cronograma valorizado - CASCAJAL

11
DESAGREGADO POR PARTIDAS UBICACIÓN : OLMOS - LAMBAYEQUE - LAMBAYEQUE ENTIDAD : GOBIERNO REGIONAL DE LAMBAYEQUE FEBRERO DEL 2016 CONTRATISTA: CONSORCIO CALLEJON DE CASCAJAL Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) 1 01 OBRAS PROVISIONALES 20,380.02 2 01.01 ALMACEN, OFICINAS Y CASETA DE GUARDIANIA glb 1.00 2,755.56 2,755.56 3 01.02 CARTEL DE OBRA 3.60 x 7.20 und 1.00 2,910.11 2,910.11 4 01.03 SERVICIOS HIGIENICOS PORTATILES mes 4.00 950.00 3,800.00 5 01.04 AGUA PARA LA OBRA glb 1.00 4,000.00 4,000.00 6 01.05 ENERGIA ELECTRICA PARA LA OBRA glb 1.00 480.00 480.00 7 01.06 CERCO PROVISIONAL DE OBRA m 95.00 67.73 6,434.35 8 02 TRABAJOS PRELIMINARES 1,881.00 9 02.01 LIMPIEZA DEL TERRENO MANUAL m2 570.00 3.30 1,881.00 10 03 MOVILIZACION DE EQUIPOS Y HERRAMIENTAS 5,175.00 11 03.01 TRANSPORTE DE EQUIPO Y MAQUINARIAS glb 1.00 5,175.00 5,175.00 12 04 TRAZO, NIVELES Y REPLANTEO 1,219.80 13 04.01 TRAZO Y REPLANTEO PRELIMINAR m2 570.00 2.14 1,219.80 14 05 SEGURIDAD Y SALUD 7,450.67 15 05.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 1,500.00 1,500.00 16 05.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 1,608.26 1,608.26 17 05.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,142.41 1,142.41 18 05.04 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 1,940.00 1,940.00 19 05.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO glb 1.00 1,260.00 1,260.00 20 06 MOVIMIENTO DE TIERRAS 39,907.69 21 06.01 EXCAVACION PARA CIMIENTOS, PISOS Y VEREDAS m3 202.04 28.51 5,760.16 22 06.02 CORTE DE TERRENO MANUAL HASTA 0.40 M DE PROF. m3 82.74 19.00 1,572.06 23 06.03 RELLENO COMPACTADO C/EQUIPO, MATERIAL PROPIO m3 39.01 21.25 828.96 24 06.04 RELLENO CON MATERIAL PRESTAMO (HORMIGÓN) m3 202.62 51.24 10,382.25 25 06.05 RELLENO CON MATERIAL PRESTAMO(AFIRMADO) m3 90.46 56.89 5,146.27 26 06.06 RELLENO CON MATERIAL PRESTAMO(ARENA FINA) m3 9.92 91.29 905.60 27 06.07 NIVELACION INTERIOR Y APISONADO m2 521.13 3.61 1,881.28 28 06.08 ACARREO Y ELIMIN. DE MAT. EXCEDENTE m3 294.93 16.29 4,804.41 29 06.09 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE 10M3 Y CARGADOR Dprom=10 km m3 294.93 29.25 8,626.70 30 07 OBRAS DE CONCRETO SIMPLE 19,203.02 31 07.01 SOLADO DE CONCRETO E=4'' (CONCRETO 1:10 C-H) m3 6.93 102.38 709.49 32 07.02 CIMIENTOS CORRIDOS 1:10 + 30% P.G m3 57.43 176.56 10,139.84 33 07.03 FALSO PISO MEZCLA C:H 1:8 E=10CM m2 282.41 29.58 8,353.69 34 08 OBRAS DE CONCRETO ARMADO 262,953.9894 35 08.01 ZAPATAS 27,246.07 36 08.01.01 CONCRETO EN ZAPATAS f'c=210 Kg/cm2 m3 41.53 406.13 16,866.58 37 08.01.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,121.34 3.99 4,474.15 38 08.01.03 ENCOFRADO Y DESENCOFRADO EN ZAPATAS m2 121.86 48.46 5,905.34 39 08.02 VIGAS DE CIMENTACION 36,908.67 40 08.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 Kg/cm2 m3 33.24 404.71 13,452.56 41 08.02.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 3,646.03 3.99 14,547.66 42 08.02.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION m2 203.25 43.83 8,908.45 43 08.03 SOBRECIMIENTOS ARMADOS 23,590.12 44 08.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO f'c=210 Kg/cm2 m3 21.74 406.75 8,842.75 45 08.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,200.85 3.99 4,791.39 46 08.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO REFORZADO m2 227.15 43.83 9,955.98 47 08.04 COLUMNAS 59,275.75 48 08.04.01 CONCRETO EN COLUMNAS f'c=210 Kg/cm2 m3 34.12 418.69 14,285.70 49 08.04.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 6,435.35 3.99 25,677.05 50 08.04.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 397.06 48.64 19,313.00 51 08.05 COLUMNENTAS 12,438.31 52 08.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 6.15 409.39 2,517.75 53 08.05.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 806.63 3.99 3,218.45 54 08.05.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 137.79 48.64 6,702.11 55 08.06 VIGAS 42,476.84 56 08.06.01 CONCRETO EN VIGAS f'c =210 Kg/cm2 m3 30.97 395.67 12,253.90 57 08.06.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 4,470.75 3.99 17,838.29 58 08.06.03 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 231.10 53.59 12,384.65 59 08.07 VIGUETAS 3,609.77 60 08.07.01 CONCRETO VIGUETAS f'c=175 kg/cm2 m3 2.13 385.71 821.56 61 08.07.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 258.53 3.99 1,031.53 62 08.07.03 ENCOFRADO Y DESENCOFRADO EN VIGUETAS m2 32.78 53.59 1,756.68 63 08.08 LOSAS ALIGERADAS 42,489.82 64 08.08.01 CONCRETO EN LOSAS ALIGERADAS f'c=210 Kg/cm2 m3 29.23 395.67 11,565.43 65 08.08.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,103.70 3.99 8,393.76 66 08.08.03 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 333.85 47.01 15,694.29 67 08.08.04 LADRILLO DE ARCILLA 15X30X30 cm PARA LOSA ALIGERADA und 2,779.00 2.46 6,836.34 68 08.09 LOSAS MACIZAS 1,115.13 69 08.09.01 CONCRETO EN LOSA MACIZAS f'c=210 kg/cm2 m3 1.08 362.81 391.83 70 08.09.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 100.69 3.99 401.75 71 08.09.03 ENCOFRADO Y DESENCOFRADO DE LOSAS MACIZAS m2 6.84 47.01 321.55 72 08.10 ESCALERAS 1,964.49 73 08.10.01 CONCRETO EN ESCALERAS f'c=175 kg/cm2 m3 1.47 418.62 615.37 74 08.10.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 160.06 3.99 638.64 75 08.10.03 ENCOFRADO Y DESENCOFRADO DE ESCALERA m2 16.21 43.83 710.48 76 08.11 CISTERNA 7,660.27 77 08.11.01 CISTERNA CONCRETO F'C= 175 KG/CM2 m3 3.16 418.62 1,322.84 78 08.11.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 16.21 3.99 64.68 79 08.11.03 CISTERNA ENCOFRADO Y DESENCOFRADO m2 160.06 39.19 6,272.75 80 08.12 POZO SEPTICO 2,825.52 81 08.12.01 CONCRETO EN POZO SEPTICO f'c=175 kg/cm2 m3 3.84 418.62 1,607.50 82 08.12.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 177.09 3.99 706.59 83 08.12.03 ENCOFRADO Y DESENCOFRADO EN POZO SEPTICO m2 13.05 39.19 511.43 84 08.13 FOSA DE PERCOLACION 1,103.24 85 08.13.01 CONCRETO EN FOSA DE PERCOLACIÓN f'c=175 kg/cm2 m3 1.55 418.62 648.86 86 08.13.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 91.78 3.99 366.20 87 08.13.03 ENCOFRADO Y DESENCOFRADO EN FOSA DE PERCOLACION m2 2.25 39.19 88.18 88 08.14 BANCA DE CONCRETO 250.00 89 08.14.01 BANCA DE CONCRETO TIPO 1 SEGUN DISEÑO und 1.00 250.00 250.00 PROYECTO : “MEJORAMIENTO DEL SERVICIO EDUCATIVO POR AMPLIACION DE COBERTURA EN LAS INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL, N° 365 CENTRO POBLADO DE CALLEJON DE CASCAJAL DEL DISTRITO DE OLMOS PROVINCIA DE LAMBAYEQUE, DEPARTAMENTO DE LAMBAYEQUE.” FECHA :

description

Modelo de Cronograma Valorizado

Transcript of cronograma valorizado - CASCAJAL

Page 1: cronograma valorizado - CASCAJAL

DESAGREGADO POR PARTIDAS

UBICACIÓN : OLMOS - LAMBAYEQUE - LAMBAYEQUE ENTIDAD : GOBIERNO REGIONAL DE LAMBAYEQUE

FEBRERO DEL 2016 CONTRATISTA:CONSORCIO CALLEJON DE CASCAJAL

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)

1 01 OBRAS PROVISIONALES 20,380.02

2 01.01 ALMACEN, OFICINAS Y CASETA DE GUARDIANIA glb 1.00 2,755.56 2,755.56

3 01.02 CARTEL DE OBRA 3.60 x 7.20 und 1.00 2,910.11 2,910.11

4 01.03 SERVICIOS HIGIENICOS PORTATILES mes 4.00 950.00 3,800.00

5 01.04 AGUA PARA LA OBRA glb 1.00 4,000.00 4,000.00

6 01.05 ENERGIA ELECTRICA PARA LA OBRA glb 1.00 480.00 480.00

7 01.06 CERCO PROVISIONAL DE OBRA m 95.00 67.73 6,434.35

8 02 TRABAJOS PRELIMINARES 1,881.00

9 02.01 LIMPIEZA DEL TERRENO MANUAL m2 570.00 3.30 1,881.00

10 03 MOVILIZACION DE EQUIPOS Y HERRAMIENTAS 5,175.00

11 03.01 TRANSPORTE DE EQUIPO Y MAQUINARIAS glb 1.00 5,175.00 5,175.0012 04 TRAZO, NIVELES Y REPLANTEO 1,219.80

13 04.01 TRAZO Y REPLANTEO PRELIMINAR m2 570.00 2.14 1,219.8014 05 SEGURIDAD Y SALUD 7,450.67

15 05.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 1,500.00 1,500.0016 05.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 1,608.26 1,608.2617 05.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,142.41 1,142.4118 05.04 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 1,940.00 1,940.0019 05.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO glb 1.00 1,260.00 1,260.0020 06 MOVIMIENTO DE TIERRAS 39,907.69

21 06.01 EXCAVACION PARA CIMIENTOS, PISOS Y VEREDAS m3 202.04 28.51 5,760.1622 06.02 CORTE DE TERRENO MANUAL HASTA 0.40 M DE PROF. m3 82.74 19.00 1,572.0623 06.03 RELLENO COMPACTADO C/EQUIPO, MATERIAL PROPIO m3 39.01 21.25 828.9624 06.04 RELLENO CON MATERIAL PRESTAMO (HORMIGÓN) m3 202.62 51.24 10,382.2525 06.05 RELLENO CON MATERIAL PRESTAMO(AFIRMADO) m3 90.46 56.89 5,146.2726 06.06 RELLENO CON MATERIAL PRESTAMO(ARENA FINA) m3 9.92 91.29 905.6027 06.07 NIVELACION INTERIOR Y APISONADO m2 521.13 3.61 1,881.2828 06.08 ACARREO Y ELIMIN. DE MAT. EXCEDENTE m3 294.93 16.29 4,804.4129 06.09 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE 10M3 Y CARGADOR Dprom=10 km m3 294.93 29.25 8,626.7030 07 OBRAS DE CONCRETO SIMPLE 19,203.02

31 07.01 SOLADO DE CONCRETO E=4'' (CONCRETO 1:10 C-H) m3 6.93 102.38 709.4932 07.02 CIMIENTOS CORRIDOS 1:10 + 30% P.G m3 57.43 176.56 10,139.8433 07.03 FALSO PISO MEZCLA C:H 1:8 E=10CM m2 282.41 29.58 8,353.6934 08 OBRAS DE CONCRETO ARMADO 262,953.989435 08.01 ZAPATAS 27,246.0736 08.01.01 CONCRETO EN ZAPATAS f'c=210 Kg/cm2 m3 41.53 406.13 16,866.5837 08.01.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,121.34 3.99 4,474.1538 08.01.03 ENCOFRADO Y DESENCOFRADO EN ZAPATAS m2 121.86 48.46 5,905.3439 08.02 VIGAS DE CIMENTACION 36,908.6740 08.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 Kg/cm2 m3 33.24 404.71 13,452.5641 08.02.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 3,646.03 3.99 14,547.6642 08.02.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION m2 203.25 43.83 8,908.4543 08.03 SOBRECIMIENTOS ARMADOS 23,590.1244 08.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO f'c=210 Kg/cm2 m3 21.74 406.75 8,842.7545 08.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,200.85 3.99 4,791.3946 08.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO REFORZADO m2 227.15 43.83 9,955.9847 08.04 COLUMNAS 59,275.7548 08.04.01 CONCRETO EN COLUMNAS f'c=210 Kg/cm2 m3 34.12 418.69 14,285.7049 08.04.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 6,435.35 3.99 25,677.0550 08.04.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 397.06 48.64 19,313.0051 08.05 COLUMNENTAS 12,438.3152 08.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 6.15 409.39 2,517.7553 08.05.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 806.63 3.99 3,218.4554 08.05.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 137.79 48.64 6,702.1155 08.06 VIGAS 42,476.8456 08.06.01 CONCRETO EN VIGAS f'c =210 Kg/cm2 m3 30.97 395.67 12,253.9057 08.06.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 4,470.75 3.99 17,838.2958 08.06.03 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 231.10 53.59 12,384.6559 08.07 VIGUETAS 3,609.7760 08.07.01 CONCRETO VIGUETAS f'c=175 kg/cm2 m3 2.13 385.71 821.5661 08.07.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 258.53 3.99 1,031.5362 08.07.03 ENCOFRADO Y DESENCOFRADO EN VIGUETAS m2 32.78 53.59 1,756.6863 08.08 LOSAS ALIGERADAS 42,489.8264 08.08.01 CONCRETO EN LOSAS ALIGERADAS f'c=210 Kg/cm2 m3 29.23 395.67 11,565.4365 08.08.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,103.70 3.99 8,393.7666 08.08.03 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 333.85 47.01 15,694.2967 08.08.04 LADRILLO DE ARCILLA 15X30X30 cm PARA LOSA ALIGERADA und 2,779.00 2.46 6,836.3468 08.09 LOSAS MACIZAS 1,115.1369 08.09.01 CONCRETO EN LOSA MACIZAS f'c=210 kg/cm2 m3 1.08 362.81 391.8370 08.09.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 100.69 3.99 401.7571 08.09.03 ENCOFRADO Y DESENCOFRADO DE LOSAS MACIZAS m2 6.84 47.01 321.5572 08.10 ESCALERAS 1,964.4973 08.10.01 CONCRETO EN ESCALERAS f'c=175 kg/cm2 m3 1.47 418.62 615.3774 08.10.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 160.06 3.99 638.6475 08.10.03 ENCOFRADO Y DESENCOFRADO DE ESCALERA m2 16.21 43.83 710.4876 08.11 CISTERNA 7,660.2777 08.11.01 CISTERNA CONCRETO F'C= 175 KG/CM2 m3 3.16 418.62 1,322.8478 08.11.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 16.21 3.99 64.6879 08.11.03 CISTERNA ENCOFRADO Y DESENCOFRADO m2 160.06 39.19 6,272.7580 08.12 POZO SEPTICO 2,825.5281 08.12.01 CONCRETO EN POZO SEPTICO f'c=175 kg/cm2 m3 3.84 418.62 1,607.5082 08.12.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 177.09 3.99 706.5983 08.12.03 ENCOFRADO Y DESENCOFRADO EN POZO SEPTICO m2 13.05 39.19 511.4384 08.13 FOSA DE PERCOLACION 1,103.2485 08.13.01 CONCRETO EN FOSA DE PERCOLACIÓN f'c=175 kg/cm2 m3 1.55 418.62 648.8686 08.13.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 91.78 3.99 366.2087 08.13.03 ENCOFRADO Y DESENCOFRADO EN FOSA DE PERCOLACION m2 2.25 39.19 88.1888 08.14 BANCA DE CONCRETO 250.0089 08.14.01 BANCA DE CONCRETO TIPO 1 SEGUN DISEÑO und 1.00 250.00 250.00

PROYECTO : “MEJORAMIENTO DEL SERVICIO EDUCATIVO POR AMPLIACION DE COBERTURA EN LAS INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL, N° 365 CENTRO POBLADO DE CALLEJON DE CASCAJAL DEL DISTRITO DE OLMOS PROVINCIA DE LAMBAYEQUE, DEPARTAMENTO DE LAMBAYEQUE.”

FECHA :

Page 2: cronograma valorizado - CASCAJAL

90 09 OTROS 30,263.2591 09.01 FLETE TERRESTRE (CHICLAYO - OBRA) glb 1.00 30,263.25 30,263.2592 01 MUROS Y TABIQUES DE ALBAÑILERIA 30,589.2993 01.01 MURO DE LADRILLO KK DE ARCILLA DE CABEZA C/M 1:5 X 1.5 CM m2 220.36 80.22 17,677.2894 01.02 MURO DE LADRILLO KK DE ARCILLA DE SOGA C/M 1:5 X 1.5 CM m2 202.66 58.98 11,952.8995 01.03 MURO DE LADRILLO KK DE ARCILLA DE CANTOC/M 1:5 X 1.5 CM m2 14.38 53.77 773.2196 01.04 ALAMBRE #8 REFUERZO HORIZONTAL kg 50.52 3.68 185.9197 02 MUROS ESPECIALES 262.0598 02.01 MURO DE PIEDRA D=6" m2 7.50 34.94 262.0599 03 REVOQUES, ENLUCIDOS Y MOLDURAS 55,229.18

100 03.01 TARRAJEO MUROS PRIMARIO m2 136.53 20.18 2,755.18101 03.02 TARRAJEO FROTACHADO DE MUROS INTERIORES 1:4 , E= 1,5 CM m2 421.47 30.23 12,741.04102 03.03 TARRAJEO FROTACHADO DE MUROS EXTERIORES 1:4 , e = 1.5 cm m2 383.42 33.71 12,925.09103 03.04 TARRAJEO FROTACHADO DE COLUMNAS 1:4 E= 1.5CM m2 249.22 38.15 9,507.74104 03.05 TARRAJEO FROTACHADO DE VIGAS 1:4 , e = 1.5 cm m2 194.85 39.88 7,770.62105 03.06 TARRAJEO FONDO DE ESCALERAS m2 4.78 33.05 157.98106 03.07 TARRAJEO IMPERMEABILIZADO m2 11.05 39.30 434.27107 03.08 VESTIDURA DE DERRAMES m 291.61 13.74 4,006.72108 03.09 JUNTA DE DILATACIÓN CON MATERIAL MICROPOROSO m 64.50 8.82 568.89109 03.10 BRUÑAS DE 1 cm x 1 cm m 461.55 9.45 4,361.65110 04 CIELO RRASOS 11,538.18111 04.01 TARRAJEO FROTACHADO DE CIELO RASO 1:4 , e = 1.5 cm m2 362.38 31.84 11,538.18112 05 PISOS Y CONTRAPISOS 40,738.98113 05.01 CONTRAPISO 7,822.43114 05.01.01 CONTRAPISO DE 40mm, MEZCLA 1:5, ACABADO 1:2 m2 362.99 21.55 7,822.43115 05.02 PISOS Y PAVIMENTOS 32,916.55116 05.02.01 PISO DE PORCELANATO DE 60 X 60 CM m2 96.13 74.95 7,204.94117 05.02.02 PISO DE LOSETA VENECIANA DE 30 X 30 CM m2 131.42 63.54 8,350.43118 05.02.03 PISO CERÁMICO DE 30x30cm m2 78.36 59.74 4,681.23119 05.02.04 PISO CERAMICO 40 X 40 m2 59.90 63.52 3,804.85120 05.02.05 PISO DE CEMENTO PULIDO Y BRUÑADO m2 5.27 29.53 155.62121 05.02.06 VEREDA DE CONCRETO F'C= 140KG/CM2 , E=4" ACABADO PULIDO Y BRUÑADO m2 66.91 52.54 3,515.45122 05.02.07 RAMPA DE CONCRETO F'C= 140KG/CM2 , E=4" ACABADO PULIDO Y BRUÑADO m2 18.80 52.54 987.75123 05.02.08 LOSA DE CONCRETO F'C= 140 KG/CM2, E=5" ACABADO BRUÑADO Y FROTACHADO m2 72.90 54.71 3,988.36124 05.02.09 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO e=1" y TECKNOPORT m 48.70 4.68 227.92125 06 ZOCALOS 7,331.66126 06.01 ZÓCALO DE CERÁMICO 30X30 cm m2 136.53 53.70 7,331.66127 07 CONTRAZOCALOS 6,114.13128 07.01 CONTRAZOCALO DE CEMENTO PULIDO m2 67.44 31.17 2,102.10129 07.02 CONTRAZOCALO DE LOSETA H=0.10 m 76.85 22.64 1,739.88130 07.03 CONTRAZOCALO DE PORCELANATO H=0.10 m 35.55 23.37 830.80131 07.04 CONTRAZ0CALO DE CERAMICO H=10 cm m 66.76 21.59 1,441.35132 08 COBERTURA 23,651.36133 08.01 CORREAS DE MADERA 2"X2" m 429.20 15.23 6,536.72134 08.02 COBERTURA CON TEJA ANDINA m2 361.10 46.54 16,805.59135 08.03 COBERTURA CON TEJA PLANA m2 5.70 54.22 309.05136 09 CARPINTERIA DE MADERA 30,364.94137 09.01 PUERTA DE MADERA CEDRO, MACHIEMBRADA EXTERIOR, CONTRAPLACAD INTERIOR (SEGUN DISEÑO) m2 18.96 423.73 8,033.92138 09.02 PUERTA DE MADERA CEDRO CONTRAPLACADA (SEGUN DISEÑO) m2 18.96 296.61 5,623.73139 09.03 PUERTA DE MADERA CEDRO TIPO TABLERO (SEGUN DISEÑO) m2 4.99 254.24 1,268.66140 09.04 PUERTA DE MADERA APANELADA m2 1.89 258.90 489.32141 09.05 VENTANA DE MADERA CEDRO (SEGUN DISEÑO) m2 58.80 254.24 14,949.31142 10 CARPINTERIA METALICA Y HERRERIA 14,255.75143 10.01 PORTON METÁLICO SEGÚN DISEÑO m2 7.95 423.73 3,368.65144 10.02 PUERTA METÁLICA DE 1.00 X 2.50 M und 2.50 423.73 1,059.33145 10.03 BARANDAS METALICAS DE D= 2" m 3.82 134.97 515.59146 10.04 BARANDAS METALICAS DE D= 1 1/2" m 16.62 121.32 2,016.34147 10.05 BARANDAS METALICAS DE D= 1" m 36.08 111.87 4,036.27148 10.06 PARANTE METALICO DE D= 1 1/2" m 12.85 121.32 1,558.96149 10.07 CANTONERA DE ALUMINIO EN PASOS DE ESCALERA m 21.12 18.42 389.03150 10.08 PUERTA METALICA DE 0.70x 0.65 m PARA CASETA DE ELECTROBOMBA m2 0.46 423.73 194.92151 10.09 TAPA DE FIERRO DE 60 x 60 CON PLANCHA DE 1 /16" EN CISTERNA und 1.00 266.62 266.62152 10.10 TAPA DE FIERRO DE 60 X 60 CON PLANCHA DE 1/16" EN POZO SÉPTICO und 1.00 266.62 266.62153 10.11 TAPA DE FIERRO DE 60 X 60 CON PLANCHA DE 1/16" EN FOSA DE PERCOLACIÓN und 1.00 266.62 266.62154 10.12 TAPA DE METALICA PARA TECHO DE 1.00 X 0.60 M und 1.00 316.80 316.80155 11 CERRAJERIA 1,815.89156 11.01 CERRADURAS TIPO PARCHE DE 2 GOLPES CON MANIJAS und 15.00 80.19 1,202.85157 11.02 JALADOR Y PICAPORTE DE BRONCE und 5.00 16.88 84.40158 11.03 SISTEMA PARA PUERTA TIPO VAIVEN und 1.00 264.32 264.32159 11.04 SISTEMA PARA PUERTA CON CORREDERA und 1.00 264.32 264.32160 12 VIDRIOS, CRISTALES Y SIMILARES 8,449.48161 12.01 VIDRIO TEMPLADO DE 4MM p2 632.92 13.35 8,449.48162 13 PINTURA 17,479.43163 13.01 PINTURA LATEX 2 MANOS EN MUROS INTERIORES m2 447.30 10.23 4,575.88164 13.02 PINTURA LATEX 2 MANOS EN MUROS EXTERIORES m2 315.98 10.89 3,441.02165 13.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 194.85 12.12 2,361.58166 13.04 PINTURA LATEX 2 MANOS EN VIGAS m2 249.22 12.12 3,020.55167 13.05 PINTURA LATEX 2 MANOS EN CIELO RASO m2 362.38 11.26 4,080.40168 14 VARIOS LIMPIEZA Y JARDINERIA 35,928.80169 14.01 LIMPIEZA GENERAL DE OBRA m2 552.90 1.07 591.60170 14.02 PIZARRA ACRÍLICA und 2.00 702.08 1,404.16171 14.03 LETRAS METÁLICAS PARA PORTADA DE INGRESO glb 1.00 2,550.00 2,550.00172 14.04 SEMBRADO DE GRASS m2 6.16 25.93 159.73173 14.05 ASTA DE BANDERA H=8.50 m SEGÚN DISEÑO und 1.00 1,162.16 1,162.16174 14.06 JUEGOS INFANTILES PREFABRICADOS und 1.00 19,525.42 19,525.42175 14.07 ESTRUCTURAS METÁLICAS Y COBERTURA PARA AREA DE JUEGOS und 1.00 10,535.73 10,535.73176 01 SISTEMA DE DESAGUE 12,022.18177 01.01 SALIDA DE DESAGUE Y VENTILACION 2,410.16178 01.01.01 SALIDA DE DESAGUE EN PVC 2" pto 12.00 60.70 728.40179 01.01.02 SALIDA DE DESAGUE EN PVC 4" pto 10.00 78.71 787.10180 01.01.03 SALIDA DE VENTILACION DE 2" pto 11.00 59.26 651.86181 01.01.04 SALIDA DE DRENAJE PLUVIAL DE 2" pto 4.00 60.70 242.80182 01.02 RED DE DERIVACION, RAMALES Y MONTANTES 3,676.04183 01.02.01 TUBERIA PVC SAL DIAM=2'' m 98.71 17.20 1,697.81184 01.02.02 TUBERIA PVC SAL DIAM=3'' m 3.72 17.70 65.84185 01.02.03 TUBERIA PVC SAL DIAM=4'' m 81.24 23.54 1,912.39186 01.03 EXCAVACIONES Y RELLENOS PARA REDES EXTERIORES DE DESAGUE 2,789.80187 01.03.01 EXCAVACION DE ZANJAS m3 16.51 38.02 627.71188 01.03.02 RELLENO CON MATERIAL PROPIO m3 16.51 32.58 537.90189 01.03.03 CAMA DE APOYO 55.02 29.52 1,624.19190 01.04 ADITAMIENTOS VARIOS 1,469.30

Page 3: cronograma valorizado - CASCAJAL

191 01.04.01 CODO DE 4" X 90° und 2.00 21.06 42.12192 01.04.02 CODO DE 2" X 90° und 11.00 18.66 205.26193 01.04.03 CODO DE 2" X 45° und 1.00 18.66 18.66194 01.04.04 "Y" DE 2" und 8.00 20.56 164.48195 01.04.05 "Y" DE 4" und 1.00 24.48 24.48196 01.04.06 "Y" DE 2" X 3" und 2.00 21.06 42.12197 01.04.07 "Y" DE 2" X 4" und 8.00 21.96 175.68198 01.04.08 "T" SANITARIA DE 2" und 1.00 18.86 18.86199 01.04.09 SOMBRERO DE VENTILACION 2" und 11.00 10.94 120.34200 01.04.10 SUMIDERO DE BRONCE ROSCADO 2" und 6.00 39.54 237.24201 01.04.11 SUMIDERO DE BRONCE ROSCADO 3" und 1.00 53.61 53.61202 01.04.12 REGISTRO DE BRONCE 2" und 2.00 35.40 70.80203 01.04.13 REGISTRO DE BRONCE 4" und 5.00 59.13 295.65204 01.05 CÁMARAS DE INSPECCION 1,019.41205 01.05.01 CAJA DE REGISTRO DE CONCRETO 30X60 M (12"X24")C/TAPA CONCRETO und 7.00 145.63 1,019.41206 01.06 VARIOS 657.47207 01.06.01 PRUEBA HIDRAULICA DE DESAGUE glb 1.00 657.47 657.47208 02 SISTEMA DE AGUA FRIA 26,127.86209 02.01 SALIDAS DE AGUA FRIA 1,914.88210 02.01.01 SALIDA DE AGUA FRIA TUBERIA PVC P DE 1/2" pto 8.00 76.26 610.08211 02.01.02 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 3/4" pto 16.00 81.55 1,304.80212 02.02 TUBERIAS DE PVC-P 2,563.47213 02.02.01 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1/2" m 13.11 21.58 282.91214 02.02.02 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=3/4" m 69.13 22.19 1,533.99215 02.02.03 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1 1/2" m 15.26 25.74 392.79216 02.02.04 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1 1/4" m 14.30 24.74 353.78217 02.03 EXCAVACIONES Y RELLENOS PARA REDES EXTERIORES DE AGUA 2,283.21218 02.03.01 EXCAVACION DE ZANJAS m3 13.96 32.58 454.82219 02.03.02 RELLENO CON MATERIAL PROPIO m3 13.96 32.58 454.82220 02.03.03 CAMA DE APOYO m 46.53 29.52 1,373.57221 02.04 ADITAMIENTOS VARIOS 174.27222 02.04.01 CODO DE 1/2" X 90° und 6.00 2.65 15.90223 02.04.02 CODO DE 3/4" X 90° und 10.00 3.16 31.60224 02.04.03 CODO DE 3/4" X 45° und 1.00 3.16 3.16225 02.04.04 CODO DE 1 1/4" X 90° und 2.00 9.18 18.36226 02.04.05 CODO DE 1 1/2" X 90° und 2.00 10.18 20.36227 02.04.06 CODO DE 2" X 90° und 2.00 11.18 22.36228 02.04.07 TEE PVC 3/4" und 4.00 3.59 14.36229 02.04.08 TEE PVC 1 1/4" und 1.00 8.59 8.59230 02.04.09 TEE PVC 1 1/2" und 1.00 8.59 8.59231 02.04.10 REDUCCION DE 3/4" A 1/2" und 1.00 3.25 3.25232 02.04.11 REDUCCION DE 1 1/2" A 1 1/4" und 1.00 6.26 6.26233 02.04.12 REDUCCION DE 1 1/4" A 3/4" und 1.00 5.86 5.86234 02.04.13 REDUCCION DE 2" A 3/4" und 1.00 7.36 7.36235 02.04.14 REDUCCION DE 2" A 1 1/2" und 1.00 8.26 8.26236 02.05 VALVULAS Y ACCESORIOS 5,676.77237 02.05.01 VALVULA ESFERICA DE BRONCE Ø=1/2" und 5.00 41.61 208.05238 02.05.02 VALVULA ESFERICA DE BRONCE Ø=3/4" und 4 72.87 291.48239 02.05.03 VALVULA ESFERICA DE 1¼" und 2.00 147.87 295.74240 02.05.04 VALVULA ESFERICA DE 1½" und 1.00 203.07 203.07241 02.05.05 VALVULA ESFERICA DE 2" und 1.00 275.39 275.39242 02.05.06 VALVULA CHECK DE BRONCE DE 1/2" und 1.00 108.63 108.63243 02.05.07 VALVULA CHECK DE BRONCE DE 3/4" und 5.00 112.03 560.15244 02.05.08 VALVULA CHECK DE BRONCE DE 1 1/4" und 2.00 152.25 304.50245 02.05.09 VALVULA CHECK DE BRONCE DE 1 1/2" und 1.00 168.70 168.70246 02.05.10 CAJA PARA ALOJAMIENTO DE VALVULAS EN MURO C/TAPA S/DETALLE und 22.00 148.23 3,261.06247 02.06 APARATOS SANITARIOS Y ACCESORIOS 8,301.11248 02.06.01 INODORO BABY COLOR BLANCO (INCLUY. ACCESORIOS) und 7.00 282.33 1,976.31249 02.06.02 INODORO SIFON JET COLOR BLANCO (INCLUY. ACCESORIOS) und 2.00 232.16 464.32250 02.06.03 OVALIN SONNET COLOR BLANCO (INCLUY. ACCESORIOS) und 4.00 297.32 1,189.28251 02.06.04 LAVATORIO FONTANA COLOR BLANCO, INC. ACCESORIOS und 3 237.08 711.24252 02.06.05 LAVATORIO MALIBU COLOR BLANCO, INC. ACCESORIOS und 2.00 248.08 496.16253 02.06.06 LAVADERO DE ACERO INOXIDABLE UNA POZA und 1.00 393.93 393.93254 02.06.07 LAVADERO DE ACERO INOXIDABLE UNA POZA CON ESCURRIDERO PARA COCINA und 1.00 433.93 433.93255 02.06.08 LAVADERO DE ACERO INOXIDABLE UNA POZA CON ESCURRIDERO PARA TOPICO und 1.00 433.93 433.93256 02.06.09 URINARIO BAMBI COLOR BLANCO, INC/ACCESORIO und 2.00 655.27 1,310.54257 02.06.10 PAPELERA LOSA BLANCO und 9.00 31.00 279.00258 02.06.11 JABONERA LOSA BLANCO und 8.00 22.38 179.04259 02.06.12 ESPEJO DE 2.40 X 0.60 M und 1.00 264.16 264.16260 02.06.13 ESPEJO DE 0.90 X 0.60 M und 1.00 104.16 104.16261 02.06.14 GRIFO DE RIEGO DE 1/2" und 1.00 65.11 65.11262 02.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS DE SUCCION 226.99263 02.07.01 TUBERIA PVC SAP DIAM=1'' C-10 m 1.56 17.97 28.03264 02.07.02 VALVULA DE PIE DE 1" und 1.00 38.94 38.94265 02.07.03 VALVULA COMPUERTA DE 1" und 1.00 85.98 85.98266 02.07.04 VALVULA FLOTADOR DE 1" und 1.00 74.04 74.04267 02.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS DE IMPULSION 411.92268 02.08.01 TUBERIA PVC SAP DIAM=1'' C-10 m 13.47 17.97 242.06269 02.08.02 VALVULA MARIPOSA DE 1" und 1.00 74.88 74.88270 02.08.03 VALVULA CHECK DE BRONCE DE 1" und 1.00 94.98 94.98271 02.09 EQUIPOS Y OTRAS INSTALACIONES 3,250.66272 02.09.01 TANQUE ELEVADO ROTOPLAS 1M3 und 1.00 1,125.33 1,125.33273 02.09.02 ELECTROBOMBAS INCLUYE TABLERO und 1.00 2,125.33 2,125.33274 02.10 VARIOS 1,324.58275 02.10.01 PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIAS DE AGUA Y CISTERNA glb 1.00 1,324.58 1,324.58276 01 Salida para alumbrado, tomacorrientes, fuerzas y señales debiles 7,918.90277 01.01 SALIDA CENTRO DE ALUMBRADO EMPOTRADO pto 49.00 78.42 3,842.58278 01.02 SALIDA PARA BRAQUETE (PARED) pto 4.00 78.06 312.24279 01.03 SALIDA TOMACORRIENTE MONOF. DOBLE CON LINEA A TIERRA pto 30.00 85.47 2,564.10280 01.04 SALIDA PARA INTERRUPTOR SIMPLE und 14.00 31.58 442.12281 01.05 SALIDA PARA INTERRUPTOR DOBLE und 5.00 35.82 179.10282 01.06 SALIDA PARA INTERRUPTOR TRIPLE und 1.00 39.79 39.79283 01.07 SALIDA PARA INTERRUPTOR CONMUTADOR SIMPLE und 4.00 34.12 136.48284 01.08 SALIDA PARA INTERRUPTOR CONMUTADOR DOBLE und 2.00 38.36 76.72285 01.09 SALIDA PARA INTERRUPTOR CONMUTADOR TRIPLE und 2.00 41.69 83.38286 01.10 SALIDA PARA FAROLES pto 1.00 85.26 85.26287 01.11 SALIDA PARA ELECTROBOMBA pto 1.00 157.13 157.13288 02 Salida para Comunicaciones y Señales (Voz y Data) 303.69289 02.01 SALIDA PARA TELEFONO Y/O INTERCOMUNICADORES pto 1.00 98.43 98.43290 02.02 SALIDA PARA TIMBRE TIPO GONG CON PVC pto 1.00 95.47 95.47291 02.03 SALIDA PARA TIMBRE TIPO DING DONG CON PVC pto 1.00 109.79 109.79

Page 4: cronograma valorizado - CASCAJAL

292 03 Canalización y/o Tubería 4,186.84293 03.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT-ELECT. m3 11.10 38.02 422.02294 03.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT.ELEC.SANIT). m3 7.77 32.58 253.15295 03.03 TUBERIA PVC - P 20 mm. ml 357.24 9.83 3,511.67296 04 Cajas 81.10297 04.01 CAJA DE PASE FºGº 6'' X 6'' X 3'' und 2.00 40.55 81.10298 05 Tableros y cuchillas 3,407.86299 05.01 TD-1 con Int. Aut.: 1-3x30A, 2-2x20A, 30mA, 220V, Reserva 12 POLOS und 1.00 604.90 604.90300 05.02 TD-2 con Int. Aut.: 1-3x30A, 2-2x20A, 1-3x20A, 30mA, 220V, Reserva 12 POLOS und 1.00 705.80 705.80301 05.03 TD-3 con Int. Aut.: 1-3x30A, 2-2x20A, 3-3X20A, 30mA, 220V, Reserva 12 POLOS und 1.00 907.60 907.60302 05.04 TG-01 con Int. Aut.: 1-3x40A, 3-2x20A, 1-3x20A,1-3x32A, 220V, Reserva 18 POLOS und 1.00 1,189.56 1,189.56303 06 Conductos y/o Cables 10,069.93304 06.01 ALIM.CAB. LSOH 2X4mm2 m 714.49 13.98 9,988.57305 06.02 ALIM.CAB. LSOH 2X6mm2 m 5.82 13.98 81.36306 07 Artefactos 4,795.63307 07.01 ART.FLUOR PARA ENDOZAR.3/36W C/REJ.MET.EMPOTRADO AF similar al tipo RAS -A-3x36 und 24.00 96.76 2,322.24308 07.02 ART.AHORRADOR 20W INC. ACCESORIOS . und 25.00 52.26 1,306.50309 07.03 BRAQUERE REFLECTOR C/LAMP. 2X18W - AHORRAD. SIMILAR RSP und 4.00 65.36 261.44310 07.04 POSTE CON DOS FAROLA HPC 144 PHILIPS LAMPARA HG 250 W und 1.00 405.17 405.17311 07.05 CAMPANILLA DE TIMBRE DE 8'' CON TRANSF. 220/12V und 1.00 114.74 114.74312 07.06 TIMBRE DING DONG DOMICILIARIO und 1.00 114.74 114.74313 07.07 LAMPARA DE EMERGENCIA und 2.00 135.40 270.80314 08 SISTEMA DE TIERRA 139.80315 08.01 CAJA PORTAMEDIDOR EQUIPADPO CON MEDIDOR ELECTRÓNICO E INTERRUPTOR und 1.00 139.80 139.80316 09 SISTEMA DE CONDUCTOS 740.00317 09.01 BUZONETA ELECTRICA und 4.00 185.00 740.00318 10 Puesta a Tierra 594.23319 10.01 PUESTA A TIERRA CON ELECTRODO COOPERWELD und 1.00 594.23 594.23320 11 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 16,039.13 16,039.13

COSTO DIRECTO 758,610.72GASTOS GENERALES 9.00% 9.00% 68,274.96UTILIDAD 8.00 % 8.00% 60,688.86SUB TOTAL 887,574.54SUBTOTAL X FR 90.00% 798,817.09IGV (18% ST) 18.00% 143,787.08MOBILIARIO, EQUIPAMIENTO Y MATERIALES EDUCATIVOS INC(IGV) 41,989.36PLAN DE MONITOREO ARQUELOGICO 9,803.32COSTO DE OBRA 994,396.85

Page 5: cronograma valorizado - CASCAJAL

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

“MEJORAMIENTO DEL SERVICIO EDUCATIVO POR AMPLIACION DE COBERTURA EN LAS INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL, N° 365 CENTRO POBLADO DE CALLEJON DE CASCAJAL DEL DISTRITO DE OLMOS PROVINCIA DE LAMBAYEQUE, DEPARTAMENTO DE LAMBAYEQUE.”

UBICACIÓN OLMOS - LAMBAYEQUE - LAMBAYEQUE ENTIDAD: GOBIERNO REGIONAL DE LAMBAYEQUEFEBRERO DEL 2016 CONTRATISTA: CONSORCIO CALLEJON DE CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

01 OBRAS PROVISIONALES 20,380.02 14,174.01 2,046.05 2,109.92 2,050.04 20,380.02

01.01 ALMACEN, OFICINAS Y CASETA DE GUARDIANIA glb 1.00 2,755.56 2,755.56 2,755.56 2,755.56

01.02 CARTEL DE OBRA 3.60 x 7.20 und 1.00 2,910.11 2,910.11 2,910.11 2,910.11

01.03 SERVICIOS HIGIENICOS PORTATILES mes 4.00 950.00 3,800.00 953.99 926.05 989.92 930.04 3,800.00

01.04 AGUA PARA LA OBRA glb 1.00 4,000.00 4,000.00 1,000.00 1,000.00 1,000.00 1,000.00 4,000.00

01.05 ENERGIA ELECTRICA PARA LA OBRA glb 1.00 480.00 480.00 120.00 120.00 120.00 120.00 480.00

01.06 CERCO PROVISIONAL DE OBRA m 95.00 67.73 6,434.35 6,434.35 6,434.35

02 TRABAJOS PRELIMINARES 1,881.00 1,881.00 0.00 0.00 0.00 1,881.00

02.01 LIMPIEZA DEL TERRENO MANUAL m2 570.00 3.30 1,881.00 1,881.00 1,881.00

03 MOVILIZACION DE EQUIPOS Y HERRAMIENTAS 5,175.00 5,175.00 0.00 0.00 0.00 5,175.00

03.01 TRANSPORTE DE EQUIPO Y MAQUINARIAS glb 1.00 5,175.00 5,175.00 5,175.00 5,175.00

04 TRAZO, NIVELES Y REPLANTEO 1,219.80 1,219.80 0.00 0.00 0.00 1,219.80

04.01 TRAZO Y REPLANTEO PRELIMINAR m2 570.00 2.14 1,219.80 1,219.80 1,219.80

05 SEGURIDAD Y SALUD 7,450.67 2,987.67 1,487.67 1,487.67 1,487.67 7,450.67

05.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 1,500.00 1,500.00 1,500.00 1,500.00

05.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 1,608.26 1,608.26 402.07 402.07 402.07 402.07 1,608.26

05.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,142.41 1,142.41 285.60 285.60 285.60 285.60 1,142.41

05.04 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 1,940.00 1,940.00 485.00 485.00 485.00 485.00 1,940.00

05.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO glb 1.00 1,260.00 1,260.00 315.00 315.00 315.00 315.00 1,260.00

06 MOVIMIENTO DE TIERRAS 39,907.69 7,332.22 13,765.02 18,810.46 0.00 39,907.69

06.01 EXCAVACION PARA CIMIENTOS, PISOS Y VEREDAS m3 202.04 28.51 5,760.16 5,760.16 5,760.16

06.02 CORTE DE TERRENO MANUAL HASTA 0.40 M DE PROF. m3 82.74 19.00 1,572.06 1,572.06 1,572.06

06.03 RELLENO COMPACTADO C/EQUIPO, MATERIAL PROPIO m3 39.01 21.25 828.96 535.37 293.59 828.96

06.04 RELLENO CON MATERIAL PRESTAMO (HORMIGÓN) m3 202.62 51.24 10,382.25 9,263.07 1,119.18 10,382.25

06.05 RELLENO CON MATERIAL PRESTAMO(AFIRMADO) m3 90.46 56.89 5,146.27 2,573.14 2,573.14 5,146.27

06.06 RELLENO CON MATERIAL PRESTAMO(ARENA FINA) m3 9.92 91.29 905.60 452.80 452.80 905.60

06.07 NIVELACION INTERIOR Y APISONADO m2 521.13 3.61 1,881.28 940.64 940.64 1,881.28

06.08 ACARREO Y ELIMIN. DE MAT. EXCEDENTE m3 294.93 16.29 4,804.41 4,804.41 4,804.41

06.09 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE 10M3 Y CARGADOR Dprom=10 km m3 294.93 29.25 8,626.70 8,626.70 8,626.70

07 OBRAS DE CONCRETO SIMPLE 19,203.02 10,849.33 4,176.85 4,176.85 0.00 19,203.02

07.01 SOLADO DE CONCRETO E=4'' (CONCRETO 1:10 C-H) m3 6.93 102.38 709.49 709.49 709.49

07.02 CIMIENTOS CORRIDOS 1:10 + 30% P.G m3 57.43 176.56 10,139.84 10,139.84 10,139.84

07.03 FALSO PISO MEZCLA C:H 1:8 E=10CM m2 282.41 29.58 8,353.69 4,176.85 4,176.85 8,353.69

08 OBRAS DE CONCRETO ARMADO 262,954.00 6,873.10 220,626.30 35,420.90 33.70 ###

08.01 ZAPATAS 27,246.07 6,873.06 20,373.01 0.00 0.00 27,246.07

08.01.01 CONCRETO EN ZAPATAS f'c=210 Kg/cm2 m3 41.53 406.13 16,866.58 16,866.58 16,866.58

08.01.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,121.34 3.99 4,474.15 4,474.15 4,474.15

08.01.03 ENCOFRADO Y DESENCOFRADO EN ZAPATAS m2 121.86 48.46 5,905.34 2,398.91 3,506.43 5,905.34

08.02 VIGAS DE CIMENTACION 36,908.67 0.00 36,908.67 0.00 0.00 36,908.67

08.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 Kg/cm2 m3 33.24 404.71 13,452.56 13,452.56 13,452.56

08.02.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 3,646.03 3.99 14,547.66 14,547.66 14,547.66

08.02.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION m2 203.25 43.83 8,908.45 8,908.45 8,908.45

08.03 SOBRECIMIENTOS ARMADOS 23,590.12 0.00 23,590.12 0.00 0.00 23,590.12

08.03.01 CONCRETO EN SOBRECIMIENTO REFORZADO f'c=210 Kg/cm2 m3 21.74 406.75 8,842.75 8,842.75 8,842.75

08.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,200.85 3.99 4,791.39 4,791.39 4,791.39

08.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO REFORZADO m2 227.15 43.83 9,955.98 9,955.98 9,955.98

08.04 COLUMNAS 59,275.75 0.00 59,275.75 0.00 0.00 59,275.75

08.04.01 CONCRETO EN COLUMNAS f'c=210 Kg/cm2 m3 34.12 418.69 14,285.70 14,285.70 14,285.70

08.04.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 6,435.35 3.99 25,677.05 25,677.05 25,677.05

08.04.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 397.06 48.64 19,313.00 19,313.00 19,313.00

08.05 COLUMNENTAS 12,438.31 0.00 12,438.31 0.00 0.00 12,438.31

08.05.01 CONCRETO COLUMNETAS f'c=175 kg/cm2 m3 6.15 409.39 2,517.75 2,517.75 2,517.75

08.05.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 806.63 3.99 3,218.45 3,218.45 3,218.45

08.05.03 ENCOFRADO Y DESENCOFRADO EN COLUMNETAS m2 137.79 48.64 6,702.11 6,702.11 6,702.11

08.06 VIGAS 42,476.84 0.00 42,476.84 0.00 0.00 42,476.84

08.06.01 CONCRETO EN VIGAS f'c =210 Kg/cm2 m3 30.97 395.67 12,253.90 12,253.90 12,253.90

08.06.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 4,470.75 3.99 17,838.29 17,838.29 17,838.29

08.06.03 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 231.10 53.59 12,384.65 12,384.65 12,384.65

08.07 VIGUETAS 3,609.77 0.00 0.00 3,609.77 0.00 3,609.77

PROYECTO :

FECHA :

PRESUPUESTOS/.

Page 6: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

08.07.01 CONCRETO VIGUETAS f'c=175 kg/cm2 m3 2.13 385.71 821.56 821.56 821.56

08.07.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 258.53 3.99 1,031.53 1,031.53 1,031.53

08.07.03 ENCOFRADO Y DESENCOFRADO EN VIGUETAS m2 32.78 53.59 1,756.68 1,756.68 1,756.68

08.08 LOSAS ALIGERADAS 42,489.82 0.00 25,563.63 16,926.20 0.00 42,489.82

08.08.01 CONCRETO EN LOSAS ALIGERADAS f'c=210 Kg/cm2 m3 29.23 395.67 11,565.43 5,782.72 5,782.72 11,565.43

08.08.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,103.70 3.99 8,393.76 4,196.88 4,196.88 8,393.76

08.08.03 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 333.85 47.01 15,694.29 8,747.69 6,946.60 15,694.29

08.08.04 LADRILLO DE ARCILLA 15X30X30 cm PARA LOSA ALIGERADA und 2,779.00 2.46 6,836.34 6,836.34 6,836.34

08.09 LOSAS MACIZAS 1,115.13 0.00 0.00 1,115.13 0.00 1,115.13

08.09.01 CONCRETO EN LOSA MACIZAS f'c=210 kg/cm2 m3 1.08 362.81 391.83 391.83 391.83

08.09.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 100.69 3.99 401.75 401.75 401.75

08.09.03 ENCOFRADO Y DESENCOFRADO DE LOSAS MACIZAS m2 6.84 47.01 321.55 321.55 321.55

08.10 ESCALERAS 1,964.49 0.00 0.00 1,964.49 0.00 1,964.49

08.10.01 CONCRETO EN ESCALERAS f'c=175 kg/cm2 m3 1.47 418.62 615.37 615.37 615.37

08.10.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 160.06 3.99 638.64 638.64 638.64

08.10.03 ENCOFRADO Y DESENCOFRADO DE ESCALERA m2 16.21 43.83 710.48 710.48 710.48

08.11 CISTERNA 7,660.27 0.00 0.00 7,626.55 33.72 7,660.27

08.11.01 CISTERNA CONCRETO F'C= 175 KG/CM2 m3 3.16 418.62 1,322.84 1,322.84 1,322.84

08.11.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 16.21 3.99 64.68 64.68 64.68

08.11.03 CISTERNA ENCOFRADO Y DESENCOFRADO m2 160.06 39.19 6,272.75 6,239.03 33.72 6,272.75

08.12 POZO SEPTICO 2,825.52 0.00 0.00 2,825.52 0.00 2,825.52

08.12.01 CONCRETO EN POZO SEPTICO f'c=175 kg/cm2 m3 3.84 418.62 1,607.50 1,607.50 1,607.50

08.12.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 177.09 3.99 706.59 706.59 706.59

08.12.03 ENCOFRADO Y DESENCOFRADO EN POZO SEPTICO m2 13.05 39.19 511.43 511.43 511.43

08.13 FOSA DE PERCOLACION 1,103.24 0.00 0.00 1,103.24 0.00 1,103.24

08.13.01 CONCRETO EN FOSA DE PERCOLACIÓN f'c=175 kg/cm2 m3 1.55 418.62 648.86 648.86 648.86

08.13.02 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 91.78 3.99 366.20 366.20 366.20

08.13.03 ENCOFRADO Y DESENCOFRADO EN FOSA DE PERCOLACION m2 2.25 39.19 88.18 88.18 88.18

08.14 BANCA DE CONCRETO 250.00 0.00 0.00 250.00 0.00 250.00

08.14.01 BANCA DE CONCRETO TIPO 1 SEGUN DISEÑO und 1.00 250.00 250.00 250.00 250.00

09 OTROS 30,263.25 7,565.81 7,565.81 7,565.81 7,565.81 30,263.25

09.01 FLETE TERRESTRE (CHICLAYO - OBRA) glb 1.00 30,263.25 30,263.25 7,565.81 7,565.81 7,565.81 7,565.81 30,263.25

01 MUROS Y TABIQUES DE ALBAÑILERIA 30,589.29 0.00 19,523.78 11,065.51 0.00 30,589.29

01.01 MURO DE LADRILLO KK DE ARCILLA DE CABEZA C/M 1:5 X 1.5 CM m2 220.36 80.22 17,677.28 12,376.40 5,300.88 17,677.28

01.02 MURO DE LADRILLO KK DE ARCILLA DE SOGA C/M 1:5 X 1.5 CM m2 202.66 58.98 11,952.89 7,147.38 4,805.51 11,952.89

01.03 MURO DE LADRILLO KK DE ARCILLA DE CANTOC/M 1:5 X 1.5 CM m2 14.38 53.77 773.21 773.21 773.21

01.04 ALAMBRE #8 REFUERZO HORIZONTAL kg 50.52 3.68 185.91 185.91 185.91

02 MUROS ESPECIALES 262.05 0.00 0.00 0.00 262.05 262.05

02.01 MURO DE PIEDRA D=6" m2 7.50 34.94 262.05 262.05 262.05

03 REVOQUES, ENLUCIDOS Y MOLDURAS 55,229.18 0.00 0.00 55,229.18 0.00 55,229.18

03.01 TARRAJEO MUROS PRIMARIO m2 136.53 20.18 2,755.18 2,755.18 2,755.18

03.02 TARRAJEO FROTACHADO DE MUROS INTERIORES 1:4 , E= 1,5 CM m2 421.47 30.23 12,741.04 12,741.04 12,741.04

03.03 TARRAJEO FROTACHADO DE MUROS EXTERIORES 1:4 , e = 1.5 cm m2 383.42 33.71 12,925.09 12,925.09 12,925.09

03.04 TARRAJEO FROTACHADO DE COLUMNAS 1:4 E= 1.5CM m2 249.22 38.15 9,507.74 9,507.74 9,507.74

03.05 TARRAJEO FROTACHADO DE VIGAS 1:4 , e = 1.5 cm m2 194.85 39.88 7,770.62 7,770.62 7,770.62

03.06 TARRAJEO FONDO DE ESCALERAS m2 4.78 33.05 157.98 157.98 157.98

03.07 TARRAJEO IMPERMEABILIZADO m2 11.05 39.30 434.27 434.27 434.27

03.08 VESTIDURA DE DERRAMES m 291.61 13.74 4,006.72 4,006.72 4,006.72

03.09 JUNTA DE DILATACIÓN CON MATERIAL MICROPOROSO m 64.50 8.82 568.89 568.89 568.89

03.10 BRUÑAS DE 1 cm x 1 cm m 461.55 9.45 4,361.65 4,361.65 4,361.65

04 CIELO RRASOS 11,538.18 0.00 0.00 11,538.18 0.00 11,538.18

04.01 TARRAJEO FROTACHADO DE CIELO RASO 1:4 , e = 1.5 cm m2 362.38 31.84 11,538.18 11,538.18 11,538.18

05 PISOS Y CONTRAPISOS 40,738.98 0.00 0.00 7,822.43 32,916.55 40,738.98

05.01 CONTRAPISO 7,822.43 0.00 0.00 7,822.43 0.00 7,822.43

05.01.01 CONTRAPISO DE 40mm, MEZCLA 1:5, ACABADO 1:2 m2 362.99 21.55 7,822.43 7,822.43 7,822.43

05.02 PISOS Y PAVIMENTOS 32,916.55 0.00 0.00 0.00 32,916.55 32,916.55

05.02.01 PISO DE PORCELANATO DE 60 X 60 CM m2 96.13 74.95 7,204.94 7,204.94 7,204.94

05.02.02 PISO DE LOSETA VENECIANA DE 30 X 30 CM m2 131.42 63.54 8,350.43 8,350.43 8,350.43

05.02.03 PISO CERÁMICO DE 30x30cm m2 78.36 59.74 4,681.23 4,681.23 4,681.23

05.02.04 PISO CERAMICO 40 X 40 m2 59.90 63.52 3,804.85 3,804.85 3,804.85

05.02.05 PISO DE CEMENTO PULIDO Y BRUÑADO m2 5.27 29.53 155.62 155.62 155.62

05.02.06 VEREDA DE CONCRETO F'C= 140KG/CM2 , E=4" ACABADO PULIDO Y BRUÑADO m2 66.91 52.54 3,515.45 3,515.45 3,515.45

05.02.07 RAMPA DE CONCRETO F'C= 140KG/CM2 , E=4" ACABADO PULIDO Y BRUÑADO m2 18.80 52.54 987.75 987.75 987.75

05.02.08 LOSA DE CONCRETO F'C= 140 KG/CM2, E=5" ACABADO BRUÑADO Y FROTACHADO m2 72.90 54.71 3,988.36 3,988.36 3,988.36

05.02.09 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO e=1" y TECKNOPORT m 48.70 4.68 227.92 227.92 227.92

06 ZOCALOS 7,331.66 0.00 0.00 0.00 7,331.66 7,331.66

Page 7: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

06.01 ZÓCALO DE CERÁMICO 30X30 cm m2 136.53 53.70 7,331.66 7,331.66 7,331.66

07 CONTRAZOCALOS 6,114.13 0.00 0.00 0.00 6,114.13 6,114.13

07.01 CONTRAZOCALO DE CEMENTO PULIDO m2 67.44 31.17 2,102.10 2,102.10 2,102.10

07.02 CONTRAZOCALO DE LOSETA H=0.10 m 76.85 22.64 1,739.88 1,739.88 1,739.88

07.03 CONTRAZOCALO DE PORCELANATO H=0.10 m 35.55 23.37 830.80 830.80 830.80

07.04 CONTRAZ0CALO DE CERAMICO H=10 cm m 66.76 21.59 1,441.35 1,441.35 1,441.35

08 COBERTURA 23,651.36 0.00 0.00 23,651.36 0.00 23,651.36

08.01 CORREAS DE MADERA 2"X2" m 429.20 15.23 6,536.72 6,536.72 6,536.72

08.02 COBERTURA CON TEJA ANDINA m2 361.10 46.54 16,805.59 16,805.59 16,805.59

08.03 COBERTURA CON TEJA PLANA m2 5.70 54.22 309.05 309.05 309.05

09 CARPINTERIA DE MADERA 30,364.94 0.00 0.00 0.00 30,364.94 30,364.94

09.01 PUERTA DE MADERA CEDRO, MACHIEMBRADA EXTERIOR, CONTRAPLACAD INTERIOR (SEGUN DISEÑO) m2 18.96 423.73 8,033.92 8,033.92 8,033.92

09.02 PUERTA DE MADERA CEDRO CONTRAPLACADA (SEGUN DISEÑO) m2 18.96 296.61 5,623.73 5,623.73 5,623.73

09.03 PUERTA DE MADERA CEDRO TIPO TABLERO (SEGUN DISEÑO) m2 4.99 254.24 1,268.66 1,268.66 1,268.66

09.04 PUERTA DE MADERA APANELADA m2 1.89 258.90 489.32 489.32 489.32

09.05 VENTANA DE MADERA CEDRO (SEGUN DISEÑO) m2 58.80 254.24 14,949.31 14,949.31 14,949.31

10 CARPINTERIA METALICA Y HERRERIA 14,255.75 0.00 0.00 0.00 14,255.75 14,255.75

10.01 PORTON METÁLICO SEGÚN DISEÑO m2 7.95 423.73 3,368.65 3,368.65 3,368.65

10.02 PUERTA METÁLICA DE 1.00 X 2.50 M und 2.50 423.73 1,059.33 1,059.33 1,059.33

10.03 BARANDAS METALICAS DE D= 2" m 3.82 134.97 515.59 515.59 515.59

10.04 BARANDAS METALICAS DE D= 1 1/2" m 16.62 121.32 2,016.34 2,016.34 2,016.34

10.05 BARANDAS METALICAS DE D= 1" m 36.08 111.87 4,036.27 4,036.27 4,036.27

10.06 PARANTE METALICO DE D= 1 1/2" m 12.85 121.32 1,558.96 1,558.96 1,558.96

10.07 CANTONERA DE ALUMINIO EN PASOS DE ESCALERA m 21.12 18.42 389.03 389.03 389.03

10.08 PUERTA METALICA DE 0.70x 0.65 m PARA CASETA DE ELECTROBOMBA m2 0.46 423.73 194.92 194.92 194.92

10.09 TAPA DE FIERRO DE 60 x 60 CON PLANCHA DE 1 /16" EN CISTERNA und 1.00 266.62 266.62 266.62 266.62

10.10 TAPA DE FIERRO DE 60 X 60 CON PLANCHA DE 1/16" EN POZO SÉPTICO und 1.00 266.62 266.62 266.62 266.62

10.11 TAPA DE FIERRO DE 60 X 60 CON PLANCHA DE 1/16" EN FOSA DE PERCOLACIÓN und 1.00 266.62 266.62 266.62 266.62

10.12 TAPA DE METALICA PARA TECHO DE 1.00 X 0.60 M und 1.00 316.80 316.80 316.80 316.80

11 CERRAJERIA 1,815.89 0.00 0.00 0.00 1,815.89 1,815.89

11.01 CERRADURAS TIPO PARCHE DE 2 GOLPES CON MANIJAS und 15.00 80.19 1,202.85 1,202.85 1,202.85

11.02 JALADOR Y PICAPORTE DE BRONCE und 5.00 16.88 84.40 84.40 84.40

11.03 SISTEMA PARA PUERTA TIPO VAIVEN und 1.00 264.32 264.32 264.32 264.32

11.04 SISTEMA PARA PUERTA CON CORREDERA und 1.00 264.32 264.32 264.32 264.32

12 VIDRIOS, CRISTALES Y SIMILARES 8,449.48 0.00 0.00 0.00 8,449.48 8,449.48

12.01 VIDRIO TEMPLADO DE 4MM p2 632.92 13.35 8,449.48 8,449.48 8,449.48

13 PINTURA 17,479.43 0.00 0.00 0.00 17,479.43 17,479.43

13.01 PINTURA LATEX 2 MANOS EN MUROS INTERIORES m2 447.30 10.23 4,575.88 4,575.88 4,575.88

13.02 PINTURA LATEX 2 MANOS EN MUROS EXTERIORES m2 315.98 10.89 3,441.02 3,441.02 3,441.02

13.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 194.85 12.12 2,361.58 2,361.58 2,361.58

13.04 PINTURA LATEX 2 MANOS EN VIGAS m2 249.22 12.12 3,020.55 3,020.55 3,020.55

13.05 PINTURA LATEX 2 MANOS EN CIELO RASO m2 362.38 11.26 4,080.40 4,080.40 4,080.40

14 VARIOS LIMPIEZA Y JARDINERIA 35,928.80 0.00 0.00 31,383.04 4,545.76 35,928.80

14.01 LIMPIEZA GENERAL DE OBRA m2 552.90 1.07 591.60 591.60 591.60

14.02 PIZARRA ACRÍLICA und 2.00 702.08 1,404.16 1,404.16 1,404.16

14.03 LETRAS METÁLICAS PARA PORTADA DE INGRESO glb 1.00 2,550.00 2,550.00 2,550.00 2,550.00

14.04 SEMBRADO DE GRASS m2 6.16 25.93 159.73 159.73 159.73

14.05 ASTA DE BANDERA H=8.50 m SEGÚN DISEÑO und 1.00 1,162.16 1,162.16 1,162.16 1,162.16

14.06 JUEGOS INFANTILES PREFABRICADOS und 1.00 19,525.42 19,525.42 19,525.42 19,525.42

14.07 ESTRUCTURAS METÁLICAS Y COBERTURA PARA AREA DE JUEGOS und 1.00 10,535.73 10,535.73 10,535.73 10,535.73

01 SISTEMA DE DESAGUE 12,022.18 0.00 0.00 5,513.50 6,508.68 12,022.18

01.01 SALIDA DE DESAGUE Y VENTILACION 2,410.16 0.00 0.00 2,410.16 0.00 2,410.16

01.01.01 SALIDA DE DESAGUE EN PVC 2" pto 12.00 60.70 728.40 728.40 728.40

01.01.02 SALIDA DE DESAGUE EN PVC 4" pto 10.00 78.71 787.10 787.10 787.10

01.01.03 SALIDA DE VENTILACION DE 2" pto 11.00 59.26 651.86 651.86 651.86

01.01.04 SALIDA DE DRENAJE PLUVIAL DE 2" pto 4.00 60.70 242.80 242.80 242.80

01.02 RED DE DERIVACION, RAMALES Y MONTANTES 3,676.04 0.00 0.00 0.00 3,676.04 3,676.04

01.02.01 TUBERIA PVC SAL DIAM=2'' m 98.71 17.20 1,697.81 1,697.81 1,697.81

01.02.02 TUBERIA PVC SAL DIAM=3'' m 3.72 17.70 65.84 65.84 65.84

01.02.03 TUBERIA PVC SAL DIAM=4'' m 81.24 23.54 1,912.39 1,912.39 1,912.39

01.03 EXCAVACIONES Y RELLENOS PARA REDES EXTERIORES DE DESAGUE 2,789.80 0.00 0.00 614.63 2,175.17 2,789.80

01.03.01 EXCAVACION DE ZANJAS m3 16.51 38.02 627.71 614.63 13.08 627.71

01.03.02 RELLENO CON MATERIAL PROPIO m3 16.51 32.58 537.90 537.90 537.90

01.03.03 CAMA DE APOYO 55.02 29.52 1,624.19 1,624.19 1,624.19

01.04 ADITAMIENTOS VARIOS 1,469.30 0.00 0.00 1,469.30 0.00 1,469.30

01.04.01 CODO DE 4" X 90° und 2.00 21.06 42.12 42.12 42.12

Page 8: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

01.04.02 CODO DE 2" X 90° und 11.00 18.66 205.26 205.26 205.26

01.04.03 CODO DE 2" X 45° und 1.00 18.66 18.66 18.66 18.66

01.04.04 "Y" DE 2" und 8.00 20.56 164.48 164.48 164.48

01.04.05 "Y" DE 4" und 1.00 24.48 24.48 24.48 24.48

01.04.06 "Y" DE 2" X 3" und 2.00 21.06 42.12 42.12 42.12

01.04.07 "Y" DE 2" X 4" und 8.00 21.96 175.68 175.68 175.68

01.04.08 "T" SANITARIA DE 2" und 1.00 18.86 18.86 18.86 18.86

01.04.09 SOMBRERO DE VENTILACION 2" und 11.00 10.94 120.34 120.34 120.34

01.04.10 SUMIDERO DE BRONCE ROSCADO 2" und 6.00 39.54 237.24 237.24 237.24

01.04.11 SUMIDERO DE BRONCE ROSCADO 3" und 1.00 53.61 53.61 53.61 53.61

01.04.12 REGISTRO DE BRONCE 2" und 2.00 35.40 70.80 70.80 70.80

01.04.13 REGISTRO DE BRONCE 4" und 5.00 59.13 295.65 295.65 295.65

01.05 CÁMARAS DE INSPECCION 1,019.41 0.00 0.00 1,019.41 0.00 1,019.41

01.05.01 CAJA DE REGISTRO DE CONCRETO 30X60 M (12"X24")C/TAPA CONCRETO und 7.00 145.63 1,019.41 1,019.41 1,019.41

Page 9: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

01.06 VARIOS 657.47 0.00 0.00 0.00 657.47 657.47

01.06.01 PRUEBA HIDRAULICA DE DESAGUE glb 1.00 657.47 657.47 657.47 657.47

02 SISTEMA DE AGUA FRIA 26,127.86 0.00 0.00 3,391.88 22,735.98 26,127.86

02.01 SALIDAS DE AGUA FRIA 1,914.88 0.00 0.00 1,914.88 0.00 1,914.88

02.01.01 SALIDA DE AGUA FRIA TUBERIA PVC P DE 1/2" pto 8.00 76.26 610.08 610.08 610.08

02.01.02 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 3/4" pto 16.00 81.55 1,304.80 1,304.80 1,304.80

02.02 TUBERIAS DE PVC-P 2,563.47 0.00 0.00 0.00 2,563.47 2,563.47

02.02.01 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1/2" m 13.11 21.58 282.91 282.91 282.91

02.02.02 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=3/4" m 69.13 22.19 1,533.99 1,533.99 1,533.99

02.02.03 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1 1/2" m 15.26 25.74 392.79 392.79 392.79

02.02.04 SUMINISTRO E INSTALACION DE TUBERIAS PVC-P Ø=1 1/4" m 14.30 24.74 353.78 353.78 353.78

02.03 EXCAVACIONES Y RELLENOS PARA REDES EXTERIORES DE AGUA 2,283.21 0.00 0.00 1,477.00 806.21 2,283.21

02.03.01 EXCAVACION DE ZANJAS m3 13.96 32.58 454.82 454.82 454.82

02.03.02 RELLENO CON MATERIAL PROPIO m3 13.96 32.58 454.82 454.82 454.82

02.03.03 CAMA DE APOYO m 46.53 29.52 1,373.57 1,022.18 351.39 1,373.57

02.04 ADITAMIENTOS VARIOS 174.27 0.00 0.00 0.00 174.27 174.27

02.04.01 CODO DE 1/2" X 90° und 6.00 2.65 15.90 15.90 15.90

02.04.02 CODO DE 3/4" X 90° und 10.00 3.16 31.60 31.60 31.60

02.04.03 CODO DE 3/4" X 45° und 1.00 3.16 3.16 3.16 3.16

02.04.04 CODO DE 1 1/4" X 90° und 2.00 9.18 18.36 18.36 18.36

02.04.05 CODO DE 1 1/2" X 90° und 2.00 10.18 20.36 20.36 20.36

02.04.06 CODO DE 2" X 90° und 2.00 11.18 22.36 22.36 22.36

02.04.07 TEE PVC 3/4" und 4.00 3.59 14.36 14.36 14.36

02.04.08 TEE PVC 1 1/4" und 1.00 8.59 8.59 8.59 8.59

02.04.09 TEE PVC 1 1/2" und 1.00 8.59 8.59 8.59 8.59

02.04.10 REDUCCION DE 3/4" A 1/2" und 1.00 3.25 3.25 3.25 3.25

02.04.11 REDUCCION DE 1 1/2" A 1 1/4" und 1.00 6.26 6.26 6.26 6.26

02.04.12 REDUCCION DE 1 1/4" A 3/4" und 1.00 5.86 5.86 5.86 5.86

02.04.13 REDUCCION DE 2" A 3/4" und 1.00 7.36 7.36 7.36 7.36

02.04.14 REDUCCION DE 2" A 1 1/2" und 1.00 8.26 8.26 8.26 8.26

02.05 VALVULAS Y ACCESORIOS 5,676.77 0.00 0.00 0.00 5,676.77 5,676.77

02.05.01 VALVULA ESFERICA DE BRONCE Ø=1/2" und 5.00 41.61 208.05 208.05 208.05

02.05.02 VALVULA ESFERICA DE BRONCE Ø=3/4" und 4.00 72.87 291.48 291.48 291.48

02.05.03 VALVULA ESFERICA DE 1¼" und 2.00 147.87 295.74 295.74 295.74

02.05.04 VALVULA ESFERICA DE 1½" und 1.00 203.07 203.07 203.07 203.07

02.05.05 VALVULA ESFERICA DE 2" und 1.00 275.39 275.39 275.39 275.39

02.05.06 VALVULA CHECK DE BRONCE DE 1/2" und 1.00 108.63 108.63 108.63 108.63

02.05.07 VALVULA CHECK DE BRONCE DE 3/4" und 5.00 112.03 560.15 560.15 560.15

02.05.08 VALVULA CHECK DE BRONCE DE 1 1/4" und 2.00 152.25 304.50 304.50 304.50

02.05.09 VALVULA CHECK DE BRONCE DE 1 1/2" und 1.00 168.70 168.70 168.70 168.70

02.05.10 CAJA PARA ALOJAMIENTO DE VALVULAS EN MURO C/TAPA S/DETALLE und 22.00 148.23 3,261.06 3,261.06 3,261.06

02.06 APARATOS SANITARIOS Y ACCESORIOS 8,301.11 0.00 0.00 0.00 8,301.11 8,301.11

02.06.01 INODORO BABY COLOR BLANCO (INCLUY. ACCESORIOS) und 7.00 282.33 1,976.31 1,976.31 1,976.31

02.06.02 INODORO SIFON JET COLOR BLANCO (INCLUY. ACCESORIOS) und 2.00 232.16 464.32 464.32 464.32

02.06.03 OVALIN SONNET COLOR BLANCO (INCLUY. ACCESORIOS) und 4.00 297.32 1,189.28 1,189.28 1,189.28

02.06.04 LAVATORIO FONTANA COLOR BLANCO, INC. ACCESORIOS und 3.00 237.08 711.24 711.24 711.24

02.06.05 LAVATORIO MALIBU COLOR BLANCO, INC. ACCESORIOS und 2.00 248.08 496.16 496.16 496.16

02.06.06 LAVADERO DE ACERO INOXIDABLE UNA POZA und 1.00 393.93 393.93 393.93 393.93

02.06.07 LAVADERO DE ACERO INOXIDABLE UNA POZA CON ESCURRIDERO PARA COCINA und 1.00 433.93 433.93 433.93 433.93

02.06.08 LAVADERO DE ACERO INOXIDABLE UNA POZA CON ESCURRIDERO PARA TOPICO und 1.00 433.93 433.93 433.93 433.93

02.06.09 URINARIO BAMBI COLOR BLANCO, INC/ACCESORIO und 2.00 655.27 1,310.54 1,310.54 1,310.54

02.06.10 PAPELERA LOSA BLANCO und 9.00 31.00 279.00 279.00 279.00

02.06.11 JABONERA LOSA BLANCO und 8.00 22.38 179.04 179.04 179.04

Page 10: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

02.06.12 ESPEJO DE 2.40 X 0.60 M und 1.00 264.16 264.16 264.16 264.16

02.06.13 ESPEJO DE 0.90 X 0.60 M und 1.00 104.16 104.16 104.16 104.16

02.06.14 GRIFO DE RIEGO DE 1/2" und 1.00 65.11 65.11 65.11 65.11

02.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS DE SUCCION 226.99 0.00 0.00 0.00 226.99 226.99

02.07.01 TUBERIA PVC SAP DIAM=1'' C-10 m 1.56 17.97 28.03 28.03 28.03

02.07.02 VALVULA DE PIE DE 1" und 1.00 38.94 38.94 38.94 38.94

02.07.03 VALVULA COMPUERTA DE 1" und 1.00 85.98 85.98 85.98 85.98

02.07.04 VALVULA FLOTADOR DE 1" und 1.00 74.04 74.04 74.04 74.04

02.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS DE IMPULSION 411.92 0.00 0.00 0.00 411.92 411.92

02.08.01 TUBERIA PVC SAP DIAM=1'' C-10 m 13.47 17.97 242.06 242.06 242.06

02.08.02 VALVULA MARIPOSA DE 1" und 1.00 74.88 74.88 74.88 74.88

02.08.03 VALVULA CHECK DE BRONCE DE 1" und 1.00 94.98 94.98 94.98 94.98

02.09 EQUIPOS Y OTRAS INSTALACIONES 3,250.66 0.00 0.00 0.00 3,250.66 3,250.66

02.09.01 TANQUE ELEVADO ROTOPLAS 1M3 und 1.00 1,125.33 1,125.33 1,125.33 1,125.33

02.09.02 ELECTROBOMBAS INCLUYE TABLERO und 1.00 2,125.33 2,125.33 2,125.33 2,125.33

02.10 VARIOS 1,324.58 0.00 0.00 0.00 1,324.58 1,324.58

02.10.01 PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIAS DE AGUA Y CISTERNA glb 1.00 1,324.58 1,324.58 1,324.58 1,324.58

01 Salida para alumbrado, tomacorrientes, fuerzas y señales debiles 7,918.90 0.00 0.00 7,626.31 292.59 7,918.90

01.01 SALIDA CENTRO DE ALUMBRADO EMPOTRADO pto 49.00 78.42 3,842.58 3,549.99 292.59 3,842.58

01.02 SALIDA PARA BRAQUETE (PARED) pto 4.00 78.06 312.24 312.24 312.24

01.03 SALIDA TOMACORRIENTE MONOF. DOBLE CON LINEA A TIERRA pto 30.00 85.47 2,564.10 2,564.10 2,564.10

01.04 SALIDA PARA INTERRUPTOR SIMPLE und 14.00 31.58 442.12 442.12 442.12

01.05 SALIDA PARA INTERRUPTOR DOBLE und 5.00 35.82 179.10 179.10 179.10

01.06 SALIDA PARA INTERRUPTOR TRIPLE und 1.00 39.79 39.79 39.79 39.79

01.07 SALIDA PARA INTERRUPTOR CONMUTADOR SIMPLE und 4.00 34.12 136.48 136.48 136.48

01.08 SALIDA PARA INTERRUPTOR CONMUTADOR DOBLE und 2.00 38.36 76.72 76.72 76.72

01.09 SALIDA PARA INTERRUPTOR CONMUTADOR TRIPLE und 2.00 41.69 83.38 83.38 83.38

01.10 SALIDA PARA FAROLES pto 1.00 85.26 85.26 85.26 85.26

01.11 SALIDA PARA ELECTROBOMBA pto 1.00 157.13 157.13 157.13 157.13

02 Salida para Comunicaciones y Señales (Voz y Data) 303.69 0.00 0.00 303.69 0.00 303.69

02.01 SALIDA PARA TELEFONO Y/O INTERCOMUNICADORES pto 1.00 98.43 98.43 98.43 98.43

02.02 SALIDA PARA TIMBRE TIPO GONG CON PVC pto 1.00 95.47 95.47 95.47 95.47

02.03 SALIDA PARA TIMBRE TIPO DING DONG CON PVC pto 1.00 109.79 109.79 109.79 109.79

03 Canalización y/o Tubería 4,186.84 0.00 0.00 2,221.76 1,965.08 4,186.84

03.01 EXCAVACION DE ZANJAS PARA REDES EXT.SANIT-ELECT. m3 11.10 38.02 422.02 422.02 422.02

03.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT.ELEC.SANIT). m3 7.77 32.58 253.15 253.15 253.15

03.03 TUBERIA PVC - P 20 mm. ml 357.24 9.83 3,511.67 1,799.74 1,711.93 3,511.67

04 Cajas 81.10 0.00 0.00 81.10 0.00 81.10

04.01 CAJA DE PASE FºGº 6'' X 6'' X 3'' und 2.00 40.55 81.10 81.10 81.10

05 Tableros y cuchillas 3,407.86 0.00 0.00 3,407.86 0.00 3,407.86

05.01 TD-1 con Int. Aut.: 1-3x30A, 2-2x20A, 30mA, 220V, Reserva 12 POLOS und 1.00 604.90 604.90 604.90 604.90

05.02 TD-2 con Int. Aut.: 1-3x30A, 2-2x20A, 1-3x20A, 30mA, 220V, Reserva 12 POLOS und 1.00 705.80 705.80 705.80 705.80

05.03 TD-3 con Int. Aut.: 1-3x30A, 2-2x20A, 3-3X20A, 30mA, 220V, Reserva 12 POLOS und 1.00 907.60 907.60 907.60 907.60

05.04 TG-01 con Int. Aut.: 1-3x40A, 3-2x20A, 1-3x20A,1-3x32A, 220V, Reserva 18 POLOS und 1.00 1,189.56 1,189.56 1,189.56 1,189.56

06 Conductos y/o Cables 10,069.93 0.00 0.00 4,375.50 5,694.43 10,069.93

06.01 ALIM.CAB. LSOH 2X4mm2 m 714.49 13.98 9,988.57 4,294.14 5,694.43 9,988.57

06.02 ALIM.CAB. LSOH 2X6mm2 m 5.82 13.98 81.36 81.36 81.36

07 Artefactos 4,795.63 0.00 0.00 1,166.89 3,628.74 4,795.63

07.01 ART.FLUOR PARA ENDOZAR.3/36W C/REJ.MET.EMPOTRADO AF similar al tipo RAS -A-3x36 und 24.00 96.76 2,322.24 2,322.24 2,322.24

07.02 ART.AHORRADOR 20W INC. ACCESORIOS . und 25.00 52.26 1,306.50 1,306.50 1,306.50

07.03 BRAQUERE REFLECTOR C/LAMP. 2X18W - AHORRAD. SIMILAR RSP und 4.00 65.36 261.44 261.44 261.44

07.04 POSTE CON DOS FAROLA HPC 144 PHILIPS LAMPARA HG 250 W und 1.00 405.17 405.17 405.17 405.17

07.05 CAMPANILLA DE TIMBRE DE 8'' CON TRANSF. 220/12V und 1.00 114.74 114.74 114.74 114.74

07.06 TIMBRE DING DONG DOMICILIARIO und 1.00 114.74 114.74 114.74 114.74

07.07 LAMPARA DE EMERGENCIA und 2.00 135.40 270.80 270.80 270.80

08 SISTEMA DE TIERRA 139.80 0.00 0.00 0.00 139.80 139.80

08.01 CAJA PORTAMEDIDOR EQUIPADPO CON MEDIDOR ELECTRÓNICO E INTERRUPTOR und 1.00 139.80 139.80 139.80 139.80

09 SISTEMA DE CONDUCTOS 740.00 0.00 0.00 0.00 740.00 740.00

09.01 BUZONETA ELECTRICA und 4.00 185.00 740.00 740.00 740.00

10 PUESTA A TIERRA 594.23 0.00 0.00 0.00 594.23 594.23

10.01 PUESTA A TIERRA CON ELECTRODO COOPERWELD und 1.00 594.23 594.23 594.23 594.23

11 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 16,039.13 16,039.13 4,009.78 4,009.78 4,009.78 4,009.78 16,039.13

COSTO DIRECTO 758,610.72 62,067.72 273,201.26 242,359.58 180,982.17 758,610.72

GASTOS GENERALES 9% 9.00% 68,274.96 5,586.09 24,588.11 21,812.36 16,288.40 68,274.96

UTILIDAD 8% 8.00% 60,688.86 4,965.42 21,856.10 19,388.77 14,478.57 60,688.86

SUB TOTAL 887,574.54 72,619.23 319,645.47 283,560.71 211,749.14 887,574.54

Page 11: cronograma valorizado - CASCAJAL

ITEM PARTIDAS UndPLAZO DE EJECUCION : 120 D.C

TOTALMETRADO PARCIAL TOTAL MES 1 MES 2 MES 3 MES 4

PRESUPUESTOS/.

SUB TOTAL * FR 90.00% 798,817.09 65,357.30 287,680.91 255,204.63 190,574.22 798,817.09

IGV (18% ST) 18.00% 143,787.08 11,764.31 51,782.56 45,936.83 34,303.36 143,787.08

MOBILIARIO, EQUIPAMIENTO Y MATERIALES EDUCATIVOS INC(IGV) 41,989.36 0.00 0.00 41,989.36 0.00 41,989.36

PLAN DE MONITOREO ARQUELOGICO 9,803.32 9,803.32 0.00 0.00 0.00 9,803.32

COSTO DE OBRA 994,396.85 86,924.93 339,463.47 343,130.82 224,877.58 994,396.85

AVANCE MENSUAL (%) 100.00% 8.74% 34.14% 34.51% 22.61% 100.00%

AVANCE ACUMULADO (%) 100.00% 8.74% 42.88% 77.39% 100.00% 100.00%