CURVA S

1
MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS MONTOS PORCENTAJES MONTOS PORCENTAJES MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL. S/. S/. % % S/. S/. % % 13-Jun-11 0 0 0 0 13-Jun-11 0 0 0 0 30-Jun-11 30,818.32 30,818.32 14.58% 14.58% 30-Jun-11 36,468.28 36,468.28 17.25% 17.25% 31-Jul-11 87,923.73 118,742.05 41.60% 56.18% 31-Jul-11 31-Aug-11 92,634.68 211,376.73 43.82% 100.00% 31-Aug-11 TOTAL 211,376.73 100.00% TOTAL 36,468.28 17.25% OBRA: "REHABILITACION DE VÍAS URBANAS DE LOS JIRONES: BOLOGNESI, INCLÁN Y MOQUEGUA DE LA CIUDAD DE HUANCANE, PROVINCIA DE HUANCANE - PUNO" - CONSTRUCCIÓN DE PAVIMENTO RIGIDO JR. INCLÁN 13-Jun-11 20-Jun-11 27-Jun-11 4-Jul-11 11-Jul-11 18-Jul-11 25-Jul-11 1-Aug-11 8-Aug-11 15-Aug-11 22-Aug-11 29-Aug-11 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 14.58% 56.18% 100.00% 0 17.25% (Gráfico Nº 01) AVANCES EN PORCENTAJES ACUMULADOS PROGRAMADO vs EJECUTADO PROGRAMADO EJECUTADO PLAZO DE EJECUCION (MESES) AVANCE MENSUAL ACUMULADO (%)

description

fgh

Transcript of CURVA S

% Prog-vs-EjecOBRA: "REHABILITACION DE VAS URBANAS DE LOS JIRONES: BOLOGNESI, INCLN Y MOQUEGUA DE LA CIUDAD DE HUANCANE, PROVINCIA DE HUANCANE - PUNO" - CONSTRUCCIN DE PAVIMENTO RIGIDO JR. INCLNMONTOS VALORIZADOS PROGRAMADOSMONTOS VALORIZADOS EJECUTADOSMONTOSPORCENTAJESMONTOSPORCENTAJESMESPARCIALACUMUL.PARCIALACUMUL.MESPARCIALACUMUL.PARCIALACUMUL.S/.S/.%%S/.S/.%%13-Jun-11000013-Jun-11000030-Jun-1130,818.3230,818.3214.58%14.58%30-Jun-1136,468.2836,468.2817.25%17.25%31-Jul-1187,923.73118,742.0541.60%56.18%31-Jul-1131-Aug-1192,634.68211,376.7343.82%100.00%31-Aug-11TOTAL211,376.73100.00%TOTAL36,468.2817.25%

% Prog-vs-Ejec

PROGRAMADOEJECUTADOPLAZO DE EJECUCION (MESES)AVANCE MENSUAL ACUMULADO (%)(Grfico N 01)AVANCES EN PORCENTAJES ACUMULADOS PROGRAMADO vs EJECUTADO