1
CALCULO MADERA PIES 2 BLOQUE CENTRAL CONTRATISTA: JULIAN LIMA L (m) h (m) AREA 3.1 0.8 3 7.4 m2 2.4 0.8 2 3.8 m2 1.8 0.6 1 1.1 m2 5 0.6 3 9.0 m2 3.5 0.5 6 10.5 m2 3.5 0.5 6 10.5 m2 10 0.5 5 25.0 m2 2.5 0.4 2 2.0 m2 5.5 0.4 16 35.2 m2 8.5 0.4 5 17.0 m2 121.6 M2 1,308.5 pies2

description

madera

Transcript of Madera Lima Pies2 BC 8 Sept

Page 1: Madera Lima Pies2 BC 8 Sept

CALCULO MADERA PIES 2BLOQUE CENTRALCONTRATISTA: JULIAN LIMA

L (m) h (m) N° AREA3.1 0.8 3 7.4 m22.4 0.8 2 3.8 m21.8 0.6 1 1.1 m25 0.6 3 9.0 m23.5 0.5 6 10.5 m23.5 0.5 6 10.5 m210 0.5 5 25.0 m22.5 0.4 2 2.0 m25.5 0.4 16 35.2 m28.5 0.4 5 17.0 m2

121.6 M21,308.5 pies2