EPS SEDACUSCO S.A. EPS SEDACUSCO S.A. Gerencia de Ingeniería REPORTE FINANCIERO OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO” CUENTA CONTABLE: 339531 ITEM CONCEPTO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO 1 MANO DE OBRA 11,762.72 2 MATERIALES 372,045.69 3 EQUIPOS 0.00 4 SERVICIOS DIVERSOS 281.10 TOTAL 0.00 0.00 384,089.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PRESUPUESTO ANALITICO ITEM CONCEPTO APROBADO EJECUTADO SALDO 1 MANO DE OBRA 639,604.64 11,762.72 627,841.92 2 MATERIALES 869,629.84 372,045.69 497,584.15 3 EQUIPOS 13,000.00 0.00 13,000.00 4 SERVICIOS DIVERSOS - OTROS 19,071.23 281.10 18,790.13 TOTAL (SOLES) 1,541,305.71 384,089.51 1,157,216.20 TOTAL(%) 100.00% 24.92% 75.08% DESCRIPCION PRESUPUESTO AVANCE DEL MES AVANCE ACUMULADO SALDO POR EJECUTAR DE OBRA S/. % S/. % S/. % Avance Financiero Programado 1,541,305.71 400,000.00 25.95% 400,000.00 25.95% ### 74.05% Avance Financiero Ejecutado 1,541,305.71 384,089.51 24.92% 384,089.51 24.92% ### 75.08%

description

metrados ejecutados

Transcript of metrados ejecutados

Page 1: metrados ejecutados

EPS SEDACUSCO S.A.EPS SEDACUSCO S.A.

Gerencia de Ingeniería

REPORTE FINANCIERO

OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

CUENTA CONTABLE: 339531

ITEM CONCEPTO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO1 MANO DE OBRA 11,762.722 MATERIALES 372,045.693 EQUIPOS 0.004 SERVICIOS DIVERSOS 281.10

TOTAL 0.00 0.00 384,089.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

PRESUPUESTO ANALITICO

ITEM CONCEPTO APROBADO EJECUTADO SALDO1 MANO DE OBRA 639,604.64 11,762.72 627,841.922 MATERIALES 869,629.84 372,045.69 497,584.153 EQUIPOS 13,000.00 0.00 13,000.004 SERVICIOS DIVERSOS - OTROS 19,071.23 281.10 18,790.13

TOTAL (SOLES) 1,541,305.71 384,089.51 1,157,216.20

TOTAL(%) 100.00% 24.92% 75.08%

DESCRIPCIONPRESUPUESTO

AVANCE DEL MES AVANCE ACUMULADO SALDO POR EJECUTARDE OBRA S/. % S/. % S/. %

Avance Financiero Programado 1,541,305.71 400,000.00 25.95% 400,000.00 25.95% 1,141,305.71 74.05%Avance Financiero Ejecutado 1,541,305.71 384,089.51 24.92% 384,089.51 24.92% 1,157,216.20 75.08%

Page 2: metrados ejecutados

REPORTE FINANCIERO

AGOSTO TOTAL 11,762.72

372,045.690.00

281.100.00 384,089.51

Page 3: metrados ejecutados

Septiembre Octubre Noviembre Diciembre Enero Febrero0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

0 0 0 0 0 0

73,609 73,609 73,609 73,609 73,609 73,609

CONTROL DE AVANCEPROGRAMADO Vs. EJECUTADO

Avance Programado Avance Ejecutado

Meses

Mon

to

Page 4: metrados ejecutados

EPS SEDACUSCO S.A.EPS SEDACUSCO S.A.

Gerencia de Ingeniería

CONTROL DE AVANCE FISICOPROGRAMADO Vs. EJECUTADO

Mes

Avance Programado Avance Ejecutado Situación de la Obra

Mensual Acumulado Mensual Acumulado Adelanto Atraso

S/. S/. % S/. S/. % % %

Septiembre #NAME? #NAME? #NAME? 73,608.54 73,609 #NAME? #NAME? #NAME?Octubre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Noviembre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Diciembre #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Enero #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?Febrero #NAME? #NAME? #NAME? 73,609 #NAME? #NAME? #NAME?

Total #NAME? 73,609

DescripciónEn el Mes Acumulado Actual Saldo por Ejecutar

S/. % S/. % S/. %

Programado #NAME? #NAME? #NAME? #NAME? #NAME? #NAME?Ejecutado 73,609 #NAME? 73,609 #NAME? #NAME? #NAME?

A.R. (%)Valorización Acumulada Real

=73,609

= #NAME?Monto del Contrato de Obra #NAME?

A.P. (%)Valorización Acumulada Prog.

=#NAME?

= #NAME?Monto del Contrato de Obra #NAME?

(%)A.R. (%)

=#NAME?

= #NAME?A.P. (%) #NAME?

Page 5: metrados ejecutados

VALORIZACION EJECUTADA MENSUAL #NAME?

% AVANCE ACTUAL #NAME?

% AVANCE ACUMULADO #NAME?

VALORIZACION PROGRAMADA MENSUAL #REF!

% AVANCE PROGRAMADA MENSUAL #REF!

VALORIZACION EJECUTADA MENSUAL Err:509COMPLEM

VALORIZACION ACUMULADA Err:509

IMPORTE DE LA EJECUCION PRESUPUESTAL ACUMULADA S/. 0.00

IMPORTE DE LA EJECUCION PRESUPUESTAL MENSUAL S/. 0.00

Page 6: metrados ejecutados

#NAME?

M1 #NAME?M2 #NAME?M3 #NAME?M4 #NAME?M5 #NAME?M6 #NAME?

#NAME?

Page 7: metrados ejecutados

0.050897004 0.18916146 2863318.12#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME? #NAME? #NAME? #NAME?#NAME? #NAME? #NAME?

Page 8: metrados ejecutados

2863318.12#NAME?#NAME?#NAME?#NAME?#NAME?#NAME?#NAME?

Page 9: metrados ejecutados

PRESUPUESTO VALORIZADO

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

#NAME? #NAME? #NAME?

Page 10: metrados ejecutados

RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA

MES DICIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC

FECHA DE PRESENTACIÓN:

ITEM VALORIZACION

PRESUPUESTOAVANCES

ANTERIOR ACTUAL

S/.% % %

1 PROGRAMADO 102,944.52 - 0.00% 71,580.77 69.53% 71,580.77 69.53%

2 MAYOR METRADOS 2,027.77 - 0.00% 2,027.77 1.97% 2,027.77 1.97%

COSTOS TOTAL 102,944.52 - 0.00% 73,608.54 71.50% 73,608.54 71.50%

ACUMULADO Valorizado

S/.Valorizado

S/.Valorizado

S/.

Page 11: metrados ejecutados

RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA

: SAN SEBASTIANA.P.V. TRABAJADORES DE CORPAC

12/1/2013

SALDO

%

31,363.77 30.47%

- 0.00%

31,363.77 30.47%

ValorizadoS/.

Page 12: metrados ejecutados

PARTIDAS EJECUTADAS EN ELPROYECTO

Se ha realizado la ejecucion de obra, según el Expediente Tecnico Aprobado, habiendoce ejecutado las siguientes partidas

PARTIDA DESCRIPCION DE LA PARTIDA UNIDAD METRADO

01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA

01.01.00 Construccion de Oficina, Almacen y Guardiania M2 0.00los beneficiaios proporcionaron ambientes tanto para la residencia y almacen de obra

01.02.00 Energia Electrica Provisional GLB 1.00se tuvo que pagar a los beneficiarios por la energia electrica temporal

01.03.00 Puentes Peatonales de Madera UND 0.00partida no ejecutada

01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 0.00partida no ejecutada

01.05.00 Cartel de Identificacion de Obra UND 0.00partida no ejecutada

01.06.00 Limpieza de Obra M2 1,383.26esta partida se ejecuto mediante faenas de los pobladores del APV Corpac Cusco

01.07.00 Cinta de seguridad M 0.00partida no ejecutada

02.00.00 TRABAJOS PRELIMINARES

02.01.00 Limpieza de Terreno Manual M2 1,383.26esta partida se ejecuto mediante faenas de los pobladores del APV Corpac Cusco

03.00.00 REDES DE DISTRIBUCION

03.01.00 TRABAJOS PRELIMINARES

03.01.01 Trazo Nivelacion y Replanteo M2 549.41

03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51

se realizo el control permanente y minucioso del alineamiento, a fin de evitar modificaciones en el eje de la tuberia instalada

03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 398.00

03.02.02 Perfilado de zanjas M 959.75

03.02.03 Cama de apoyo para tuberias E=0.10m M3 57.58

03.02.04 Relleno y compactado con material propio M3 233.27

03.02.05 Eliminacion y acarreo de material exedente M3 114.46

03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00se utilizo maderamen adquirido con recursos propios (tablas y listones)

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 959.75

03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS

03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00

se utilizo esta valvula de purga al final de la tuberia instalada, en la parte mas baja de la red

03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 2.00

03.05.02 Desinfeccion en tuberias M 915.69

una vez realizada la prueba hidraulica se procdio con la desinfeccion de la tuberia para su posterior puesta en marcha

03.06.00 VARIOS

03.06.01 Reposicion de conexiones de agua UND 0.00partida no ejecutada

03.06.02 Demolicion y reposicion de pavimento M2 0.00partida no ejecutada

03.06.03 Puesta en operación del sistema de agua GLB 1.00

NOTA:

se ubico en el terreno l eje de la red de distribucion, habiendoce ubicado ademas el are de empalme, valvulas de compuerta y demas detalles que aparecen en los planos, luego se procedio al trazo del ancho de la zanja con yeso, según lo que indica en los planos de planta

se realizo el corte de la zanja a mano a fin de evitar daños en las instalaciones existentes habiendoce realizado entibaciones para evitar derrumbe de las zanjas excavadas, en tramos donde no existia instalaciones se utilizo maquinaria pesada (retroexcavadora) para aperturar la zanja.

una vez realizada el refine de fondo de la zanja, se utilizo material granular ( piedra chancada de 1/2") como cama de apoyo para la tuberia instalada

se procedio a la selección del terreno, que se utilizo como primer relleno, habiendoce ejecutado este en capas de 15 cm de altura realizandoce la compactacion manual hasta una altura de 60 cm, luego se procedio a realizar el segundo relleno habiendoce utilizado apisonadores tipo pison (compactador canguro)

se elimino una parte del material exedente con maquinaria alquilada, el restante se procedio con apoyo de la municipalidad Distrital de San Sebastian

se utilizo tuberia de PVC con union flexible clase 10 de 90 mm de diametro según norma de fabricacion ISO 4422, con anillo elastomerico, según lo especificado en el expediente tecnico aprobado, habiendoce puesto especial cuidado en el transporte manipuleo evitando ser golpeado y/o arrastrado, el almacenamiento se ralizo en un lugar alquilado bajo techo y ventilcion natural.

las valvulas usadas son de tipo compuerta HD ISO 7259 de 90 mm de diametro según especificado en el expediente tecnico aprobado

para la ejecucion de la prueba hidraulica, se procedio a instalar el balde de prueba con el manometro en el extremo mas bajo del tramo de prueba, una vez taponado los extremos del tramo sometido a la prueba, se realizo el llenado de la red con agua , luego se procedio con el bombeo a travez del valde de prueba en las presiones de 50, 80, 100, 150 psi, se purgo el aire atrapado en la red , luego de llegar a la presion de prueba (1.5 veces la presion de trabajo), se procedio a comprobar la impermeabilidad del tramo observando las posibles variaciones en el manometro durante 1 hora de prueba, lo cual no se tuvo variaciones y se procedio a dar el visto buebo por parte del supervisor y su posterior firmado de los protocolos de calidad.

luego de ejecutar la instalacion de las diferentes tuberias, accesorios y valvulas con la aprobacion de la supervision de obra, se procedio a la puesta de operación del sistema

EL PROYECTISTA EN LA PARTIDA DE EXCAVACION DE ZANJAS PARA LA INSTALACION DE LA TUBERIA CONCIDERA LA UNIDAD EN METROS CUBICOS Y NO EN METROS LINEALES.

Page 13: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

PRINCIPAL

MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC

FECHA DE PRESENTACIÓN:

PARTIDA DESCRIPCION UNIDAD

PRESUPUESTO PROGRAMADO AVANCESSALDO

METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO

S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA

01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 81.85 4,092.50 4092.5 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 50.00 01.02.00 Energia Electrica Provisional GLB 1.00 500.00 500.00 500.00 0.00 - 0.00% 1.00 500.00 100.00% 1.00 500.00 100.00% - 01.03.00 Puentes Peatonales de Madera UND 20.00 19.47 389.40 389.4 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 20.00 01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 29.37 234.96 234.96 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 8.00 01.05.00 Cartel de Identificacion de Obra UND 1.00 593.93 593.93 593.93 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 1.00 01.06.00 Limpieza de Obra M2 1,383.26 0.95 1,314.10 1,314.10 0.00 - 0.00% 1,383.26 1,314.10 100.00% 1,383.26 1,314.10 100.00% - 01.07.00 Cinta de seguridad M 1,831.38 0.50 915.69 915.69 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 1,831.38

02.00.00 TRABAJOS PRELIMINARES

02.01.00 Limpieza de Terreno Manual M2 1,383.26 0.95 1,314.10 1,314.10 - 0.00% 1,383.26 1,314.10 100.00% 1,383.26 1,314.10 100.00% -

03.00.00 REDES DE DISTRIBUCION

03.01.00 TRABAJOS PRELIMINARES

03.01.01 Trazo Nivelacion y Replanteo M2 549.41 1.35 741.70 741.70 0.00 - 0.00% 549.41 741.70 100.00% 549.41 741.70 100.00% - 03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51 1.07 587.98 587.98 0.00 - 0.00% 549.51 587.98 100.00% 549.51 587.98 100.00% -

03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 366.28 21.68 7,940.95 7,940.95 0.00 - 0.00% 366.28 7,940.95 100.00% 366.28 7,940.95 100.00% - 03.02.02 Perfilado de zanjas M 915.69 0.63 576.88 576.88 0.00 - 0.00% 915.69 576.88 100.00% 915.69 576.88 100.00% - 03.02.03 Cama de apoyo para tuberias E=0.10m M3 54.94 59.00 3,241.46 3,241.46 - 0.00% 54.94 3,241.46 100.00% 54.94 3,241.46 100.00% - 03.02.04 Relleno y compactado con material propio M3 219.77 18.07 3,971.24 3,971.24 0.00 - 0.00% 219.77 3,971.24 100.00% 219.77 3,971.24 100.00% - 03.02.05 Eliminacion y acarreo de material exedente M3 114.46 14.51 1,660.81 1,660.81 0.00 - 0.00% 114.46 1,660.81 100.00% 114.46 1,660.81 100.00% - 03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00 17.02 1,531.80 1,531.80 0.00 - 0.00% 90.00 1,531.80 100.00% 90.00 1,531.80 100.00% -

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 915.69 10.48 9,596.43 9,596.43 0.00 - 0.00% 915.69 9,596.43 100.00% 915.69 9,596.43 100.00% -

03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00 843.99 843.99 843.99 0.00 - 0.00% 1.00 843.99 100.00% 1.00 843.99 100.00% - 03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00 674.59 1,349.18 1,349.18 - 0.00% 2.00 1,349.18 100.00% 2.00 1,349.18 100.00% -

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 1.00 450.59 450.59 450.59 0.00 - 0.00% 1.00 450.59 100.00% 1.00 450.59 100.00% - 03.05.02 Desinfeccion en tuberias M 915.69 0.16 146.51 146.51 0.00 - 0.00% 915.69 146.51 100.00% 915.69 146.51 100.00% -

03.06.00 VARIOS

03.06.01 Reposicion de conexiones de agua UND 21.00 221.12 4,643.52 4,643.52 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 21.00 03.06.02 Demolicion y reposicion de pavimento M2 50.00 98.47 4,923.50 4,923.50 0.00 - 0.00% 0.00 0.00 0.00% - - 0.00% 50.00 03.06.03 Puesta en operación del sistema de agua GLB 1.00 277.40 277.40 277.40 - 0.00% 1.00 277.40 100.00% 1.00 277.40 100.00% -

COSTO DIRECTO 51,838.62 0.0 0.00% 36,045.1 69.53% 36,045.1 69.53%0.6829368 GASTOS GENERALES 68.29 % 35,402.50 0.00 24,616.54 24,616.54

0.18 IMPUESTO IGV 18% 15,703.40 0.00 10,919.10 10,919.10PRESUPUESTO TOTAL 102,944.52 0.0 0.00% 71,580.77 69.53% 71,580.77 69.53%

Page 14: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

ADICIONALES - POR MAYORES METRADOS

MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 11/19/2013 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 60 DIAS DISTRITO : SAN SEBASTIANFECHA DE TERMINO 1/18/2014 LOCALIDAD A.P.V. TRABAJADORES DE CORPAC

FECHA DE PRESENTACIÓN:

PARTIDA DESCRIPCION UNIDAD

PRESUPUESTO PROGRAMADO AVANCESSALDO

METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO

S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 31.72 21.68 687.75 687.75 0.00 - 0.00% 31.72 687.75 100.00% 31.72 687.75 100.00% -

03.02.02 Perfilado de zanjas M 44.06 0.63 27.76 27.76 0.00 - 0.00% 44.06 27.76 100.00% 44.06 27.76 100.00% -

03.02.03 Cama de apoyo para tuberias E=0.10m M3 2.64 59.00 155.97 155.97 0.00 - 0.00% 2.64 155.97 100.00% 2.64 155.97 100.00% -

03.02.04 Relleno y compactado con material propio M3 13.50 18.07 243.95 243.95 0.00 - 0.00% 13.50 243.95 100.00% 13.50 243.95 100.00% -

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 44.06 10.48 461.75 461.75 0.00 - 0.00% 44.06 461.75 100.00% 44.06 461.75 100.00% -

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 1.00 450.59 450.59 450.59 0.00 - 0.00% 1.00 450.59 100.00% 1.00 450.59 100.00% -

COSTO DIRECTO 2,027.77 0.00 0.00% 2,027.77 100.00% 2,027.77 100.00%

Page 15: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

ADICIONALES - POR NUEVAS PARTIDAS

MES NOVIEMBRE 2013OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

MONTO DE OBRA S/. 102,944.52 REGION : CUSCOMONTO ASIGNADO S/. 102,944.52 DEPARTAMENTO : CUSCOFECHA DE INICIO DE OBRA 10/1/2012 PROVINCIA : CUSCOPLAZO DE EJECUCIÓN 210 DIAS DISTRITO : CUSCOFECHA DE TERMINO 4/28/2013 LOCALIDAD : SANTA ANA - JARDINES DEL INCA

FECHA DE PRESENTACIÓN:

PARTIDA DESCRIPCION UNIDAD

PRESUPUESTO PROGRAMADO AVANCESSALDO

METRADOP. UNIT. PRESUP. P. TOTAL ANTERIOR ACTUAL ACUMULADO

S/. S/. S/. Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado Valorizado S/. % Metrado

0.00 - 0.00 0.00 - - -

COSTO DIRECTO 0.00 0.00 0.00 0.00

Page 16: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

PRINCIPAL

4/21/2023

SALDO

Valorizado S/. %

4,092.50 100.00% - 0.00% 389.40 100.00% 234.96 100.00% 593.93 100.00% - 0.00% 915.69 100.00%

- 0.00%

- 0.00% - 0.00%

- 0.00% - 0.00% - 0.00% - 0.00% - 0.00% - 0.00%

- 0.00%

- 0.00% - 0.00%

- 0.00% - 0.00%

4,643.52 100.00% 4,923.50 100.00% - 0.00%

15,793.50 30.47%10,785.964,784.3031,363.77 30.47%

Page 17: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

ADICIONALES - POR MAYORES METRADOS

4/21/2023

SALDO

Valorizado S/. %

- 0.00%

- 0.00%

- 0.00%

- 0.00%

- 0.00%

- 0.00%

0.00 0.00%

Page 18: metrados ejecutados

VALORIZACION DE AVANCE DE OBRA

ADICIONALES - POR NUEVAS PARTIDAS

4/21/2023

SALDO

Valorizado S/. %

-

0.00

Page 19: metrados ejecutados

VALORIZACION DEDUCTIVOSMES DICIEMBRE 2013

OBRA “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

PARTIDA DESCRIPCION

PRESUPUESTO

UNIDAD METRADOP. UNIT.

S/.01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA

01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 81.85 01.03.00 Puentes Peatonales de Madera UND 20.00 19.47 01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 29.37 01.05.00 Cartel de Identificacion de Obra UND 1.00 593.93 01.07.00 Cinta de seguridad M 1,831.38 0.50

03.06.00 VARIOS

03.06.01 Reposicion de conexiones de agua UND 21.00 221.12 03.06.02 Demolicion y reposicion de pavimento M2 50.00 98.47

COSTO DIRECTO

0.6829368 GASTOS GENERALES 68.29 %

0.18 IMPUESTO IGV 18%PRESUPUESTO TOTAL

Page 20: metrados ejecutados

VALORIZACION DEDUCTIVOS

“CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

PRESUPUESTO

P. TOTAL

S/.

4092.5389.4234.96593.93915.69

4,643.524,923.50

15,793.5010,785.964,784.3031,363.77

Page 21: metrados ejecutados

PLANILLA DE METRADOS OBRA PRINCIPAL

PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOM M J V S D L M M J V S

19 20 21 22 23 24 25 26 27 28 29 30 TOTAL

01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA

01.01.00 Construccion de Oficina, Almacen y Guardiania M2 50.00 0.00 0.00 0.00 0.0001.02.00 Energia Electrica Provisional GLB 1.00 1 1.00 0.00 1.00 1.0001.03.00 Puentes Peatonales de Madera UND 20.00 0.00 0.00 0.00 0.0001.04.00 Tranqueras de Madera Para Desvio Vehicular UND 8.00 0.00 0.00 0.00 0.0001.05.00 Cartel de Identificacion de Obra UND 1.00 0.00 0.00 0.00 0.0001.06.00 Limpieza de Obra M2 1,383.26 725.4 657.86 1,383.26 0.00 1383.26 1383.2601.07.00 Cinta de seguridad M 1,831.38 0.00 0.00 0.00 0.00

02.00.00 TRABAJOS PRELIMINARES

02.01.00 Limpieza de Terreno Manual M2 1383.26 420 380 405 178.26 1,383.26 0.00 1383.26 1383.26

03.00.00 REDES DE DISTRIBUCION

03.01.00 TRABAJOS PRELIMINARES

03.01.01 Trazo Nivelacion y Replanteo M2 549.41 120 80 180 169.41 549.41 0.00 549.41 549.4103.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 549.51 220 180 149.51 549.51 0.00 549.51 549.51

03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 366.28 80.5 70.8 88.5 66.5 59.98 366.28 0.00 366.28 366.2803.02.02 Perfilado de zanjas M 915.69 220 280 180 130 105.69 915.69 0.00 915.69 915.6903.02.03 Cama de apoyo para tuberias E=0.10m M3 54.94 11 10.5 12 11.44 10 54.94 0.00 54.94 54.9403.02.04 Relleno y compactado con material propio M3 219.77 44.5 43.5 46 43 42.77 219.77 0.00 219.77 219.7703.02.05 Eliminacion y acarreo de material exedente M3 114.46 30 15 45 24.46 114.46 0.00 114.46 114.4603.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 90.00 28 25 26 11 90.00 0.00 90.00 90.00

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 915.69 220 195 210 150.5 140.19 915.69 0.00 915.69 915.69

03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS

03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 1.00 1 1.00 0.00 1.00 1.0003.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 2.00 1 1 2.00 0.00 2.00 2.00

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 1.00 1 1.00 0.00 1.00 1.0003.05.02 Desinfeccion en tuberias M 915.69 915.69 915.69 0.00 915.69 915.69

03.06.00 VARIOS

03.06.01 Reposicion de conexiones de agua UND 21.00 0.00 0.00 0.00 0.0003.06.02 Demolicion y reposicion de pavimento M2 50.00 0.00 0.00 0.00 0.0003.06.03 Puesta en operación del sistema de agua GLB 1.00 1 1.00 0.00 1.00 1.00

Page 22: metrados ejecutados

PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS

PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOM M J V S D L M M J V S

19 20 21 22 23 24 25 26 27 28 29 30 TOTAL

03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 31.72 31.723 31.72 0.00 31.72 31.7203.02.02 Perfilado de zanjas M 44.06 44.06 44.06 0.00 44.06 44.0603.02.03 Cama de apoyo para tuberias E=0.10m M3 2.64 2.6436 2.64 0.00 2.64 2.6403.02.04 Relleno y compactado con material propio M3 13.50 13.5 13.50 0.00 13.50 13.50

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 44.06 44.06 44.06 0.00 44.06 44.06

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 1.00 1 1.00 0.00 1.00 1.00

Page 23: metrados ejecutados

PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS NUEVAS PARTIDAS

PROYECTO: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

ITEM DESCRIPCION UND METRADO ANTERIOR ACTUAL ACUMULADOL M M J V S D L M M J V

12 13 14 15 16 17 18 19 20 21 22 23 TOTAL

0.00 0.00 0.00 0.00

Page 24: metrados ejecutados

PLANILLA DE METRADOS OBRA PRINCIPAL

SALDO

CANT %

50.00 100.00%0.00 0.00%

20.00 100.00%8.00 100.00%1.00 100.00%0.00 0.00%

1831.38 100.00%

0.00 0.00%

0.00 0.00%0.00 0.00%

0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%

0.00 0.00%

0.00 0.00%0.00 0.00%

0.00 0.00%0.00 0.00%

21.00 100.00%50.00 100.00%0.00 0.00%

Page 25: metrados ejecutados

PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS

SALDO

CANT %

0.00 0.00%0.00 0.00%0.00 0.00%0.00 0.00%

0.00 0.00%

0.00 0.00%

Page 26: metrados ejecutados

PLANILLA DE METRADOSPARTIDAS ADICIONALES - POR MAYORES METRADOS NUEVAS PARTIDAS

SALDO

CANT %

0.00

Page 27: metrados ejecutados

METAS DE AVANCE DE OBRA

PARTIDA DESCRIPCION UNIDAD ACTUAL ACUMULADO

% %01.00.00 OBRAS PROVISIONALES SISTEMA DE AGUA

01.01.00 Construccion de Oficina, Almacen y Guardiania M2 0.00% 0.00%01.02.00 Energia Electrica Provisional GLB 100.00% 100.00%01.03.00 Puentes Peatonales de Madera UND 0.00% 0.00%01.04.00 Tranqueras de Madera Para Desvio Vehicular UND 0.00% 0.00%01.05.00 Cartel de Identificacion de Obra UND 0.00% 0.00%01.06.00 Limpieza de Obra M2 100.00% 100.00%01.07.00 Cinta de seguridad M 0.00% 0.00%

02.00.00 TRABAJOS PRELIMINARES

02.01.00 Limpieza de Terreno Manual M2 100.00% 100.00%

03.00.00 REDES DE DISTRIBUCION

03.01.00 TRABAJOS PRELIMINARES

03.01.01 Trazo Nivelacion y Replanteo M2 100.00% 100.00%03.01.02 Trazo Nivelacion y Replanteo Durante el Proceso M2 100.00% 100.00%

03.02.00 MOVIMIENTO DE TIERRAS

03.02.01 Excavacion de Zanjas para Tuberia PVC (C-10) 90mm M3 100.00% 100.00%03.02.02 Perfilado de zanjas M 100.00% 100.00%03.02.03 Cama de apoyo para tuberias E=0.10m M3 100.00% 100.00%03.02.04 Relleno y compactado con material propio M3 100.00% 100.00%03.02.05 Eliminacion y acarreo de material exedente M3 100.00% 100.00%03.02.06 Entibado y apuntalamiento de zanjas H>2.5m M 100.00% 100.00%

03.03.00 TUBERIAS

03.03.01 PVC NTP ISO 4422 SERIE 20 (C-10) 90mm M 100.00% 100.00%

03.04.00 SUMINISTRO Y COLOCACION DE ACCESORIOS Y VALVULAS

03.04.01 Suministro y colocacion de valvula de purga 90mm en red de distribucion PZA 100.00% 100.00%03.04.02 Suministro y colocacion de valvula de compuerta de 90mm en red de distribucion PZA 100.00% 100.00%

03.05.00 PRUEBA HIDRAULICA

03.05.01 Prueba hidraulica en tuberias GLB 100.00% 100.00%03.05.02 Desinfeccion en tuberias M 100.00% 100.00%

03.06.00 VARIOS

03.06.01 Reposicion de conexiones de agua UND 0.00% 0.00%03.06.02 Demolicion y reposicion de pavimento M2 0.00% 0.00%03.06.03 Puesta en operación del sistema de agua GLB 100.00% 100.00%

Page 28: metrados ejecutados

METAS DE AVANCE DE OBRA

SALDO

%

100.00%0.00%

100.00%100.00%100.00%0.00%

100.00%

0.00%

0.00%0.00%

0.00%0.00%0.00%0.00%0.00%0.00%

0.00%

0.00%0.00%

0.00%0.00%

100.00%100.00%0.00%

Page 29: metrados ejecutados

RESUMEN DE EJECUCION PRESUPUESTAL

OBRA : “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”F. DE FINANCIAMIENTO : RECURSOS PROPIOS

Nº TIPO DE DOCUMNETO NUMERO DESCRIPCION

COMPRAS1 B/V 36632 COMPRA DE TUBERIA Y ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 9306.152 B/V 4941 MATERIAL DE FILTRO (CONFITILLO) 250.003 B/V 17012 LUBRICANTE PARA TUBERIA 38.004 PROFORMA 1 CORDEL NYLON 11.005 B/V 4390 SOGA DRIZA 40.006 GASOHOL 44.007 B/V 4950 MATERIAL DE FILTRO (CONFITILLO) 150.008 B/V 4524 BOTAS DE JEBE 36.009 B/V 1239 MATERIAL DE FILTRO (CONFITILLO) 550.00

10 B/V 481 MATERIAL DE FILTRO (CONFITILLO) 250.0011 NOTA PEDIDO 1072 MADERAMEN PARA ENTIBADOS 131.0012 B/V 4399 VARIOS 9.00

B/V MATERIAL DE FILTRO (PIEDRA CHANCADA DE 1/2") 975.0013 B/V 225 GRASA Nº3 VISTONY 20.0014 B/V 1240 VARIOS 18.0015 B/V 483 MATERIAL DE FILTRO (CONFITILLO) 250.0016 B/V 10282 LLAVE CHECK 30.0017 B/V 10281 BOTAS DE JEBE 22.0018 B/V 10286 CEMENTO 24.0019 GASOHOL 50.0020 B/V 9189 VARIOS 56.0021 B/V 1308 MATERIAL DE FILTRO (CONFITILLO) 275.0022 B/V 1028 MANGUERA DE 3/4" 36.0023 B/V 36746 COMPRA DE TUBERIA Y ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 4907.3024 B/V 36745 ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 160.0025 B/V 1311 MATERIAL DE FILTRO (CONFITILLO) 275.0026 B/V 1310 MATERIAL DE FILTRO (CONFITILLO) 275.0027 B/V 1309 MATERIAL DE FILTRO (CONFITILLO) 110.0028 B/V CINTA TEFLON 1.5029 B/V 36878 UNION DE REPARACION 20.0030 B/V 36883 ACCESORIOS PARA LA INSTALACION DE AGUA POTABLE 99.5031 B/V 492 MATERIAL DE FILTRO (CONFITILLO) Y CEMENTO 104.0032 B/V 10316 VARIOS (ALQUILER DE LOCALES PARA ALMACENES ENTRE OTROS) 4254.5033 B/V 10339 WINCHA DE 50 MTS 22.00

SUB TOTAL 22799.95

CARGA DE PERSONAL1 NINGUNA MOVILIDAD (PASAJES) 49.002 NINGUNA LEVANTAMIENTO DE OBSERVACIONES EXPEDIENTE TECNICO 3000.003 NINGUNA SERVICIOS DE MANO DE OBRA 1000.004 NINGUNA SERVICIOS DE MANO DE OBRA 700.005 NINGUNA COSTO POR MANO DE OBRA EN LAS FAENAS 26400.006 NINGUNA SERVICIOS DE MANO DE OBRA 1700.00

SUB TOTAL 32849.00

SERVICIO POR TERCEROS1 NOTA DE ENTREGA 81 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 550.002 NOTA DE ENTREGA 82 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 600.003 NOTA DE ENTREGA 83 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 700.004 NOTA DE ENTREGA 85 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 1100.005 NOTA DE ENTREGA 86 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 700.006 NOTA DE ENTREGA 87 ALQUILER DE MAQUINARIA PESADA PARA EXCAVACION DE ZANJA (RETROEXCAVADORA) 1070.007 ELIMINACION DE MATERIAL EXEDENTE CON MAQUINARIA ALQUILADA 2135.828 TARBAJOS DE TOPOGRAFIA 2000.009 B/V 3 ALQUILER DE MAQUINARIA LIVIANA 660.00

SUB TOTAL 9515.82

TOTAL

IMPORTE PARCIAL

Page 30: metrados ejecutados

RESUMEN DE EJECUCION PRESUPUESTAL

: “CONSTRUCCION DEL SISTEMA DE AGUA POTABLE APV. TRABAJADORES CORPAC - CUSCO”

TOTAL

22799.95

32849.00

9515.82

65164.77