PRESUPUESTO GENERAL ACTIVIDAD UNIDAD CANTIDAD PRECIO UNITARIO (Bs) PRECIO PARCIAL (Bs) 1 TRAZADO Y REPLANTEO m 2 688.53 8.26 5688.83 2 EXCAVACIÓN 0-1.5 M SUELO SEMIDURO m 3 94.46 31.05 2932.43 3 HORMIGON ARMADO ZAPATAS m 3 22.04 2348.25 51755.50 4 RELLENO Y COMPACTADO m 3 15.00 34.28 514.26 5 SOBRECIMIENTOS DE HºAº m 3 19.20 2337.77 44885.19 6 IMPERMEABILIZACION DE SOBRECIMIENTOS m 2 48.00 42.31 2030.72 7 HORMIGON ARMADO COLUMNAS m 3 15.52 3816.62 59233.99 8 HORMIGON ARMADO VIGAS m 3 29.25 3641.23 106516.8 5 9 MURO DE LADRILLO 6H E=0,18 CM m 2 886.33 165.50 146691.0 7 10 HORMIGON ARMADO LOSA MACIZA m 2 25.77 4089.34 105382.4 1 11 ESCALERAS DE HORMIGON ARMADO m 3 6.04 4109.02 24818.47 12 CUB. DE CALAMINA GALV. Nº28 C/ESTR.METALICA m 2 467.00 1951.23 911224.3 2 13 CIELO RASO BAJO LOSA m 2 191.20 89.01 17018.67 14 CIELO FALSO DE PVC (ESTR. METALICA) m 2 467.00 116.16 54246.72 15 PUNTO TELEFONO pto 1.00 54.97 54.97 16 PROV. Y COLOC. DE ILUMINACIÓN pza 48.00 199.76 9588.44 17 TOMACORRIENTE punt o 22.00 217.23 4779.15 18 PROV. Y COLOC. TABLERO DE DISTRIBUCIÓN pza 1.00 743.91 743.91 19 TUBERIA DE AGUA DE 1/2 ml 78.60 35.27 2772.13 20 PROV. Y TENDIDO TUBERIA PVC 4" ml 51.60 72.69 3750.92 21 PROV. Y TENDIDO TUBERIA PVC 2" ml 3.60 57.63 207.47 22 PROV. Y COLOC. DE INODORO pza 2.00 402.48 804.95 23 PROV. Y COLOC. DE LAVAMANOS pza 2.00 732.41 1464.82 24 CONTRAPISO DE PIEDRA Y CEMENTO m 2 387.85 104.82 40652.76 25 REVOQUE CAL-CEMENTO SOBRE LADRILLO m 2 675.09 97.28 65671.38 26 REVOQUE INTERIOR CAL-CEMENTO-YESO m 2 673.33 103.98 70010.97 27 REVESTIMINETO DE PARED DE BAÑOS m 2 15.30 178.30 2728.04 28 REJILLA METALICA PARA SUMIDERO m 2 0.50 227.38 113.69 29 PISO CERAMICO ESMALTADO m 2 538.56 176.80 95220.21 30 ZOCALO DE CERAMICA ESMALTADA ml 161.00 90.24 14527.97 31 MESON DE HºAº m 2 1.60 575.27 920.43

description

presupuesto

Transcript of Presupuesto General Viernes

PRESUPUESTO GENERAL

NACTIVIDADUNIDADCANTIDADPRECIO UNITARIO (Bs)PRECIO PARCIAL (Bs)

1TRAZADO Y REPLANTEO m2688.538.265688.83

2EXCAVACIN 0-1.5 M SUELO SEMIDURO m394.4631.052932.43

3HORMIGON ARMADO ZAPATAS m322.042348.2551755.50

4RELLENO Y COMPACTADO m315.0034.28514.26

5SOBRECIMIENTOS DE HA m319.202337.7744885.19

6IMPERMEABILIZACION DE SOBRECIMIENTOS m248.0042.312030.72

7HORMIGON ARMADO COLUMNAS m315.523816.6259233.99

8HORMIGON ARMADO VIGAS m329.253641.23106516.85

9MURO DE LADRILLO 6H E=0,18 CM m2886.33165.50146691.07

10HORMIGON ARMADO LOSA MACIZAm225.774089.34105382.41

11ESCALERAS DE HORMIGON ARMADO m36.044109.0224818.47

12CUB. DE CALAMINA GALV. N28 C/ESTR.METALICAm2467.001951.23911224.32

13CIELO RASO BAJO LOSA m2191.2089.0117018.67

14CIELO FALSO DE PVC (ESTR. METALICA) m2467.00116.1654246.72

15PUNTO TELEFONOpto1.0054.9754.97

16PROV. Y COLOC. DE ILUMINACIN pza48.00199.769588.44

17TOMACORRIENTE punto22.00217.234779.15

18PROV. Y COLOC. TABLERO DE DISTRIBUCINpza1.00743.91743.91

19TUBERIA DE AGUA DE 1/2ml78.6035.272772.13

20PROV. Y TENDIDO TUBERIA PVC 4"ml51.6072.693750.92

21PROV. Y TENDIDO TUBERIA PVC 2"ml3.6057.63207.47

22PROV. Y COLOC. DE INODOROpza2.00402.48804.95

23PROV. Y COLOC. DE LAVAMANOS pza2.00732.411464.82

24CONTRAPISO DE PIEDRA Y CEMENTOm2387.85104.8240652.76

25REVOQUE CAL-CEMENTO SOBRE LADRILLO m2675.0997.2865671.38

26REVOQUE INTERIOR CAL-CEMENTO-YESO m2673.33103.9870010.97

27REVESTIMINETO DE PARED DE BAOS m215.30178.302728.04

28REJILLA METALICA PARA SUMIDEROm20.50227.38113.69

29PISO CERAMICO ESMALTADOm2538.56176.8095220.21

30ZOCALO DE CERAMICA ESMALTADAml161.0090.2414527.97

31MESON DE HAm21.60575.27920.43

32PROV. Y COLOC. PUERTA TABLERO m223.741030.5824465.89

33PROV. Y COLOC. VENTANA DE ALUMINIOm2173.64496.6886243.47

34QUINCALLERIA DE PUERTASpza12.00933.8811206.56

35PROV. Y COLOC. VIDRIOS m2173.6480.1613918.90

36BARANDA METALICAml49.10262.0512866.69

37PINTURA EXTERIORm2675.0936.8324866.15

38PINTURA INTERIORm2852.5329.9425527.91

39CANALETA DE CALAMINA PLANAm1710.20124.45212842.75

40PROV. Y COLOC. DE CAMPANApza13469.4595853469.46

41PROV. Y COLOC. DE TANQUE ELEVADOpza1217.2339962217.23

42DINTEL DE HA ml19.00663.7112610.47

43PROV. Y COLOC. DE PAPEELRO, JABONERApza4.00169.13676.51

44SUMIDERO DE PISOpza2.00172.47344.95

45PROV. Y COLOC. DE LAVANDERIApza1.00378.98378.98

Total monto en Bs.=2276587.58

El rea total de construccin es de 788 m2 y el presupuesto del costo de la obra haciende a un monto total de Bs. 2276587.58 y un valor de 325226.80 en $us Americanos.Por lo tanto el costo por metro cuadrado de la construccin es de 412.72 $us/m2