Kidurong Presentation 2
description
Transcript of Kidurong Presentation 2
PROJECT INTRODUCTION
Project Executor : Pengarah Kerja Raya Sarawak Superintending : Regional Manager, JKR Officer Northern Regional Office,
Miri Contractor : METROBRITE ENGINEERING
SDN. BHD. Project Commence- : 16th January 2015 ment Date Project Scheduled Completion : 15th October 2016 Contract Period : 21 months Contract Amount : RM 71, 618, 000.00
Scope of Works comprising of planning, preparation, construction and completion of the following :-
Road Construction Including site clearing, excavation and removal of unsuitable materials, cut and fill, imported suitable fill, spread and compact to the required formation level.Flexible Pavement Construction of proposed new carriageway including sub-base, road base and asphaltic concrete finishes, resurfacing existing carriageway, roundabout and junctions, crack sealing and patching works.Drainage Construction and completion of Reinforced Concrete Box and Pipe Culverts for extension of main road’s culverts), Surface Drainage facilities and associated ancillary works. Traffic Signal System Supply, install, testing and commissioning of Traffic Signal system.
SCOPE OF WORKS
Piling Works (Provisional) Comprising of installation of :-
200mm x 200mm RC Square Piles as foundation for RC Culverts 150mm x 150mm and 250mm x 250mm RC Square Piles as foundation for
piled embankment 355.6mm Micropiles for bridges foundation.
Road Furnitures Traffic Management Provision for full time traffic management team for the entire duration of the contract. Bridge Works Reinforced Concrete Works and other associated works for the construction and completion of :-
Sg. Similajau Bridge (B)- 90m length in 3 spans Sg. Similajau Bridge No. 3 (B) -45m length in 3 spans
Miscellaneous Works
SCOPE OF WORKS
Sylvester Rampai Ak Kudum
Tang Soon Huat Sepakat Geodrilling Freyssinet PSC Geospec Testing
Traffic Controller 1 Traffic Controller 2 Micropile Specialist
Post-Tensioning Works
Tester RC Piling Works
Hudson Ak Duncan Dundang
Ong Kah Ho Chan Yii Liang Voon Wen Hang Lau Kiiung Pew Wong Khing Boh
Supervisor for Traffic
Management Team
Supervisor for Emergency
Response Team
Drainage & Miscellaneous
Works
Bridge Works Supervisor
Road Works, Flexible Pavement & Road Furnitures
Traffic Signal System
Site Safety Supervisor
Traffic Management
Quantity SurveyorJenny Tiong Ching
ChingJohn Ha Tung Soon Chai Chang Kim
Project Engineer
Sh. Delaila Wan Abdillah
Lawrence Robert Tasser
NRM Environmental Consultant
Wong Ting KuiOswald Lau Puong
HoeJames Ha Tung Ing
Survey Development
Services
Safety Officer EMP/EMR Surveyor Site Manager QA/QC Engineer Contract Manager
Project ManagerIr. Wong Ting Yew
PROJECT TEAM
90 Days Critical Activities
1.Completion of site clearing and earthwork up to near 2 KM2.Completion of 6 culverts.3.Completion of bridge embankment pilings4.Completion of 15M precast beams production.
Contactor has submitted Insurance Policies cover notes prior to site possession date for:- Workmen’s Compensation (Cover Note No. : AK 96234) Contractor’s All Risk (Cover Note No. : AK96233)
Contractor to notify plantation owner of intention to commence work and to clear the area up to construction limit.
Notification to relevant authorities with regard to utilities relocation.
HIGHLIGHTED ISSUES