METRADOS DE OBR
PROYECTO INSTALACION DEL SISTEMA DE AGUA POTABLE EN LA AA.VV LOS OLIVOS -
SUB PROY. :
UBICACIÓN : JUNIN - CHANCHAMAYO - JUNIN
PART. DESCRIPCION
01 OBRAS PROVISIONALES
01.01 ALMACEN Y GUARDIANIA
01.02 CARTEL DE IDENTIFICACION DE OBRA DE 1.80m x 3.60m
01.03 MOVILIZACION Y DESMOVILIZACION DE EUIPO
01.0! EUIPOS DE PROTECCION COLECTIVA
02 TRABA"OS PRELIMINARES
02.01 TRANUERAS DE MADERA 1.20 # 1.10 m PARA DESVIO TRANSITO VE$ICULAR
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
02.02 PUENTE DE MADERA P' ACCESO PEATONAL
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
02.03 TRAZO( NIVELACION Y REPLANTEO PRELIMINAR
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
02.0! TRAZO Y NIVELACION DURANTE EL PROCESO
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 2/10
METRADOS DE OBR
PROYECTO INSTALACION DEL SISTEMA DE AGUA POTABLE EN LA AA.VV LOS OLIVOS -
SUB PROY. :
UBICACIÓN : JUNIN - CHANCHAMAYO - JUNIN
PART. DESCRIPCION
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
03 MOVIMIENTO DE TIERRAS
03.01 E#CAVACION MANUAL DE ZAN"AS
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
03.02 REFINE Y NIVELACION DE FONDOS DE ZAN"A
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
03.03 ELIMINACION DE MATERIAL E#CEDENTE
03.03.01 ELIMINACION DE MATERIAL E#EDENTE DIST. PROM. ) *M
CALLE B 01
0! LINEA DE DISTRIBUCION +1631.31 ML,
!.01 CAMA DE APOYO PARA TUBERIAS
"R. NEMESIO NU%EZ PONCE
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 3/10
METRADOS DE OBR
PROYECTO INSTALACION DEL SISTEMA DE AGUA POTABLE EN LA AA.VV LOS OLIVOS -
SUB PROY. :
UBICACIÓN : JUNIN - CHANCHAMAYO - JUNIN
PART. DESCRIPCION
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
!.02 INSTALACION TUBERIA PVC CL 10 DE 3-
CALLE LOS OLIVOS
AV. CIRCUNVALACION
!.03 INSTALACION TUBERIA PVC CL 10 DE 1 12-
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
!.0! RELLENO CLASIFICADO
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
!.0) RELLENO CON MATERIAL PROPIO
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 4/10
METRADOS DE OBR
PROYECTO INSTALACION DEL SISTEMA DE AGUA POTABLE EN LA AA.VV LOS OLIVOS -
SUB PROY. :
UBICACIÓN : JUNIN - CHANCHAMAYO - JUNIN
PART. DESCRIPCION
CALLE LOS OLIVOS
AV. CIRCUNVALACION
!.06 PRUEBA $IDRAULICA TUB. A ZAN"A TAPADA
"R. NEMESIO NU%EZ PONCE
AV. 2& DE SETIEMBRE
"R. "OSE CARLOS MARIATEGUI
"R. EBEN EZER
AV. BELLO $ORIZONTE
"R. LA PAZ
"R. INDEPENDENCIA
CALLE LOS OLIVOS
AV. CIRCUNVALACION
!.0/ VALVULA DE COMPUERTA 3-
0).00 CONE#IONES DOMICILIARIAS +62 UND.,
).01 E#CAVACION MANUAL DE ZAN"AS
CONECCION 01 62
).02 CAMA DE APOYO PARA TUBERIAS
CONECCION 01 62
).03 INSTALACION TUBERIA PVC CL 10 DE 12-
CONECCION 01 62
).0! RELLENO CLASIFICADO
CONECCION 01 62
).0) RELLENO CON MATERIAL PROPIO
CONECCION 01 62
).06 CA"A DE REGISTRO DE AGUA 12- # 12-
).0/ ACCESORIOS
06 VARIOS
06.01 LIMPIEZA FINAL DE OBRA
06.02 PLACA RECORDATORIA
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 5/10
METRADOS DE OBR
PROYECTO INSTALACION DEL SISTEMA DE AGUA POTABLE EN LA AA.VV LOS OLIVOS -
SUB PROY. :
UBICACIÓN : JUNIN - CHANCHAMAYO - JUNIN
PART. DESCRIPCION
0/ FLETE TRASLADO DE MATERIALES
0/.01 TRANSPORTE DE MATERIALES
08 IMPACTO AMBIENTAL
08.01 MITIGACION AMBIENTAL
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 6/10
SANGANI - I ETAPA - DISTRITO DE PERENE - CHANCHAMAYO - JUNIN
FEC$A : MAYO 2013
UND CANT.D I M E N S I O N E S METRADO
LARGO ANCHO ALTO PARCIAL TOTAL
MES 3.0 3.00 3.00
UND 1.00 1.00 1.00
GLB 1.00 1.00 1.00
GLB 1.00 1.00 1.00
UND 18.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND30.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 2.00 2.00
UND 10.00 10.00
UND 6.00 6.00
M2 982.55
M2 1.0 6!.!3 0.60 38.66
M2 1.0 61.// 0.60 3/.06
M2 1.0 61.11 0.60 36.6/
M2 1.0 /0.0& 0.60 !2.0)
M2 1.0 )1.)6 0.60 30.&!
M2 1.0 )8.)3 0.60 3).12
M2 1.0 )/.33 0.60 3!.!0
M2 1.0 /20.10 0.60 !32.06
M2 1.0 !&2.66 0.60 2&).60
M2 982.55
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 7/10
SANGANI - I ETAPA - DISTRITO DE PERENE - CHANCHAMAYO - JUNIN
FEC$A : MAYO 2013
UND CANT.D I M E N S I O N E S METRADO
LARGO ANCHO ALTO PARCIAL TOTAL
M2 1.0 6!.!3 0.60 38.66
M2 1.0 61.// 0.60 3/.06
M2 1.0 61.11 0.60 36.6/
M2 1.0 /0.0& 0.60 !2.0)
M2 1.0 )1.)6 0.60 30.&!
M2 1.0 )8.)3 0.60 3).12
M2 1.0 )/.33 0.60 3!.!0
M2 1.0 /20.10 0.60 !32.06
M2 1.0 !&2.66 0.60 2&).60
M3 88.29
M3 1.0 6!.!3 0.60 0.&0 3!./&
M3 1.0 61.// 0.60 0.&0 33.36
M3 1.0 61.11 0.60 0.&0 33.00
M3 1.0 /0.0& 0.60 0.&0 3/.8)
M3 1.0 )1.)6 0.60 0.&0 2/.8!
M3 1.0 )8.)3 0.60 0.&0 31.61
M3 1.0 )/.33 0.60 0.&0 30.&6
M3 1.0 /20.10 0.60 0.&0 388.8)
M3 1.0 !&2.66 0.60 0.&0 266.0!
ML 1!31.31
ML 1.0 6).62 6).62
ML 1.0 63.26 63.26
ML 1.0 62.3) 62.3)
ML 1.0 /1.36 /1.36
ML 1.0 )3.02 )3.02
ML 1.0 )&.86 )&.86
ML 1.0 )8.61 )8.61
ML 1.0 /1).21 /1).21
ML 1.0 !82.02 !82.02
M3 38!.13
M3 1.3 V 2&/.02 386.13
ML 1!31.31
ML 1.0 6).62 6).62
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 8/10
SANGANI - I ETAPA - DISTRITO DE PERENE - CHANCHAMAYO - JUNIN
FEC$A : MAYO 2013
UND CANT.D I M E N S I O N E S METRADO
LARGO ANCHO ALTO PARCIAL TOTAL
ML 1.0 63.26 63.26
ML 1.0 62.3) 62.3)
ML 1.0 /1.36 /1.36
ML 1.0 )3.02 )3.02
ML 1.0 )&.86 )&.86
ML 1.0 )8.61 )8.61
ML 1.0 /1).21 /1).21
ML 1.0 !82.02 !82.02
ML 119".23
ML 1.0 /1).21 /1).21
ML 1.0 !82.02 !82.02
ML 3.08
ML 1.0 6).62 6).62
ML 1.0 63.26 63.26
ML 1.0 62.3) 62.3)
ML 1.0 /1.36 /1.36
ML 1.0 )3.02 )3.02
ML 1.0 )&.86 )&.86
ML 1.0 )8.61 )8.61
M3 293.!
M3 1.0 6).62 0.60 0.30 11.81
M3 1.0 63.26 0.60 0.30 11.3&
M3 1.0 62.3) 0.60 0.30 11.22
M3 1.0 /1.36 0.60 0.30 12.8!
M3 1.0 )3.02 0.60 0.30 &.)!
M3 1.0 )&.86 0.60 0.30 10.//
M3 1.0 )8.61 0.60 0.30 10.))
M3 1.0 /1).21 0.60 0.30 128./!
M3 1.0 !82.02 0.60 0.30 86./6
M3 58".2"
M3 1.0 6).62 0.60 0.60 23.62
M3 1.0 63.26 0.60 0.60 22.//
M3 1.0 62.3) 0.60 0.60 22.!)
M3 1.0 /1.36 0.60 0.60 2).6&
M3 1.0 )3.02 0.60 0.60 1&.0&
M3 1.0 )&.86 0.60 0.60 21.))
M3 1.0 )8.61 0.60 0.60 21.10
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 9/10
SANGANI - I ETAPA - DISTRITO DE PERENE - CHANCHAMAYO - JUNIN
FEC$A : MAYO 2013
UND CANT.D I M E N S I O N E S METRADO
LARGO ANCHO ALTO PARCIAL TOTAL
M3 1.0 /1).21 0.60 0.60 2)/.!8
M3 1.0 !82.02 0.60 0.60 1/3.)3
ML 1!31.31
ML 1.0 6).62 6).62
ML 1.0 63.26 63.26
ML 1.0 62.3) 62.3)
ML 1.0 /1.36 /1.36
ML 1.0 )3.02 )3.02
ML 1.0 )&.86 )&.86
ML 1.0 )8.61 )8.61
ML 1.0 /1).21 /1).21
ML 1.0 !82.02 !82.02
UND 3.0 3.00 3.00
M3 81.8
M3 62.0 2.20 0.60 1.00 81.8!
ML 13!.0
ML 62.0 2.20 136.!0
ML 13!.0
ML 62.0 2.20 136.!0
M3 2.55
M3 62.0 2.20 0.60 0.30 2!.))
M3 5".29
M3 62.0 2.20 0.60 0./0 )/.2&
UND 62.0 62.00 !2.00
UND 62.0 62.00 !2.00
GLB 1 1.00 1.00
UND 1 1.00 1.00
7/17/2019 Metrado Agua Potable Olivos (1)
http://slidepdf.com/reader/full/metrado-agua-potable-olivos-1 10/10
SANGANI - I ETAPA - DISTRITO DE PERENE - CHANCHAMAYO - JUNIN
FEC$A : MAYO 2013
UND CANT.D I M E N S I O N E S METRADO
LARGO ANCHO ALTO PARCIAL TOTAL
GLB 1 1.00 1.00
GLB 1 1.00 1.00