/RECUPERACIÓN DE TESTIGOS m 120.00 662.94 79,552.80 120.00 79,552.80 - 120.00 79,552.80 - - 03.05.02 PERFORACIONES PARA INYECCIÓNES Y DRENES D=2" m 225.00 296.30 66,667.50 225.00 66,667.50 - 225.00 66,667.50 - - 03.05.03 INYECCIONES DE CONSOLIDACIÓN E IMPERMEABILIZACIÓN ton 31.50 342.02 10,773.63 31.50 10,773.63 - 31.50 10,773.63 - -
GEOMEMBRANA HPDE e=1.5 mm
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
03.05.04 SUMINISTRO DE CEMENTO TIPO I ton 27.00 679.83 18,355.41 27.00 18,355.41 - 27.00 18,355.41 - - 03.05.05 SUMINISTRO DE BENTONITA ton 0.60 1,475.47 885.28 0.60 885.28 - 0.60 885.28 - - 03.05.06 SUMINISTRO DE ADITIVO PLASTIFICANTE ton 0.14 5,810.02 813.40 0.14 813.40 - 0.14 813.40 - - 04 DESCARGA DE FONDO 871,828.72 - 0.00 0.00 0.00 871,828.72
04.01 CABEZAL DE ENTRADA 49,275.83 - 0.00 0.00 0.00 49,275.83
04.01.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 39.00 221.45 8,636.55 - - - - - 39.00 8,636.55 04.01.02 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 51.00 394.95 20,142.45 - - - - - 51.00 20,142.45 04.01.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 170.00 40.22 6,837.40 - - - - - 170.00 6,837.40 04.01.04 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 3,055.80 4.47 13,659.43 - - - - - 3,055.80 13,659.43 04.02 TOMA DE TUBERÍA - ESTRUCTURA DE INGRESO 407,218.03 - 0.00 0.00 0.00 407,218.03
04.02.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 24.00 221.45 5,314.80 - - - - - 24.00 5,314.80 04.02.02 CONCRETO F´C=175 KG/CM2 (Dcant.=20.0 km) m3 74.40 368.71 27,432.02 - - - - - 74.40 27,432.02 04.02.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 322.00 40.22 12,950.84 - - - - - 322.00 12,950.84 04.02.04 CAMA DE APOYO PARA TUBERIAS m3 92.30 74.82 6,905.89 - - - - - 92.30 6,905.89 04.02.05 TUBERIA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) m 156.00 1,002.08 156,324.48 - - - - - 156.00 156,324.48 04.02.06 CODO PARA GRP DE 135° D=700 MM. (INC. SUMINISTRO Y COLOCACION) und 1.00 640.00 640.00 - - - - - 1.00 640.00 04.02.07 YEE PARA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) und 1.00 650.00 650.00 - - - - - 1.00 650.00 04.02.08 VALVULA DE 700 MM. (INC. SUMINISTRO Y COLOCACION) und 2.00 98,500.00 197,000.00 - - - - - 2.00 197,000.00 04.03 ALERONES EN PRESA 68,057.44 - 0.00 0.00 0.00 68,057.44
04.03.01 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 158.40 394.95 62,560.08 - - - - - 158.40 62,560.08 04.03.02 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 74.50 40.22 2,996.39 - - - - - 74.50 2,996.39 04.03.03 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 559.50 4.47 2,500.97 - - - - - 559.50 2,500.97 04.04 CASETA DE VÁLVULAS -ENTREGA A LA QUEBRADA 235,528.93 - 0.00 0.00 0.00 235,528.93
04.04.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 3.40 23.24 79.02 - - - - - 3.40 79.02 04.04.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 3.40 6.50 22.10 - - - - - 3.40 22.10 04.04.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 51.10 25.65 1,310.72 - - - - - 51.10 1,310.72 04.04.04 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 34.70 394.95 13,704.77 - - - - - 34.70 13,704.77 04.04.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 4.20 221.45 930.09 - - - - - 4.20 930.09 04.04.06 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 174.80 40.22 7,030.46 - - - - - 174.80 7,030.46 04.04.07 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 3,429.30 4.47 15,328.97 - - - - - 3,429.30 15,328.97 04.04.08 VÁLVULA MARIPOSA DE F°F° DE 24 " und 1.00 62,762.80 62,762.80 - - - - - 1.00 62,762.80 04.04.09 VÁLVULA CUCHILLA DE 24" und 1.00 70,800.00 70,800.00 - - - - - 1.00 70,800.00 04.04.10 MANÓMETRO DE CONTROL DE 2" und 2.00 580.00 1,160.00 - - - - - 2.00 1,160.00 04.04.11 BRIDA DRESSER PARA UNIÓN DE VÁLVULAS und 4.00 15,600.00 62,400.00 - - - - - 4.00 62,400.00 04.05 CÁMARA ROMPEPRESIÓN 111,748.49 - 0.00 0.00 0.00 111,748.49
04.05.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 16.90 23.24 392.76 - - - - - 16.90 392.76 04.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 16.90 6.50 109.85 - - - - - 16.90 109.85 04.05.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 5.90 25.65 151.34 - - - - - 5.90 151.34 04.05.04 CONCRETO CICLÓPEO 1:10 + 30% PG m3 13.50 221.45 2,989.58 - - - - - 13.50 2,989.58 04.05.05 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 2.00 293.10 586.20 - - - - - 2.00 586.20 04.05.06 CONCRETO F´C=280 KG/CM2 (Dcant.=20.0 km) m3 81.50 470.15 38,317.23 - - - - - 81.50 38,317.23 04.05.07 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 220.30 40.22 8,860.47 - - - - - 220.30 8,860.47 04.05.08 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 13,025.40 4.47 58,223.54 - - - - - 13,025.40 58,223.54 04.05.09 TAPA JUNTA WS 4" m 36.00 58.82 2,117.52 - - - - - 36.00 2,117.52 05 ALIVIADERO DE DEMASIAS - RAPIDA 1,300,945.85 - 373,176.29 67,993.40 441,169.69 859,775.86
05.01 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 1,077.60 13.16 14,181.22 1,077.60 14,181.22 - 1,077.60 14,181.22 - - 05.02 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 4,310.30 23.24 100,171.37 4,310.30 100,171.37 - 4,310.30 100,171.37 - - 05.03 PERFILADO DE TALUDES m3 3,146.10 1.00 3,146.10 2,202.70 2,202.70 943.40 943.40 3,146.10 3,146.10 - - 05.04 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 8,534.00 6.50 55,471.00 8,534.00 55,471.00 - 8,534.00 55,471.00 - - 05.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 179.10 221.45 39,661.70 - - - - - 179.10 39,661.70 05.06 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 287.10 293.10 84,149.01 - - - - - 287.10 84,149.01 05.07 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 1,175.40 394.95 464,619.18 - - - - - 1,175.40 464,618.88 05.08 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 2,867.70 40.22 115,338.89 - - - - - 2,867.70 115,338.89 05.09 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 87,054.00 4.47 389,131.38 45,000.00 201,150.00 15,000.00 67,050.00 60,000.00 268,200.00 27,054.00 120,931.38 05.10 TAPA JUNTA WS 4" m 355.00 58.82 20,881.10 - - - - - 355.00 20,881.10 05.11 JUNTA ELASTOMÉRICA m 310.00 45.79 14,194.90 - - - - - 310.00 14,194.90 06 PLAN DE MANEJO AMBIENTAL 70,765.84 - 50,394.86 5,682.50 56,077.36 0.00
06.01 PROGRAMA DE MEDIDAS PREVENTIVAS CORRECTIVAS Y/O MITIGACIÓN 30,000.00 - 23,630.00 1,995.00 25,625.00 - - 06.01.01 ESPECIALISTA AMBIENTAL (RESIDENTE) mes 8.00 3,500.00 28,000.00 6.18 21,630.00 0.57 1,995.00 6.75 23,625.00 1.25 4,375.00 06.01.02 SEÑALES INFORMATIVAS Y PREVENTIVAS und 4.00 500.00 2,000.00 4.00 2,000.00 - 4.00 2,000.00 - - 06.02 PROGRAMA DE MANEJO DE RESIDUOS 12,176.00 - 10,556.36 0.00 10,556.36 - - 06.02.01 BAÑOS QUIMICOS und 2.00 800.00 1,600.00 1.00 800.00 - 1.00 800.00 1.00 800.00
06.02.02 ACOPIO Y RESIDUOS SOLIDOS mes 8.00 1,322.00 10,576.00 7.38 9,756.36 - 7.38 9,756.36 0.62 819.64 06.03 PROGRAMA DE MONITOREO AMBIENTAL 4,800.00 - 3,996.00 0.00 3,996.00 - - 06.03.01 MONITOREO DE LA CALIDAD DEL AGUA und 4.00 1,200.00 4,800.00 3.33 3,996.00 - 3.33 3,996.00 0.67 804.00 06.04 PROGRAMA DE CAPACITACIÓN Y EDUCACIÓN AMBIENTAL 5,500.00 - 4,000.00 1,500.00 5,500.00 - - 06.04.01 CAPACITACIÓN EN MEDIO AMBIENTE AL PERSONAL DE OBRA und 2.00 2,000.00 4,000.00 2.00 4,000.00 - 2.00 4,000.00 - - 06.04.02 CAPACITACIÓN Y CONCIENTIZACIÓN DE LA POBLACIÓN SOBRE RIESGOS Y EMERGund 1.00 1,500.00 1,500.00 - - 1.00 1,500.00 1.00 1,500.00 - - 06.05 PROGRAMA DE CONTINGENCIA 6,500.00 - 6,262.50 237.50 6,500.00 - - 06.05.01 EQUIPO DE PRIMEROS AUXILIOS und 1.00 2,500.00 2,500.00 1.00 2,500.00 - 1.00 2,500.00 - - 06.05.02 EQUIPO CONTRA INCENDIOS und 1.00 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 - - 06.05.03 EQUIPOS DE RADIO COMUNICACIONES mes 8.00 250.00 2,000.00 7.05 1,762.50 0.95 237.50 8.00 2,000.00 - - 06.06 PROGRAMA DE RELACIONES COMUNITARIAS 3,900.00 - 1,950.00 1,950.00 3,900.00 - - 06.06.01 EDUCACIÓN AMBIENTAL A LA POBLACIÓN EN GENERAL glb 1.00 3,500.00 3,500.00 0.50 1,750.00 0.50 1,750.00 1.00 3,500.00 - - 06.06.02 AFICHES INFORMATIVOS glb 1.00 400.00 400.00 0.50 200.00 0.50 200.00 1.00 400.00 - - 06.07 PROGRAMA DE CIERRE O ABANDONO DE OBRA 7,889.84 - 0.00 0.00 0.00 - - 06.07.01 REHABILITACIÓN DE ÁREAS ha 0.50 7,563.36 3,781.68 - - - - - 0.50 3,781.68 06.07.02 RESTAURACIÓN DE ÁREAS ( REVEGETACIÓN) ha 1.00 4,108.16 4,108.16 - - - - - 1.00 4,108.16
-
COSTO DIRECTO S/. 6,244,507.20 2,138,284.54 173,629.05 2,311,913.58 3,917,904.83
GASTOS GENERALES 10.501% S/. 655,728.47 224,538.78 18,232.59 242,771.37 411,414.65
UTILIDAD 6.00% S/. 374,670.43 128,297.07 10,417.74 138,714.81 235,074.29
SUBTOTAL S/. 7,274,906.10 2,491,120.40 202,279.38 2,693,399.76 4,564,393.77
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000 1.00000
SUBTOTAL ( c/ Factor de Relación ) S/. 7,274,906.10 2,491,120.40 202,279.38 2,693,399.76 4,564,393.77
Porcentaje de avance 100.00% 34.24% 2.78% 37.02% 62.74%
OBRA : INSTALACION DE LA REPRESA SUYARIDA EN EL DISTRITO DE SANTIAGO DE CHUCO, PROVINCIA DE SANTIAGO DE CHUCO- LA LIBERTADPROPIETARIO : MINISTERIO DE AGRICULTURA - PROGRAMA SUBSECTORIAL DE IRRIGACIONES (PSI)UBICACIÓN : REGION LA LIBERTAD - PROVINCIA SANTIAGO DE CHUCO- DISTRITO SANTIAGO DE CHUCOCONTRATISTA : CONSORCIO COGAFE CAJAMARCASUPERVISOR : ING. LUIS RIVAS MECHATOMONTO CONTRATADO : S/. 8'584,389.20
VALORIZACION DE OBRA Nº 09 – NOVIEMBRE DEL 201401 de Noviembre al 30 de Noviembre del 2014
Item DescripciónPRESUPUESTO OFERTADOPRESENTE VALORIZACION ACUMULADO MES ACTUAL SALDO POR VALORIZAR
Und. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/.01 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 23,171.87 257,267.11 85,018.72
01.01 CARTEL DE OBRA 4.80X3.60 M. (GIGANTOGRAFÍA) und - 3.00 5,240.34 - - 01.02 MOVILIZACIÓN Y DESMOVILIZACIÓN (D=210.0 Km) glb - 0.50 22,864.72 0.50 22,864.72 01.03 CASETA DE GUARDIANÍA, OFICINA Y ALMACÉN m2 - 120.00 26,400.00 - - 01.04 REPLANTEO, CONTROL TOPOGRÁFICO Y MONUMENTACIÓN mes 1.00 15,745.92 6.62 104,237.99 1.38 21,729.37 01.05 CONSTRUCCIÓN DE CAMINOS DE ACCESO km - 2.90 39,732.81 2.10 28,772.04 01.06 MANTENIMIENTO DE CAMINOS DE ACCESO KM-MES 2.53 7,425.95 20.03 58,791.25 3.97 11,652.59 02 CONSTRUCCION DE CAMPAMENTO PERMANENTE 2,146.35 32,834.85 2,220.15
02.01 CONSTRUCCION DE CAMPAMENTO PERMANENTE m2 3.49 2,146.35 53.39 32,834.85 3.61 2,220.15 03 CONSTRUCCIÓN DE LA PRESA 105,338.15 1,424,611.43 2,199,014.52
03.01 ATAGUÍA 0.00 35,425.80 0.00
03.01.01 DESBROCE Y LIMPIEZA ha - 0.50 1,535.03 - - 03.01.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 - 483.40 1,846.59 - - 03.01.03 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 - 1,441.50 15,842.09 - - 03.01.04 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k - 1,441.50 11,013.06 - - 03.01.05 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k - 1,441.50 2,046.93 - - 03.01.06 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 - 483.40 3,142.10 - - 03.02 CIMENTACIÓN DE PRESA 0.00 604,488.34 64,994.99
03.02.01 DESBROCE Y LIMPIEZA ha - 1.60 4,912.10 0.20 614.01 03.02.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 - 3,060.65 11,691.68 200.65 766.48 03.02.03 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 - 8,543.84 112,436.93 503.26 6,622.90 03.02.04 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 - 13,172.30 306,124.25 2,040.70 47,425.87 03.02.05 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 - 26,049.75 169,323.38 1,471.65 9,565.73 03.03 CONFORMACIÓN DE TERRAPLÉN 105,338.15 607,649.27 2,094,551.29
03.03.01 RELLENO CON MATERIAL GRAVO-ARCILLOSO m3 7,485.30 74,778.15 15,985.30 159,693.15 112,951.80 1,128,388.48 03.03.02 RELLENO CON FILTRO DE ARENA m3 - - - 3,629.40 66,744.67 03.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 - - - 2,353.10 19,718.98 03.03.04 RELLENO CON GRAVA GRUESA PARA PROTECCIÓN m3 - - - 5,167.60 183,966.56 03.03.05 ENROCADO DE PROTECCIÓN Dmax.=0.50 M. m3 - - - 6,985.20 239,452.66 03.03.06 RELLENO COMPACTADO CON MATERIAL DE AFIRMADO m3 - - - 112.50 2,475.00 03.03.07 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 4,000.00 30,560.00 58,633.00 447,956.12 7,706.50 58,877.66 03.03.08 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k - - - 112.50 159.75 03.03.09 TRANSPORTE DE ROCA 120 M < D < 1.0 KM. m3k - - - 6,076.40 50,069.54
03.03.10 m2 - - - 9,023.00 120,005.90
03.03.11 m2 - - - 9,068.10 63,658.06
03.03.12 GEOCOMPUESTO DE DRENAJE ENKANDRAIN TYPE B10/1-2S m2 - - - 6,449.10 161,034.03 03.04 SISTEMA DE DRENAJE 0.00 0.00 39,468.24
03.04.01 RELLENO COMPACTADO CON FILTRO DE GRAVA m3 - - - 175.90 4,780.96 03.04.02 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k - - - 175.90 1,343.88 03.04.03 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k - - - 1,758.80 2,497.50 03.04.04 TUBERIA PVC D=200 mm. (INC. SUMINISTRO Y COLOCACION) m - - - 195.00 14,196.00 03.04.05 TUBERIA PVC PERFORADA D=200 mm. (INC. SUMINISTRO Y COLOCACION) m - - - 185.00 15,281.00
03.04.06 m2 - - - 195.00 1,368.90
03.05 PANTALLA IMPERMEABLE 0.00 177,048.02 0.00
03.05.01 PERFORACIONES DIAMANTINA NQ O NX S/RECUPERACIÓN DE TESTIGOS m - 120.00 79,552.80 - - 03.05.02 PERFORACIONES PARA INYECCIÓNES Y DRENES D=2" m - 225.00 66,667.50 - - 03.05.03 INYECCIONES DE CONSOLIDACIÓN E IMPERMEABILIZACIÓN ton - 31.50 10,773.63 - -
GEOMEMBRANA HPDE e=1.5 mm
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
03.05.04 SUMINISTRO DE CEMENTO TIPO I ton - 27.00 18,355.41 - - 03.05.05 SUMINISTRO DE BENTONITA ton - 0.60 885.28 - - 03.05.06 SUMINISTRO DE ADITIVO PLASTIFICANTE ton - 0.14 813.40 - - 04 DESCARGA DE FONDO 0.00 0.00 871,828.72
04.01 CABEZAL DE ENTRADA 0.00 0.00 49,275.83
04.01.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 - - - 39.00 8,636.55 04.01.02 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 - - - 51.00 20,142.45 04.01.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 170.00 6,837.40 04.01.04 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg - - - 3,055.80 13,659.43 04.02 TOMA DE TUBERÍA - ESTRUCTURA DE INGRESO 0.00 0.00 407,218.03
04.02.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 - - - 24.00 5,314.80 04.02.02 CONCRETO F´C=175 KG/CM2 (Dcant.=20.0 km) m3 - - - 74.40 27,432.02 04.02.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 322.00 12,950.84 04.02.04 CAMA DE APOYO PARA TUBERIAS m3 - - - 92.30 6,905.89 04.02.05 TUBERIA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) m - - - 156.00 156,324.48 04.02.06 CODO PARA GRP DE 135° D=700 MM. (INC. SUMINISTRO Y COLOCACION) und - - - 1.00 640.00 04.02.07 YEE PARA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) und - - - 1.00 650.00 04.02.08 VALVULA DE 700 MM. (INC. SUMINISTRO Y COLOCACION) und - - - 2.00 197,000.00 04.03 ALERONES EN PRESA 0.00 0.00 68,057.44
04.03.01 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 - - - 158.40 62,560.08 04.03.02 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 74.50 2,996.39 04.03.03 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg - - - 559.50 2,500.97 04.04 CASETA DE VÁLVULAS -ENTREGA A LA QUEBRADA 0.00 0.00 235,528.93
04.04.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 - - - 3.40 79.02 04.04.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 - - - 3.40 22.10 04.04.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 - - - 51.10 1,310.72 04.04.04 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 - - - 34.70 13,704.77 04.04.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 - - - 4.20 930.09 04.04.06 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 174.80 7,030.46 04.04.07 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg - - - 3,429.30 15,328.97 04.04.08 VÁLVULA MARIPOSA DE F°F° DE 24 " und - - - 1.00 62,762.80 04.04.09 VÁLVULA CUCHILLA DE 24" und - - - 1.00 70,800.00 04.04.10 MANÓMETRO DE CONTROL DE 2" und - - - 2.00 1,160.00 04.04.11 BRIDA DRESSER PARA UNIÓN DE VÁLVULAS und - - - 4.00 62,400.00 04.05 CÁMARA ROMPEPRESIÓN 0.00 0.00 111,748.49
04.05.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 - - - 16.90 392.76 04.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 - - - 16.90 109.85 04.05.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 - - - 5.90 151.34 04.05.04 CONCRETO CICLÓPEO 1:10 + 30% PG m3 - - - 13.50 2,989.58 04.05.05 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 - - - 2.00 586.20 04.05.06 CONCRETO F´C=280 KG/CM2 (Dcant.=20.0 km) m3 - - - 81.50 38,317.23 04.05.07 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 220.30 8,860.47 04.05.08 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg - - - 13,025.40 58,223.54 04.05.09 TAPA JUNTA WS 4" m - - - 36.00 2,117.52 05 ALIVIADERO DE DEMASIAS - RAPIDA 2,423.20 373,175.79 927,375.11
05.01 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 - 1,077.60 14,181.22 - - 05.02 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 - 4,310.30 100,171.37 - - 05.03 PERFILADO DE TALUDES m3 2,202.20 2,202.20 2,202.20 2,202.20 943.90 943.90 05.04 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 34.00 221.00 8,534.00 55,471.00 - - 05.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 - - - 179.10 39,661.70 05.06 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 - - - 287.10 84,149.01 05.07 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 - - - 1,175.40 464,224.23 05.08 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 - - - 2,867.70 115,338.89 05.09 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg - 45,000.00 201,150.00 42,054.00 187,981.38 05.10 TAPA JUNTA WS 4" m - - - 355.00 20,881.10 05.11 JUNTA ELASTOMÉRICA m - - - 310.00 14,194.90 06 PLAN DE MANEJO AMBIENTAL 8,498.36 50,394.86 20,370.98
06.01 PROGRAMA DE MEDIDAS PREVENTIVAS CORRECTIVAS Y/O MITIGACIÓN 3,500.00 23,630.00 6,370.00
06.01.01 ESPECIALISTA AMBIENTAL (RESIDENTE) mes 1.00 3,500.00 6.18 21,630.00 1.82 6,370.00 06.01.02 SEÑALES INFORMATIVAS Y PREVENTIVAS und - 4.00 2,000.00 - - 06.02 PROGRAMA DE MANEJO DE RESIDUOS 502.36 10,556.36 1,619.64
06.02.01 BAÑOS QUIMICOS und - 1.00 800.00 1.00 800.00
06.02.02 ACOPIO Y RESIDUOS SOLIDOS mes 0.38 502.36 7.38 9,756.36 0.62 819.64 06.03 PROGRAMA DE MONITOREO AMBIENTAL 396.00 3,996.00 804.00
06.03.01 MONITOREO DE LA CALIDAD DEL AGUA und 0.33 396.00 3.33 3,996.00 0.67 804.00 06.04 PROGRAMA DE CAPACITACIÓN Y EDUCACIÓN AMBIENTAL 2,000.00 4,000.00 1,500.00
06.04.01 CAPACITACIÓN EN MEDIO AMBIENTE AL PERSONAL DE OBRA und 1.00 2,000.00 2.00 4,000.00 - - 06.04.02 CAPACITACIÓN Y CONCIENTIZACIÓN DE LA POBLACIÓN SOBRE RIESGOS Y EMERGund - - - 1.00 1,500.00 06.05 PROGRAMA DE CONTINGENCIA 150.00 6,262.50 237.50
06.05.01 EQUIPO DE PRIMEROS AUXILIOS und - 1.00 2,500.00 - - 06.05.02 EQUIPO CONTRA INCENDIOS und - 1.00 2,000.00 - - 06.05.03 EQUIPOS DE RADIO COMUNICACIONES mes 0.60 150.00 7.05 1,762.50 0.95 237.50 06.06 PROGRAMA DE RELACIONES COMUNITARIAS 1,950.00 1,950.00 1,950.00
06.06.01 EDUCACIÓN AMBIENTAL A LA POBLACIÓN EN GENERAL glb 0.50 1,750.00 0.50 1,750.00 0.50 1,750.00 06.06.02 AFICHES INFORMATIVOS glb 0.50 200.00 0.50 200.00 0.50 200.00 06.07 PROGRAMA DE CIERRE O ABANDONO DE OBRA 0.00 0.00 7,889.84
06.07.01 REHABILITACIÓN DE ÁREAS ha - - - 0.50 3,781.68 06.07.02 RESTAURACIÓN DE ÁREAS ( REVEGETACIÓN) ha - - - 1.00 4,108.16
COSTO DIRECTO 141,577.93 2,138,284.04 4,105,828.20
GASTOS GENERALES 10.501% 14,866.93 224,538.73 431,148.26
UTILIDAD 6.00% 8,494.68 128,297.04 246,349.69
SUBTOTAL 164,939.54 2,491,119.81 4,783,326.16
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000
SUBTOTAL ( c/ Factor de Relación ) 164,939.54 2,491,119.81 4,783,326.16
Porcentaje de avance 2.27% 34.24% 65.75%
OBRA : INSTALACION DE LA REPRESA SUYARIDA EN EL DISTRITO DE SANTIAGO DE CHUCO, PROVINCIA DE SANTIAGO DE CHUCO- LA LIBERTADPROPIETARIO : MINISTERIO DE AGRICULTURA - PROGRAMA SUBSECTORIAL DE IRRIGACIONES (PSI)UBICACIÓN : REGION LA LIBERTAD - PROVINCIA SANTIAGO DE CHUCO- DISTRITO SANTIAGO DE CHUCOCONTRATISTA : CONSORCIO COGAFE CAJAMARCASUPERVISOR : ING. LUIS RIVAS MECHATOMONTO CONTRATADO : S/. 8'584,389.20
VALORIZACION DE OBRA Nº 08 – OCTUBRE DEL 201401 de Octubre al 31 de Octubre del 2014
Item DescripciónPRESUPUESTO OFERTADO ACUMULADO MES ANTERIOR PRESENTE VALORIZACION ACUMULADO MES ACTUAL SALDO POR VALORIZAR
Und. Metrado P.U. MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/. Metrado MONTO S/.01 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 342,285.83 - 214,582.53 19,512.71 234,095.24 108,190.59
01.01 CARTEL DE OBRA 4.80X3.60 M. (GIGANTOGRAFÍA) und 3.00 1,746.78 5,240.34 3.00 5,240.34 - 3.00 5,240.34 - - 01.02 MOVILIZACIÓN Y DESMOVILIZACIÓN (D=210.0 Km) glb 1.00 45,729.44 45,729.44 0.50 22,864.72 - 0.50 22,864.72 0.50 22,864.72 01.03 CASETA DE GUARDIANÍA, OFICINA Y ALMACÉN m2 120.00 220.00 26,400.00 120.00 26,400.00 - 120.00 26,400.00 - - 01.04 REPLANTEO, CONTROL TOPOGRÁFICO Y MONUMENTACIÓN mes 8.00 15,745.92 125,967.36 4.94 77,784.84 0.68 10,707.23 5.62 88,492.07 2.38 37,475.29 01.05 CONSTRUCCIÓN DE CAMINOS DE ACCESO km 5.00 13,700.97 68,504.85 2.90 39,732.81 - 2.90 39,732.81 2.10 28,772.04 01.06 MANTENIMIENTO DE CAMINOS DE ACCESO KM-MES 24.00 2,935.16 70,443.84 14.50 42,559.82 3.00 8,805.48 17.50 51,365.30 6.50 19,078.54 02 CONSTRUCCION DE CAMPAMENTO PERMANENTE 35,055.00 - 24,538.50 6,150.00 30,688.50 4,366.50
02.01 CONSTRUCCION DE CAMPAMENTO PERMANENTE m2 57.00 615.00 35,055.00 39.90 24,538.50 10.00 6,150.00 49.90 30,688.50 7.10 4,366.50 03 CONSTRUCCIÓN DE LA PRESA 3,623,625.96 - 1,117,993.28 201,280.00 1,319,273.28 2,304,352.67
03.01 ATAGUÍA 35,425.80 - 35,425.80 0.00 35,425.80 0.00
03.01.01 DESBROCE Y LIMPIEZA ha 0.50 3,070.06 1,535.03 0.50 1,535.03 - 0.50 1,535.03 - - 03.01.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 483.40 3.82 1,846.59 483.40 1,846.59 - 483.40 1,846.59 - - 03.01.03 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 1,441.50 10.99 15,842.09 1,441.50 15,842.09 - 1,441.50 15,842.09 - - 03.01.04 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 1,441.50 7.64 11,013.06 1,441.50 11,013.06 - 1,441.50 11,013.06 - - 03.01.05 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 1,441.50 1.42 2,046.93 1,441.50 2,046.93 - 1,441.50 2,046.93 - - 03.01.06 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 483.40 6.50 3,142.10 483.40 3,142.10 - 483.40 3,142.10 - - 03.02 CIMENTACIÓN DE PRESA 669,483.34 - 604,488.34 0.00 604,488.34 64,994.99
03.02.01 DESBROCE Y LIMPIEZA ha 1.80 3,070.06 5,526.11 1.60 4,912.10 - 1.60 4,912.10 0.20 614.01 03.02.02 EXCAVACIÓN DE MATERIAL SUELTO C/EQUIPO m3 3,261.30 3.82 12,458.17 3,060.65 11,691.68 - 3,060.65 11,691.68 200.65 766.48 03.02.03 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 9,047.10 13.16 119,059.84 8,543.84 112,436.93 - 8,543.84 112,436.93 503.26 6,622.90 03.02.04 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 15,213.00 23.24 353,550.12 13,172.30 306,124.25 - 13,172.30 306,124.25 2,040.70 47,425.87 03.02.05 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 27,521.40 6.50 178,889.10 26,049.75 169,323.38 - 26,049.75 169,323.38 1,471.65 9,565.73 03.03 CONFORMACIÓN DE TERRAPLÉN 2,702,200.56 - 301,031.12 201,280.00 502,311.12 2,199,889.44
03.03.01 RELLENO CON MATERIAL GRAVO-ARCILLOSO m3 128,937.10 9.99 1,288,081.63 2,500.00 24,975.00 6,000.00 59,940.00 8,500.00 84,915.00 120,437.10 1,203,166.63 03.03.02 RELLENO CON FILTRO DE ARENA m3 3,629.40 18.39 66,744.67 - - - - - 3,629.40 66,744.67 03.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,353.10 8.38 19,718.98 - - - - - 2,353.10 19,718.98 03.03.04 RELLENO CON GRAVA GRUESA PARA PROTECCIÓN m3 5,167.60 35.60 183,966.56 - - - - - 5,167.60 183,966.56 03.03.05 ENROCADO DE PROTECCIÓN Dmax.=0.50 M. m3 6,985.20 34.28 239,452.66 - - - - - 6,985.20 239,452.66 03.03.06 RELLENO COMPACTADO CON MATERIAL DE AFIRMADO m3 112.50 22.00 2,475.00 - - - - - 112.50 2,475.00 03.03.07 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 66,339.50 7.64 506,833.78 36,133.00 276,056.12 18,500.00 141,340.00 54,633.00 417,396.12 11,706.50 89,437.66 03.03.08 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 112.50 1.42 159.75 - - - - - 112.50 159.75 03.03.09 TRANSPORTE DE ROCA 120 M < D < 1.0 KM. m3k 6,076.40 8.24 50,069.54 - - - - - 6,076.40 50,069.54
03.03.10 m2 9,023.00 13.30 120,005.90 - - - - - 9,023.00 120,005.90
03.03.11 m2 9,068.10 7.02 63,658.06 - - - - - 9,068.10 63,658.06
03.03.12 GEOCOMPUESTO DE DRENAJE ENKANDRAIN TYPE B10/1-2S m2 6,449.10 24.97 161,034.03 - - - - - 6,449.10 161,034.03 03.04 SISTEMA DE DRENAJE 39,468.24 - 0.00 0.00 0.00 39,468.24
03.04.01 RELLENO COMPACTADO CON FILTRO DE GRAVA m3 175.90 27.18 4,780.96 - - - - - 175.90 4,780.96 03.04.02 TRANSPORTE DE MATERIAL GRANULAR 120 M < D < 1.0 KM. m3k 175.90 7.64 1,343.88 - - - - - 175.90 1,343.88 03.04.03 TRANSPORTE DE MATERIAL GRANULAR D > 1.0 KM. m3k 1,758.80 1.42 2,497.50 - - - - - 1,758.80 2,497.50 03.04.04 TUBERIA PVC D=200 mm. (INC. SUMINISTRO Y COLOCACION) m 195.00 72.80 14,196.00 - - - - - 195.00 14,196.00 03.04.05 TUBERIA PVC PERFORADA D=200 mm. (INC. SUMINISTRO Y COLOCACION) m 185.00 82.60 15,281.00 - - - - - 185.00 15,281.00
03.04.06 m2 195.00 7.02 1,368.90 - - - - - 195.00 1,368.90
03.05 PANTALLA IMPERMEABLE 177,048.02 - 177,048.02 0.00 177,048.02 0.00
03.05.01 PERFORACIONES DIAMANTINA NQ O NX S/RECUPERACIÓN DE TESTIGOS m 120.00 662.94 79,552.80 120.00 79,552.80 - 120.00 79,552.80 - - 03.05.02 PERFORACIONES PARA INYECCIÓNES Y DRENES D=2" m 225.00 296.30 66,667.50 225.00 66,667.50 - 225.00 66,667.50 - - 03.05.03 INYECCIONES DE CONSOLIDACIÓN E IMPERMEABILIZACIÓN ton 31.50 342.02 10,773.63 31.50 10,773.63 - 31.50 10,773.63 - -
GEOMEMBRANA HPDE e=1.5 mm
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
GEOTEXTIL NO TEJIDO PP TIPO TDM GT 270P
03.05.04 SUMINISTRO DE CEMENTO TIPO I ton 27.00 679.83 18,355.41 27.00 18,355.41 - 27.00 18,355.41 - - 03.05.05 SUMINISTRO DE BENTONITA ton 0.60 1,475.47 885.28 0.60 885.28 - 0.60 885.28 - - 03.05.06 SUMINISTRO DE ADITIVO PLASTIFICANTE ton 0.14 5,810.02 813.40 0.14 813.40 - 0.14 813.40 - - 04 DESCARGA DE FONDO 871,828.72 - 0.00 0.00 0.00 871,828.72
04.01 CABEZAL DE ENTRADA 49,275.83 - 0.00 0.00 0.00 49,275.83
04.01.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 39.00 221.45 8,636.55 - - - - - 39.00 8,636.55 04.01.02 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 51.00 394.95 20,142.45 - - - - - 51.00 20,142.45 04.01.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 170.00 40.22 6,837.40 - - - - - 170.00 6,837.40 04.01.04 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 3,055.80 4.47 13,659.43 - - - - - 3,055.80 13,659.43 04.02 TOMA DE TUBERÍA - ESTRUCTURA DE INGRESO 407,218.03 - 0.00 0.00 0.00 407,218.03
04.02.01 CONCRETO CICLÓPEO 1:10 + 30% PG m3 24.00 221.45 5,314.80 - - - - - 24.00 5,314.80 04.02.02 CONCRETO F´C=175 KG/CM2 (Dcant.=20.0 km) m3 74.40 368.71 27,432.02 - - - - - 74.40 27,432.02 04.02.03 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 322.00 40.22 12,950.84 - - - - - 322.00 12,950.84 04.02.04 CAMA DE APOYO PARA TUBERIAS m3 92.30 74.82 6,905.89 - - - - - 92.30 6,905.89 04.02.05 TUBERIA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) m 156.00 1,002.08 156,324.48 - - - - - 156.00 156,324.48 04.02.06 CODO PARA GRP DE 135° D=700 MM. (INC. SUMINISTRO Y COLOCACION) und 1.00 640.00 640.00 - - - - - 1.00 640.00 04.02.07 YEE PARA GRP D=700 MM. (INC. SUMINISTRO Y COLOCACION) und 1.00 650.00 650.00 - - - - - 1.00 650.00 04.02.08 VALVULA DE 700 MM. (INC. SUMINISTRO Y COLOCACION) und 2.00 98,500.00 197,000.00 - - - - - 2.00 197,000.00 04.03 ALERONES EN PRESA 68,057.44 - 0.00 0.00 0.00 68,057.44
04.03.01 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 158.40 394.95 62,560.08 - - - - - 158.40 62,560.08 04.03.02 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 74.50 40.22 2,996.39 - - - - - 74.50 2,996.39 04.03.03 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 559.50 4.47 2,500.97 - - - - - 559.50 2,500.97 04.04 CASETA DE VÁLVULAS -ENTREGA A LA QUEBRADA 235,528.93 - 0.00 0.00 0.00 235,528.93
04.04.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 3.40 23.24 79.02 - - - - - 3.40 79.02 04.04.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 3.40 6.50 22.10 - - - - - 3.40 22.10 04.04.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 51.10 25.65 1,310.72 - - - - - 51.10 1,310.72 04.04.04 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 34.70 394.95 13,704.77 - - - - - 34.70 13,704.77 04.04.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 4.20 221.45 930.09 - - - - - 4.20 930.09 04.04.06 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 174.80 40.22 7,030.46 - - - - - 174.80 7,030.46 04.04.07 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 3,429.30 4.47 15,328.97 - - - - - 3,429.30 15,328.97 04.04.08 VÁLVULA MARIPOSA DE F°F° DE 24 " und 1.00 62,762.80 62,762.80 - - - - - 1.00 62,762.80 04.04.09 VÁLVULA CUCHILLA DE 24" und 1.00 70,800.00 70,800.00 - - - - - 1.00 70,800.00 04.04.10 MANÓMETRO DE CONTROL DE 2" und 2.00 580.00 1,160.00 - - - - - 2.00 1,160.00 04.04.11 BRIDA DRESSER PARA UNIÓN DE VÁLVULAS und 4.00 15,600.00 62,400.00 - - - - - 4.00 62,400.00 04.05 CÁMARA ROMPEPRESIÓN 111,748.49 - 0.00 0.00 0.00 111,748.49
04.05.01 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 16.90 23.24 392.76 - - - - - 16.90 392.76 04.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 16.90 6.50 109.85 - - - - - 16.90 109.85 04.05.03 RELLENO COMPACTADO PARA ESTRUCTURAS C/MATERIAL PROPIO m3 5.90 25.65 151.34 - - - - - 5.90 151.34 04.05.04 CONCRETO CICLÓPEO 1:10 + 30% PG m3 13.50 221.45 2,989.58 - - - - - 13.50 2,989.58 04.05.05 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 2.00 293.10 586.20 - - - - - 2.00 586.20 04.05.06 CONCRETO F´C=280 KG/CM2 (Dcant.=20.0 km) m3 81.50 470.15 38,317.23 - - - - - 81.50 38,317.23 04.05.07 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 220.30 40.22 8,860.47 - - - - - 220.30 8,860.47 04.05.08 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 13,025.40 4.47 58,223.54 - - - - - 13,025.40 58,223.54 04.05.09 TAPA JUNTA WS 4" m 36.00 58.82 2,117.52 - - - - - 36.00 2,117.52 05 ALIVIADERO DE DEMASIAS - RAPIDA 1,300,945.85 - 6,118.00 364,634.59 370,752.59 929,798.31
05.01 EXCAVACIÓN DE ROCA SUELTA C/EQUIPO m3 1,077.60 13.16 14,181.22 200.00 2,632.00 877.60 11,549.22 1,077.60 14,181.22 - - 05.02 EXCAVACIÓN DE ROCA FIJA C/EQUIPO m3 4,310.30 23.24 100,171.37 150.00 3,486.00 4,160.30 96,685.37 4,310.30 100,171.37 - - 05.03 PERFILADO DE TALUDES m3 3,146.10 1.00 3,146.10 - - - - - 3,146.10 3,146.10 05.04 ELIMINACIÓN DE MATERIAL EXCEDENTE (D=0.5 KM) m3 8,534.00 6.50 55,471.00 - - 8,500.00 55,250.00 8,500.00 55,250.00 34.00 221.00 05.05 CONCRETO CICLÓPEO 1:10 + 30% PG m3 179.10 221.45 39,661.70 - - - - - 179.10 39,661.70 05.06 CONCRETO F´C=100 KG/CM2 (Dcant.=20.0 km) m3 287.10 293.10 84,149.01 - - - - - 287.10 84,149.01 05.07 CONCRETO F´C=210 KG/CM2 (Dcant.=20.0 km) m3 1,175.40 394.95 464,619.18 - - - - - 1,175.40 464,224.23 05.08 ENCOFRADO Y DESENCOFRADO P/ESTRUCTURAS m2 2,867.70 40.22 115,338.89 - - - - - 2,867.70 115,338.89 05.09 ACERO DE REFUERZO F´C=4,200 KG/CM2 kg 87,054.00 4.47 389,131.38 - - 45,000.00 201,150.00 45,000.00 201,150.00 42,054.00 187,981.38 05.10 TAPA JUNTA WS 4" m 355.00 58.82 20,881.10 - - - - - 355.00 20,881.10 05.11 JUNTA ELASTOMÉRICA m 310.00 45.79 14,194.90 - - - - - 310.00 14,194.90 06 PLAN DE MANEJO AMBIENTAL 70,765.84 - 38,762.00 3,134.50 41,896.50 28,869.34
06.01 PROGRAMA DE MEDIDAS PREVENTIVAS CORRECTIVAS Y/O MITIGACIÓN 30,000.00 - 18,555.00 1,575.00 20,130.00 9,870.00
06.01.01 ESPECIALISTA AMBIENTAL (RESIDENTE) mes 8.00 3,500.00 28,000.00 4.73 16,555.00 0.45 1,575.00 5.18 18,130.00 2.82 9,870.00 06.01.02 SEÑALES INFORMATIVAS Y PREVENTIVAS und 4.00 500.00 2,000.00 4.00 2,000.00 - 4.00 2,000.00 - - 06.02 PROGRAMA DE MANEJO DE RESIDUOS 12,176.00 - 8,732.00 1,322.00 10,054.00 2,122.00
06.02.01 BAÑOS QUIMICOS und 2.00 800.00 1,600.00 1.00 800.00 - 1.00 800.00 1.00 800.00
06.02.02 ACOPIO Y RESIDUOS SOLIDOS mes 8.00 1,322.00 10,576.00 6.00 7,932.00 1.00 1,322.00 7.00 9,254.00 1.00 1,322.00 06.03 PROGRAMA DE MONITOREO AMBIENTAL 4,800.00 - 3,600.00 0.00 3,600.00 1,200.00
06.03.01 MONITOREO DE LA CALIDAD DEL AGUA und 4.00 1,200.00 4,800.00 3.00 3,600.00 - 3.00 3,600.00 1.00 1,200.00 06.04 PROGRAMA DE CAPACITACIÓN Y EDUCACIÓN AMBIENTAL 5,500.00 - 2,000.00 0.00 2,000.00 3,500.00
06.04.01 CAPACITACIÓN EN MEDIO AMBIENTE AL PERSONAL DE OBRA und 2.00 2,000.00 4,000.00 1.00 2,000.00 - 1.00 2,000.00 1.00 2,000.00 06.04.02 CAPACITACIÓN Y CONCIENTIZACIÓN DE LA POBLACIÓN SOBRE RIESGOS Y EMERGund 1.00 1,500.00 1,500.00 - - - - - 1.00 1,500.00 06.05 PROGRAMA DE CONTINGENCIA 6,500.00 - 5,875.00 237.50 6,112.50 387.50
06.05.01 EQUIPO DE PRIMEROS AUXILIOS und 1.00 2,500.00 2,500.00 1.00 2,500.00 - 1.00 2,500.00 - - 06.05.02 EQUIPO CONTRA INCENDIOS und 1.00 2,000.00 2,000.00 1.00 2,000.00 - 1.00 2,000.00 - - 06.05.03 EQUIPOS DE RADIO COMUNICACIONES mes 8.00 250.00 2,000.00 5.50 1,375.00 0.95 237.50 6.45 1,612.50 1.55 387.50 06.06 PROGRAMA DE RELACIONES COMUNITARIAS 3,900.00 - 0.00 0.00 0.00 3,900.00
06.06.01 EDUCACIÓN AMBIENTAL A LA POBLACIÓN EN GENERAL glb 1.00 3,500.00 3,500.00 - - - - - 1.00 3,500.00 06.06.02 AFICHES INFORMATIVOS glb 1.00 400.00 400.00 - - - - - 1.00 400.00 06.07 PROGRAMA DE CIERRE O ABANDONO DE OBRA 7,889.84 - 0.00 0.00 0.00 7,889.84
06.07.01 REHABILITACIÓN DE ÁREAS ha 0.50 7,563.36 3,781.68 - - - - - 0.50 3,781.68 06.07.02 RESTAURACIÓN DE ÁREAS ( REVEGETACIÓN) ha 1.00 4,108.16 4,108.16 - - - - - 1.00 4,108.16
-
COSTO DIRECTO S/. 6,244,507.20 1,401,994.31 594,711.80 1,996,706.11 4,247,406.13
GASTOS GENERALES 10.501% S/. 655,728.47 147,221.80 62,450.00 209,671.80 446,015.20
UTILIDAD 6.00% S/. 374,670.43 84,119.66 35,682.71 119,802.37 254,844.37
SUBTOTAL S/. 7,274,906.10 1,633,335.77 692,844.51 2,326,180.27 4,948,265.70
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000 1.00000
SUBTOTAL ( c/ Factor de Relación ) S/. 7,274,906.10 1,633,335.77 692,844.51 2,326,180.27 4,948,265.70
Porcentaje de avance 100.00% 22.45% 9.52% 31.98% 68.02%