PRESUPUESTO DEL PROYECTO
PARTIDAS UND METRADO P.U. PARCIAL
OBRAS PROVISIONALES 9,800.00
OFICINAS, ALMACEN, CASETA DE GUARDIANIA GLB 1.00 8,000.00 8,000.00SUMINISTRO DE ENERGIA ELECTRICA MES 3.00 300.00 900.00AGUA Y DESAGUE MES 3.00 300.00 900.00OBRAS PRELIMINARES 781.92
LIMPIEZA INICIAL DE OBRA M2 162.90 1.90 309.51TRAZO Y REPLANTEO DE OBRA M2 162.90 2.90 472.41MOVIMIENTO DE TIERRAS 2,644.47
EXCAVACION DE ZANJAS C/EQUIPO m3 29.85 55.80 1,665.63RELLENO COMPACTADO MATERIAL INTERIOR m3RELLENO COMPACTADO MATERIAL EXTERIOR m3 12.95 9.50 123.02ELIMINACION DE MATERIAL EXCEDENTE m3 20.28 42.20 855.82CONCRETO SIMPLE 5,182.76
SOLADO F'C=100KG/CM2 M2 18.15 32.50 589.88CIMIENTOS CORRIDOS M3 13.10 280.50 3,674.55SOBRECIMIENTO F'C=140KG/CM2 M3 2.82 325.65 918.33ENCOFRADO PARA SOBRECIMIENTOS M2 22.50 42.50 956.25CONCRETO ARMADO 29,953.00
ZAPATAS 65.94
CONCRETO F'C=210 KG/CM2 M3 0.00 565.85 0.00ACERO F'Y=4200KG/CM2 KG 13.68 4.82 65.94VIGAS DE CIMENTACION 622.44
CONCRETO F'C=210 KG/CM2 M3 0.00 565.85 0.00ENCOFRADO Y DESENCOFRADO NORMAL M2 8.34 42.50 354.45ACERO F'Y=4200KG/CM2 KG 55.60 4.82 267.99COLUMNAS 138.82
CONCRETO F'C=210 KG/CM2 M3 0.00 565.85 0.00ENCOFRADO Y DESENCOFRADO METALICO M2 0.00 89.50 0.00ACERO F'Y=4200KG/CM2 KG 28.80 4.82 138.82VIGAS 0.00
CONCRETO F'C=210 KG/CM2 M3 0.00 565.85 0.00ENCOFRADO Y DESENCOFRADO METALICO M2 0.00 89.50 0.00ACERO F'Y=4200KG/CM2 KG 0.00 4.82 0.00LOSA ALIGERADA 29,125.80
CONCRETO F'C=210 KG/CM2 M3 9.12 565.85 5,160.55ENCOFRADO Y DESENCOFRADO METALICO M2 155.50 89.50 13,917.25ACERO F'Y=4200KG/CM2 KG 121.99 4.82 588.00LADRILLO PARA TECHO 20X30X30 UND 1,720.00 5.50 9,460.00ALBAÑILERIA 9,041.76
MURO DE SOGA LADRILLO KK 9X14X24 M2 128.80 70.20 9,041.76
![Page 2: Programacion de Obra Plantilla de Costo](https://reader036.fdocumento.com/reader036/viewer/2022081811/5695d27f1a28ab9b029aa9c6/html5/thumbnails/2.jpg)
REVESTIMIENTOS, TARRAJEOS 13,022.40
TARRAJEO INTERIOR Y EXTERIOR M2 257.60 28.00 7,212.80TARRAJEO EN CIELO RASO M2 158.50 32.50 5,151.25TARRAJEO EN COLUMNAS M2 26.13 25.20 658.35PINTURA 6,191.95
PINTURA EN CIELO RASO M2 158.50 15.50 2,456.75PINTURA EN MUROS INTERIORES Y EXTERIORES M2 257.60 14.50 3,735.20PISOS 43,961.60
PISO DE CERAMICO ALTO TRANSITO M2 158.50 48.00 7,608.00CONTRAZOCALO DE CERAMICO ML 75.20 18.00 1,353.60PISO DE CEMENTO PULIDO - EXTERIORES M2 100.00 350.00 35,000.00CARPINTERA DE MADERA 6,250.00
PUERTA DE MADERA DE TABLERO REBAJADO UND 5.00 1,250.00 6,250.00CARPINTERIA METALICA 1,938.98
PROTECTORES METALICOS M2 15.45 125.50 1,938.98VIDRIOS 12,907.34
VENTANAS TIPO SALOMONICAS M2 25.45 105.20 2,677.34MURO TIPO CORTINA M2 44.00 232.50 10,230.00INSTALACIONES ELECTRICAS 8,669.70
CENTROS DE LUZ PTO 18.00 32.90 592.20CABLE THW PARA INSTALACIONES ELECTRICAS ML 125.00 2.50 312.50SALIDA PARA INTERRUPTORES UND 4.00 40.00 160.00SALIDA PARA TOMACORRIENTES UND 11.00 45.00 495.00ARTEFACTO P/ADOSAR 2 LAMPARAS FLUORESCEN UND 18.00 395.00 7,110.00INSTALACIONES SANITARIAS 368.80
PUNTO DE SALIDA PARA AGUA UND 1.00 89.00 89.00PUNTO DE SALIDA PARA DESAGUE UND 1.00 98.00 98.00TUBERIA PVC 1/2" ML 6.00 12.10 72.60TUBERIA PVC 4" ML 6.00 18.20 109.20VARIOS 570.15
LIMPIEZA FINAL DE OBRA M2 162.90 3.50 570.15
COSTO DIRECTO DEL PROYECTO 151,284.82
COSTO INDIRECTO 20% 30,256.96
PRESUPUESTO TOTAL 181,541.79
![Page 3: Programacion de Obra Plantilla de Costo](https://reader036.fdocumento.com/reader036/viewer/2022081811/5695d27f1a28ab9b029aa9c6/html5/thumbnails/3.jpg)
METRADOS DE MAYOR INDICENCIA
PARTIDA CANT LARGO ANCHO ALTO PARCIAL
ZAPATAS
CONCRETO F'C=210 KG/CM2 19 1.20 1.20 0.50 13.68ACERO F'Y=4200KG/CM2 19 9.60 1.02 186.05
VIGAS DE CIMENTACION
CONCRETO F'C=210 KG/CM2 69.50 0.30 0.40 8.34ENCOFRADO Y DESENCOFRADO NORMAL 2 69.50 0.40 55.60ACERO F'Y=4200KG/CM2 6 69.50 1.60 667.20
COLUMNAS
CONCRETO F'C=210 KG/CM2 13 0.50 0.50 4.00 13.006 0.30 0.30 4.00 2.16
ENCOFRADO Y DESENCOFRADO METALICO 13 2.00 4.00 104.006 1.20 4.00 28.80
ACERO F'Y=4200KG/CM2 19 8.00 2.25 4.30 1470.60
VIGAS
CONCRETO F'C=210 KG/CM2 40.00 0.40 0.70 11.2029.50 0.25 0.50 3.69
ENCOFRADO Y DESENCOFRADO METALICO 40.00 1.55 62.0029.50 1.00 29.50
ACERO F'Y=4200KG/CM2 8 40.00 2.25 720.008 29.50 1.60 377.60
![Page 4: Programacion de Obra Plantilla de Costo](https://reader036.fdocumento.com/reader036/viewer/2022081811/5695d27f1a28ab9b029aa9c6/html5/thumbnails/4.jpg)
METRADOS DE MAYOR INDICENCIA
TOTAL
13.68
186.05
8.34
55.60
667.20
15.16
132.80
1470.60
14.89
91.50
1097.60