VALORIZACIÓN ADICIONAL DE OBRA N°03 - PINTURA (PERIODO 15.02.13 AL 21.02.2013) VALORIZACION N°03 OBRA RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS CONTRATISTA: BAEZ CONSUL SAC FECHA 2/1/2013 RESIDENTE : MRFH / JSVH Ítem Partidas PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por Ejecutar Und. Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar 1.00.00 PINTURA 1.08.00 PINTURA RETOQUE EXTERIORES 1.08.01 PINTURA M2 1,200.00 3.00 3,600.00 700.00 2,100.00 350.00 1,050.00 1,050.00 3,150.00 87.50% 150.00 450.00 12.50% 1.08.00 PINTURA RETOQUE DUCTOS INTERIORES 1.08.01 PINTURA M2 1,500.00 3.00 4,500.00 700.00 2,100.00 350.00 1,050.00 1,050.00 3,150.00 70.00% 450.00 1,350.00 30.00% 1.08.00 PINTURA VARIOS INTERIORES 1.08.01 PINTURA M2 2,000.00 2.50 5,000.00 960.00 2,400.00 458.95 1,147.37 1,418.95 3,547.37 70.95% 581.05 1,452.64 29.05% 4,700.00 SUB-TOTAL 13,100.00 6,600.00 3,247.37 9,847.37 3,252.64 0.72 IGV 18% 2,358.00 1,188.00 584.53 1,772.53 585.47 0.07 TOTAL 15,458.00 7,788.00 3,831.89 11,619.89 75.17% 3,838.11 24.83% NUEVOS SOLES Costo Unitario S/. Parcial Monto de Valorización Total Monto de Valorización Total Monto de Valorización Total Monto de Valorización Total

description

valorizacion pintura

Transcript of Valorizacion Pintura Baez

Page 1: Valorizacion Pintura Baez

VALORIZACIÓN ADICIONAL DE OBRA N°03 - PINTURA(PERIODO 15.02.13 AL 21.02.2013)

VALORIZACION N°03OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 2/1/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.08.00 PINTURA RETOQUE EXTERIORES

1.08.01 PINTURA M2 1,200.00 3.00 3,600.00 700.00 2,100.00 350.00 1,050.00 1,050.00 3,150.00 87.50% 150.00 450.00 12.50%

1.08.00 PINTURA RETOQUE DUCTOS INTERIORES

1.08.01 PINTURA M2 1,500.00 3.00 4,500.00 700.00 2,100.00 350.00 1,050.00 1,050.00 3,150.00 70.00% 450.00 1,350.00 30.00%

1.08.00 PINTURA VARIOS INTERIORES

1.08.01 PINTURA M2 2,000.00 2.50 5,000.00 960.00 2,400.00 458.95 1,147.37 1,418.95 3,547.37 70.95% 581.05 1,452.64 29.05%

4,700.00

SUB-TOTAL 13,100.00 6,600.00 3,247.37 9,847.37 3,252.64 0.72

IGV 18% 2,358.00 1,188.00 584.53 1,772.53 585.47 0.07

TOTAL 15,458.00 7,788.00 3,831.89 11,619.89 75.17% 3,838.11 24.83%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 2: Valorizacion Pintura Baez

VALORIZACIÓN ADICIONAL DE OBRA N°02 - PINTURA(PERIODO 15.02.13 AL 21.02.2013)

VALORIZACION N°02OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 2/22/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.08.00 PINTURA RETOQUE EXTERIORES

1.08.01 PINTURA M2 1,200.00 3.00 3,600.00 350.00 1,050.00 350.00 1,050.00 700.00 2,100.00 58.33% 500.00 1,500.00 41.67%

1.08.00 PINTURA RETOQUE DUCTOS INTERIORES

1.08.01 PINTURA M2 1,500.00 3.00 4,500.00 350.00 1,050.00 350.00 1,050.00 700.00 2,100.00 46.67% 800.00 2,400.00 53.33%

1.08.00 PINTURA VARIOS INTERIORES

1.08.01 PINTURA M2 2,000.00 2.50 5,000.00 480.00 1,200.00 480.00 1,200.00 960.00 2,400.00 48.00% 1,040.00 2,600.00 52.00%

4,700.00

SUB-TOTAL 13,100.00 3,300.00 3,300.00 6,600.00 6,500.00 1.47

IGV 18% 2,358.00 594.00 594.00 1,188.00 1,170.00 0.15

TOTAL 15,458.00 3,894.00 3,894.00 7,788.00 50.38% 7,670.00 49.62%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 3: Valorizacion Pintura Baez

VALORIZACIÓN ADICIONAL DE OBRA N°01 - PINTURA(PERIODO 08.02.13 AL 14.02.2013)

VALORIZACION N°01OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 2/14/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.08.00 PINTURA RETOQUE EXTERIORES

1.08.01 PINTURA M2 1,200.00 3.00 3,600.00 - 350.00 1,050.00 350.00 1,050.00 29.17% 850.00 2,550.00 70.83%

1.08.00 PINTURA RETOQUE DUCTOS INTERIORES

1.08.01 PINTURA M2 1,500.00 3.00 4,500.00 - 350.00 1,050.00 350.00 1,050.00 23.33% 1,150.00 3,450.00 76.67%

1.08.00 PINTURA VARIOS INTERIORES

1.08.01 PINTURA M2 2,000.00 2.50 5,000.00 - 480.00 1,200.00 600.00 1,200.00 24.00% 1,400.00 3,500.00 70.00%

4,700.00

SUB-TOTAL 13,100.00 0.00 3,300.00 3,300.00 9,500.00 2.18

IGV 18% 2,358.00 0.00 594.00 594.00 1,710.00 0.22

TOTAL 15,458.00 0.00 3,894.00 3,894.00 25.19% 11,210.00 72.52%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 4: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°23 - PINTURA(PERIODO 01.02.13 AL 07.02.2013)

VALORIZACION N°23OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 2/7/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 35.00 210.00 1,100.00 6,600.00 100.00% - - 0.00%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 23.00 184.00 1,523.00 12,184.00 100.00% - - 0.00%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,923.00 11,538.00 77.00 462.00 2,000.00 12,000.00 100.00% - - 0.00%

1.08.00 PINTURA RETOQUE

1.08.01 PINTURA RETOQUE - DESPUES DE COLOCACION DE PUERTAS Y PISOS M2 8,000.00 2.00 16,000.00 6,800.00 13,600.00 1,200.00 2,400.00 8,000.00 16,000.00 100.00% - - 0.00%

17,473.92

SUB-TOTAL 81,389.52 78,133.52 3,256.00 81,389.52 0.00 0.00

IGV 18% 14,650.11 14,064.03 586.08 14,650.11 0.00 0.00

TOTAL 96,039.63 92,197.55 3,842.08 96,039.63 100.00% 0.00 0.00%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 5: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°22 - PINTURA(PERIODO 25.01.13 AL 31.01.2013)

VALORIZACION N°22OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 1/31/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,923.00 11,538.00 - 1,923.00 11,538.00 96.15% 77.00 462.00 3.85%

1.08.00 PINTURA RETOQUE

1.08.01 PINTURA RETOQUE - DESPUES DE COLOCACION DE PUERTAS Y PISOS M2 8,000.00 2.00 16,000.00 5,200.00 10,400.00 1,600.00 3,200.00 6,800.00 13,600.00 85.00% 1,200.00 2,400.00 15.00%

17,473.92

SUB-TOTAL 81,389.52 74,933.52 3,200.00 78,133.52 3,256.00 0.24

IGV 18% 14,650.11 13,488.03 576.00 14,064.03 586.08 0.02

TOTAL 96,039.63 88,421.55 3,776.00 92,197.55 96.00% 3,842.08 4.00%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 6: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°21 - PINTURA(PERIODO 18.01.13 AL 24.01.2013)

VALORIZACION N°21OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 1/21/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,923.00 11,538.00 - 1,923.00 11,538.00 96.15% 77.00 462.00 3.85%

1.08.00 PINTURA RETOQUE

1.08.01 PINTURA RETOQUE - DESPUES DE COLOCACION DE PUERTAS Y PISOS M2 8,000.00 2.00 16,000.00 3,600.00 7,200.00 1,600.00 3,200.00 5,200.00 10,400.00 65.00% 2,800.00 5,600.00 35.00%

17,473.92

SUB-TOTAL 81,389.52 71,733.52 3,200.00 74,933.52 6,456.00 0.44

IGV 18% 14,650.11 12,912.03 576.00 13,488.03 1,162.08 0.04

TOTAL 96,039.63 84,645.55 3,776.00 88,421.55 92.07% 7,618.08 7.93%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 7: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°20 - PINTURA(PERIODO 11.01.13 AL 17.01.2013)

VALORIZACION N°20OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 1/17/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,923.00 11,538.00 - 1,923.00 11,538.00 96.15% 77.00 462.00 3.85%

1.08.00 PINTURA RETOQUE

1.08.01 PINTURA RETOQUE - DESPUES DE COLOCACION DE PUERTAS Y PISOS M2 8,000.00 2.00 16,000.00 1,600.00 3,200.00 2,000.00 4,000.00 3,600.00 7,200.00 45.00% 4,400.00 8,800.00 55.00%

17,473.92

SUB-TOTAL 81,389.52 67,733.52 4,000.00 71,733.52 9,656.00 0.64

IGV 18% 14,650.11 12,192.03 720.00 12,912.03 1,738.08 0.06

TOTAL 96,039.63 79,925.55 4,720.00 84,645.55 88.14% 11,394.08 11.86%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 8: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°19 - PINTURA(PERIODO 04.01.13 AL 10.01.2013)

VALORIZACION N°19OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 1/10/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,923.00 11,538.00 - 1,923.00 11,538.00 96.15% 77.00 462.00 3.85%

1.08.00 PINTURA RETOQUE

1.08.01 PINTURA RETOQUE - DESPUES DE COLOCACION DE PUERTAS Y PISOS M2 8,000.00 2.00 16,000.00 - - 1,600.00 3,200.00 1,600.00 3,200.00 20.00% 6,400.00 12,800.00 80.00%

17,473.92

SUB-TOTAL 81,389.52 64,533.52 3,200.00 67,733.52 13,656.00 0.89

IGV 18% 14,650.11 11,616.03 576.00 12,192.03 2,458.08 0.09

TOTAL 96,039.63 76,149.55 3,776.00 79,925.55 83.22% 16,114.08 16.78%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 9: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°18 - PINTURA(PERIODO 28.12.12 AL 03.01.2013)

VALORIZACION N°18OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 1/3/2013

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 550.00 2,750.00 - - 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 1,398.00 8,388.00 525.00 3,150.00 1,923.00 11,538.00 96.15% 77.00 462.00 3.85%

9,473.92

SUB-TOTAL 59,889.52 61,383.52 3,150.00 64,533.52 856.00 0.09

IGV 18% 10,780.11 11,049.03 567.00 11,616.03 154.08 0.01

TOTAL 70,669.63 72,432.55 3,717.00 76,149.55 107.75% 1,010.08 1.43%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 10: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°17 - PINTURA(PERIODO 21.12.12 AL 27.12.2012)

VALORIZACION N°17OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 12/27/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 450.00 2,250.00 100.00 500.00 550.00 2,750.00 100.00% - - 0.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 500.00 2,500.00 50.00 250.00 550.00 2,750.00 100.00% - - 0.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,065.00 6,390.00 - 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,500.00 12,000.00 - 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 808.00 4,848.00 590.00 3,540.00 1,398.00 8,388.00 69.90% 602.00 3,612.00 30.10%

9,473.92

SUB-TOTAL 59,889.52 57,093.52 4,290.00 61,383.52 4,006.00 0.35

IGV 18% 10,780.11 10,276.83 772.20 11,049.03 721.08 0.03

TOTAL 70,669.63 67,370.35 5,062.20 72,432.55 102.49% 4,727.08 6.69%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 11: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°16 - PINTURA(PERIODO 14.12.12 AL 20.12.2012)

VALORIZACION N°16OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 12/20/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 350.00 1,750.00 100.00 500.00 450.00 2,250.00 81.82% 100.00 500.00 18.18%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 350.00 1,750.00 150.00 750.00 500.00 2,500.00 90.91% 50.00 250.00 9.09%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,035.00 6,210.00 30.00 180.00 1,065.00 6,390.00 96.82% 35.00 210.00 3.18%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,400.00 11,200.00 100.00 800.00 1,500.00 12,000.00 98.49% 23.00 184.00 1.51%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 2,000.00 6.00 12,000.00 458.00 2,748.00 350.00 2,100.00 808.00 4,848.00 40.40% 1,192.00 7,152.00 59.60%

9,473.92

SUB-TOTAL 59,889.52 52,763.52 4,330.00 57,093.52 8,296.00 0.92

IGV 18% 10,780.11 9,497.43 779.40 10,276.83 1,493.28 0.09

TOTAL 70,669.63 62,260.95 5,109.40 67,370.35 95.33% 9,789.28 13.85%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 12: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°15 - PINTURA(PERIODO 07.12.12 AL 13.12.2012)

VALORIZACION N°15OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 12/13/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 PINTURA

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 200.00 1,000.00 150.00 750.00 350.00 1,750.00 63.64% 200.00 1,000.00 36.36%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 300.00 1,500.00 50.00 250.00 350.00 1,750.00 63.64% 200.00 1,000.00 36.36%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 1,025.00 6,150.00 10.00 60.00 1,035.00 6,210.00 94.09% 65.00 390.00 5.91%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,300.00 10,400.00 100.00 800.00 1,400.00 11,200.00 91.92% 123.00 984.00 8.08%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 1,000.00 6.00 6,000.00 180.00 1,080.00 278.00 1,668.00 458.00 2,748.00 45.80% 542.00 3,252.00 54.20%

8,473.92

SUB-TOTAL 53,889.52 49,235.52 3,528.00 52,763.52 6,626.00 1.41

IGV 18% 9,700.11 8,862.39 635.04 9,497.43 1,192.68 0.14

TOTAL 63,589.63 58,097.91 4,163.04 62,260.95 97.91% 7,818.68 12.30%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 13: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°14 - PINTURA(PERIODO 30.11.12 AL 06.12.2012)

VALORIZACION N°14OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 12/6/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 - - 200.00 1,000.00 200.00 1,000.00 36.36% 350.00 1,750.00 63.64%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 - - 300.00 1,500.00 300.00 1,500.00 54.55% 250.00 1,250.00 45.45%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,212.73 7,276.38 - 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 975.00 5,850.00 50.00 300.00 1,025.00 6,150.00 93.18% 75.00 450.00 6.82%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 1,200.00 9,600.00 100.00 800.00 1,300.00 10,400.00 85.36% 223.00 1,784.00 14.64%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 1,000.00 6.00 6,000.00 - - 180.00 1,080.00 180.00 1,080.00 18.00% 820.00 4,920.00 82.00%

8,473.92

SUB-TOTAL 53,889.52 44,555.52 4,680.00 49,235.52 10,154.00 2.13

IGV 18% 9,700.11 8,019.99 842.40 8,862.39 1,827.72 0.21

TOTAL 63,589.63 52,575.51 5,522.40 58,097.91 91.36% 11,981.72 18.84%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 14: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°13 - PINTURA(PERIODO 23.11.12 AL 29.11.2012)

VALORIZACION N°12OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 11/29/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 SOTANO 2

1.04.01 SOTANO 2 M2 550.00 5.00 2,750.00 - - - - 0.00% 550.00 2,750.00 100.00%

1.06.00 SOTANO 1

1.06.01 SOTANO 1 M2 550.00 5.00 2,750.00 - - - - 0.00% 550.00 2,750.00 100.00%

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,180.00 7,080.00 32.73 196.38 1,212.73 7,276.38 100.00% - - 0.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,120.00 6,720.00 92.73 556.38 1,212.73 7,276.38 100.00% - - 0.00%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,166.00 6,996.00 46.73 280.38 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,130.00 6,780.00 82.73 496.38 1,212.73 7,276.38 100.00% - - 0.00%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 975.00 5,850.00 - 975.00 5,850.00 88.64% 125.00 750.00 11.36%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,523.00 8.00 12,184.00 950.00 7,600.00 250.00 2,000.00 1,200.00 9,600.00 78.79% 323.00 2,584.00 21.21%

1.08.00 PINTURA VECINOS

1.08.01 PINTURA EXTERIORES M2 1,000.00 6.00 6,000.00 - - - - 0.00% 1,000.00 6,000.00 100.00%

8,473.92

SUB-TOTAL 53,889.52 41,026.00 3,529.52 44,555.52 14,834.00 3.33

IGV 18% 9,700.11 7,384.68 635.31 8,019.99 2,670.12 0.33

TOTAL 63,589.63 48,410.68 4,164.83 52,575.51 82.68% 17,504.12 27.53%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 15: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°12 - PINTURA(PERIODO 16.11.12 AL 22.11.2012)

VALORIZACION N°12OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 11/22/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,180.00 7,080.00 - 1,180.00 7,080.00 97.30% 32.73 196.38 2.70%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,120.00 6,720.00 - 1,120.00 6,720.00 92.35% 92.73 556.38 7.65%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,166.00 6,996.00 - 1,166.00 6,996.00 96.15% 46.73 280.38 3.85%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,130.00 6,780.00 - 1,130.00 6,780.00 93.18% 82.73 496.38 6.82%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 450.00 2,700.00 525.00 3,150.00 975.00 5,850.00 88.64% 125.00 750.00 11.36%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,000.00 8.00 8,000.00 950.00 7,600.00 - 950.00 7,600.00 95.00% 50.00 400.00 5.00%

6,950.92

SUB-TOTAL 43,705.52 37,876.00 3,150.00 41,026.00 2,679.52 0.37

IGV 18% 7,866.99 6,817.68 567.00 7,384.68 482.31 0.04

TOTAL 51,572.51 44,693.68 3,717.00 48,410.68 93.87% 3,161.83 6.13%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 16: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°11 - PINTURA(PERIODO 09.11.12 AL 15.11.2012)

VALORIZACION N°11OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 11/15/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,180.00 7,080.00 - 1,180.00 7,080.00 97.30% 32.73 196.38 2.70%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,120.00 6,720.00 - 1,120.00 6,720.00 92.35% 92.73 556.38 7.65%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,166.00 6,996.00 - 1,166.00 6,996.00 96.15% 46.73 280.38 3.85%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,130.00 6,780.00 - 1,130.00 6,780.00 93.18% 82.73 496.38 6.82%

1.08.00 PINTURA 1

1.08.01 PINTURA 1 M2 1,100.00 6.00 6,600.00 - 450.00 2,700.00 450.00 2,700.00 40.91% 650.00 3,900.00 59.09%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,000.00 8.00 8,000.00 950.00 7,600.00 - 950.00 7,600.00 95.00% 50.00 400.00 5.00%

6,950.92

SUB-TOTAL 43,705.52 35,176.00 2,700.00 37,876.00 5,829.52 0.85

IGV 18% 7,866.99 6,331.68 486.00 6,817.68 1,049.31 0.09

TOTAL 51,572.51 41,507.68 3,186.00 44,693.68 86.66% 6,878.83 13.34%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 17: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°10 - PINTURA(PERIODO 01.10.12 AL 08.11.2012)

VALORIZACION N°10OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 11/8/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,160.00 6,960.00 20.00 120.00 1,180.00 7,080.00 97.30% 32.73 196.38 2.70%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,090.00 6,540.00 30.00 180.00 1,120.00 6,720.00 92.35% 92.73 556.38 7.65%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,146.00 6,876.00 20.00 120.00 1,166.00 6,996.00 96.15% 46.73 280.38 3.85%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,110.00 6,660.00 20.00 120.00 1,130.00 6,780.00 93.18% 82.73 496.38 6.82%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,000.00 8.00 8,000.00 750.00 6,000.00 200.00 1,600.00 950.00 7,600.00 95.00% 50.00 400.00 5.00%

5,850.92

SUB-TOTAL 37,105.52 33,036.00 2,140.00 35,176.00 1,929.52 0.26

IGV 18% 6,678.99 5,946.48 385.20 6,331.68 347.31 0.03

TOTAL 43,784.51 38,982.48 2,525.20 41,507.68 94.80% 2,276.83 5.20%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 18: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°09 - PINTURA(PERIODO 25.10.12 AL 31.10.2012)

VALORIZACION N°09OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 10/31/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,080.00 6,480.00 80.00 480.00 1,160.00 6,960.00 95.65% 52.73 316.38 4.35%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 1,010.00 6,060.00 80.00 480.00 1,090.00 6,540.00 89.88% 122.73 736.38 10.12%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,066.00 6,396.00 80.00 480.00 1,146.00 6,876.00 94.50% 66.73 400.38 5.50%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,030.00 6,180.00 80.00 480.00 1,110.00 6,660.00 91.53% 102.73 616.38 8.47%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,000.00 8.00 8,000.00 500.00 4,000.00 250.00 2,000.00 750.00 6,000.00 75.00% 250.00 2,000.00 25.00%

5,850.92

SUB-TOTAL 37,105.52 29,116.00 3,920.00 33,036.00 4,069.52 0.53

IGV 18% 6,678.99 5,240.88 705.60 5,946.48 732.51 0.05

TOTAL 43,784.51 34,356.88 4,625.60 38,982.48 89.03% 4,802.03 10.97%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 19: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°08 - PINTURA(PERIODO 18.10.12 AL 24.10.2012)

VALORIZACION N°08OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 10/24/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 1,080.00 6,480.00 - 1,080.00 6,480.00 89.06% 132.73 796.38 10.94%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 960.00 5,760.00 50.00 300.00 1,010.00 6,060.00 83.28% 202.73 1,216.38 16.72%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 1,036.00 6,216.00 30.00 180.00 1,066.00 6,396.00 87.90% 146.73 880.38 12.10%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 1,000.00 6,000.00 30.00 180.00 1,030.00 6,180.00 84.93% 182.73 1,096.38 15.07%

1.08.00 PINTURA EXTERIORES

1.08.01 PINTURA EXTERIORES M2 1,000.00 8.00 8,000.00 - 500.00 4,000.00 500.00 4,000.00 50.00% 500.00 4,000.00 50.00%

5,850.92

SUB-TOTAL 37,105.52 24,456.00 4,660.00 29,116.00 7,989.52 1.05

IGV 18% 6,678.99 4,402.08 838.80 5,240.88 1,438.11 0.10

TOTAL 43,784.51 28,858.08 5,498.80 34,356.88 78.47% 9,427.63 21.53%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 20: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°07 - PINTURA(PERIODO 11.10.12 AL 17.10.2012)

VALORIZACION N°06OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 10/10/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 830.00 4,980.00 250.00 1,500.00 1,080.00 6,480.00 89.06% 132.73 796.38 10.94%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 730.00 4,380.00 230.00 1,380.00 960.00 5,760.00 79.16% 252.73 1,516.38 20.84%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 810.00 4,860.00 226.00 1,356.00 1,036.00 6,216.00 85.43% 176.73 1,060.38 14.57%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 810.00 4,860.00 190.00 1,140.00 1,000.00 6,000.00 82.46% 212.73 1,276.38 17.54%

4,850.92

SUB-TOTAL 29,105.52 19,080.00 5,376.00 24,456.00 4,649.52 0.64

IGV 18% 5,238.99 3,434.40 967.68 4,402.08 836.91 0.06

TOTAL 34,344.51 22,514.40 6,343.68 28,858.08 84.03% 5,486.43 15.97%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 21: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°06 - PINTURA(PERIODO 04.10.12 AL 10.10.2012)

VALORIZACION N°06OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 10/10/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 680.00 4,080.00 150.00 900.00 830.00 4,980.00 68.44% 382.73 2,296.38 31.56%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 630.00 3,780.00 100.00 600.00 730.00 4,380.00 60.19% 482.73 2,896.38 39.81%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 660.00 3,960.00 150.00 900.00 810.00 4,860.00 66.79% 402.73 2,416.38 33.21%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 660.00 3,960.00 150.00 900.00 810.00 4,860.00 66.79% 402.73 2,416.38 33.21%

4,850.92

SUB-TOTAL 29,105.52 15,780.00 3,300.00 19,080.00 10,025.52 1.38

IGV 18% 5,238.99 2,840.40 594.00 3,434.40 1,804.59 0.14

TOTAL 34,344.51 18,620.40 3,894.00 22,514.40 65.55% 11,830.11 34.45%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 22: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°05 - PINTURA(PERIODO 27.09.12 AL 03.10.2012)

VALORIZACION N°05OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 10/3/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 530.00 3,180.00 150.00 900.00 680.00 4,080.00 56.07% 532.73 3,196.38 43.93%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 530.00 3,180.00 100.00 600.00 630.00 3,780.00 51.95% 582.73 3,496.38 48.05%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 510.00 3,060.00 150.00 900.00 660.00 3,960.00 54.42% 552.73 3,316.38 45.58%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 510.00 3,060.00 150.00 900.00 660.00 3,960.00 54.42% 552.73 3,316.38 45.58%

4,850.92

SUB-TOTAL 29,105.52 12,480.00 3,300.00 15,780.00 13,325.52 1.83

IGV 18% 5,238.99 2,246.40 594.00 2,840.40 2,398.59 0.18

TOTAL 34,344.51 14,726.40 3,894.00 18,620.40 54.22% 15,724.11 45.78%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 23: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°04 - PINTURA(PERIODO 20.09.12 AL 26.09.2012)

VALORIZACION N°04OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 9/26/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 380.00 2,280.00 150.00 900.00 530.00 3,180.00 43.70% 682.73 4,096.38 56.30%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 380.00 2,280.00 150.00 900.00 530.00 3,180.00 43.70% 682.73 4,096.38 56.30%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 360.00 2,160.00 150.00 900.00 510.00 3,060.00 42.05% 702.73 4,216.38 57.95%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 360.00 2,160.00 150.00 900.00 510.00 3,060.00 42.05% 702.73 4,216.38 57.95%

4,850.92

SUB-TOTAL 29,105.52 8,880.00 3,600.00 12,480.00 16,625.52 2.28

IGV 18% 5,238.99 1,598.40 648.00 2,246.40 2,992.59 0.23

TOTAL 34,344.51 10,478.40 4,248.00 14,726.40 42.88% 19,618.11 57.12%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 24: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°03 - PINTURA(PERIODO 13.09.12 AL 19.09.2012)

VALORIZACION N°03OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 9/19/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 280.00 1,680.00 100.00 600.00 380.00 2,280.00 31.33% 832.73 4,996.38 68.67%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 280.00 1,680.00 100.00 600.00 380.00 2,280.00 31.33% 832.73 4,996.38 68.67%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 180.00 1,080.00 180.00 1,080.00 360.00 2,160.00 29.69% 852.73 5,116.38 70.31%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 180.00 1,080.00 180.00 1,080.00 360.00 2,160.00 29.69% 852.73 5,116.38 70.31%

4,850.92 560.00

SUB-TOTAL 29,105.52 5,520.00 3,360.00 8,880.00 20,225.52 2.78

IGV 18% 5,238.99 993.60 604.80 1,598.40 3,640.59 0.28

TOTAL 34,344.51 6,513.60 3,964.80 10,478.40 30.51% 23,866.11 69.49%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 25: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°02 - PINTURA(PERIODO 06.09.12 AL 12.09.2012)

VALORIZACION N°02OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 9/12/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 180.00 1,080.00 100.00 600.00 280.00 1,680.00 23.09% 932.73 5,596.38 76.91%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 180.00 1,080.00 100.00 600.00 280.00 1,680.00 23.09% 932.73 5,596.38 76.91%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 - - 180.00 1,080.00 180.00 1,080.00 14.84% 1,032.73 6,196.38 85.16%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 - - 180.00 1,080.00 180.00 1,080.00 14.84% 1,032.73 6,196.38 85.16%

4,850.92

SUB-TOTAL 29,105.52 2,160.00 3,360.00 5,520.00 23,585.52 3.24

IGV 18% 5,238.99 388.80 604.80 993.60 4,245.39 0.32

TOTAL 34,344.51 2,548.80 3,964.80 6,513.60 18.97% 27,830.91 81.03%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 26: Valorizacion Pintura Baez

VALORIZACIÓN DE OBRA N°01 - PINTURA(PERIODO 30.08.12 AL 05.09.2012)

VALORIZACION N°01OBRA : RESIDENCIAL MALLKI MODALIDAD: A PRECIOS UNITARIOS

CONTRATISTA: BAEZ CONSUL SAC

FECHA : 9/5/2012

RESIDENTE : MRFH / JSVH

Ítem Partidas

PROPUESTA CONTRACTUAL Avance Anterior Avance Actual Avance Acumulado Saldo por EjecutarUnd.

Metrado Metrado Metrado Metrado % Ejecutado Metrado % Por Ejecutar

1.00.00 CONTRAPISOS

1.04.00 PINTURA 4

1.04.01 PINTURA 4 M2 1,212.73 6.00 7,276.38 - 180.00 1,080.00 180.00 1,080.00 14.84% 1,032.73 6,196.38 85.16%

1.05.00 PINTURA 5

1.05.01 PINTURA 5 M2 1,212.73 6.00 7,276.38 - - - - 0.00% 1,212.73 7,276.38 100.00%

1.06.00 PINTURA 6

1.06.01 PINTURA 6 M2 1,212.73 6.00 7,276.38 - 180.00 1,080.00 180.00 1,080.00 14.84% 1,032.73 6,196.38 85.16%

1.07.00 PINTURA 7

1.07.01 PINTURA 7 M2 1,212.73 6.00 7,276.38 - - - - 0.00% 1,212.73 7,276.38 100.00%

1.08.00 PINTURA 8

1.08.01 PINTURA 8 M2 1,212.73 6.00 7,276.38 - - - - 0.00% 1,212.73 7,276.38 100.00%

1.09.00 PINTURA 9

1.03.01 PINTURA 9 M2 1,212.73 6.00 7,276.38 - - - - 0.00% 1,212.73 7,276.38 100.00%

1.09.01 PINTURA 10

1.03.02 PINTURA 9 M2 1,212.73 6.00 7,276.38 - - - - 0.00% 1,212.73 7,276.38 100.00%

1.10.00 PINTURA EXTERIORES

1.04.01 EXTERIORES M2 1,739.55 6.00 10,437.30 - - - - 0.00% 1,739.55 10,437.30 100.00%

10,228.66

SUB-TOTAL 61,371.96 0.00 2,160.00 2,160.00 59,211.96 7.70

IGV 18% 11,046.95 0.00 388.80 388.80 10,658.15 0.77

TOTAL 72,418.91 0.00 2,548.80 2,548.80 3.52% 69,870.11 96.48%

NUEVOS SOLES

Costo Unitario

S/.

Costo Parcial

S. Monto de Valorización Total

Monto de Valorización

Total

Monto de Valorización

Total

Monto de Valorización

Total

Page 27: Valorizacion Pintura Baez

RESUMEN DE VALORIZACION PINTURA ADICIONAL Nº03

OBRA : RESIDENCIAL MALLKICONTRATISTA : BAEZ CONSUL SACPERIODO VALORIZADO : DEL 23.02.13 AL 01.03.13FECHA CONTRATO : 8/13/2012MONTO CONTRATO : S/. NUEVOS SOLES

DESCRIPCION MONTO

COSTO DIRECTO TOTAL S/. 3247.37

IGV 18% S/. 584.53

VALORIZACION NETA S/. 3831.89

RETENCION POR FIEL CUMPLIMIENTO 5% S/. 191.59

TOTAL A PAGAR S/. 3640.30

MONTO A CANCELAR CHEQUE S/. 3640.30 NUEVOS SOLES

A NOMBRE DE : BAEZ CONSUL SAC

Page 28: Valorizacion Pintura Baez

PAGOS EFECTUADOS

OBRA : RESIDENCIAL MALLKICONTRATISTA : BAEZ CONSUL SACPERIODO VALORIZADO : DEL 23.02.13 al 01.03.13FECHA CONTRATO : 8/13/2101MONTO CONTRATO S/. NUEVOS SOLES

FECHA VALORIZACION COSTO DIRECTO IGV 18% VALORIZACION RETENCION TOTALNETA 5%

05.09.12 VALORIZACION N°01 2160.00 388.80 2548.80 127.44 2421.3612.09.12 VALORIZACION N°02 3360.00 604.80 3964.80 198.24 3766.5619.09.12 VALORIZACION N°03 3360.00 604.80 3964.80 198.24 3766.56 26.09.12 VALORIZACION N°04 3600.00 648.00 4248.00 212.40 4035.6003.10.12 VALORIZACION N°05 3300.00 594.00 3894.00 194.70 3699.3010.10.12 VALORIZACION N°06 3300.00 594.00 3894.00 194.70 3699.3017.10.12 VALORIZACION N°07 5376.00 967.68 6343.68 317.18 6026.5024.10.12 VALORIZACION N°08 4660.00 838.80 5498.80 274.94 5223.8631.10.12 VALORIZACION N°09 3920.00 705.60 4625.60 231.28 4394.3208.11.12 VALORIZACION N°10 2140.00 385.20 2525.20 126.26 2398.9415.11.12 VALORIZACION N°11 2700.00 486.00 3186.00 159.30 3026.7022.11.12 VALORIZACION N°12 3150.00 567.00 3717.00 185.85 3531.1529.11.12 VALORIZACION N°13 3529.52 635.31 4164.83 208.24 3956.5906.12.12 VALORIZACION N°14 4680.00 842.40 5522.40 276.12 5246.2813.12.12 VALORIZACION N°15 3528.00 635.04 4163.04 208.15 3954.8920.12.12 VALORIZACION N°16 4330.00 779.40 5109.40 255.47 4853.9327.12.12 VALORIZACION N°17 4290.00 772.20 5062.20 253.11 4809.0903.01.13 VALORIZACION N°18 3150.00 567.00 3717.00 185.85 3531.1510.01.13 VALORIZACION N°19 3200.00 576.00 3776.00 188.80 3587.2017.01.13 VALORIZACION N°20 4000.00 720.00 4720.00 236.00 4484.0024.01.13 VALORIZACION N°21 3200.00 576.00 3776.00 188.80 3587.2031.01.13 VALORIZACION N°22 3200.00 576.00 3776.00 188.80 3587.2007.02.13 VALORIZACION N°23 3256.00 586.08 3842.08 192.10 3649.9814.02.13 ADICIONAL N°01 3300.00 594.00 3894.00 194.70 3699.3021.02.13 ADICIONAL N°02 3300.00 594.00 3894.00 194.70 3699.3001.03.13 ADICIONAL N°03 3247.37 584.53 3831.89 191.59 3640.30

PAGOS TOTALES 91,236.89 16,422.64 107,659.52 5,382.98 102,276.55

A NOMBRE DE : BAEZ CONSUL SAC

Page 29: Valorizacion Pintura Baez

RESUMEN DE VALORIZACION

1.- AVANCE EJECUTADO S/.

VALORZACION N°01 2250.03VALORZACION N°02 2774.97

2.- IMPUESTO IGV 18% (1)S/.

VALORZACION N°01 405.01VALORZACION N°02 499.49

3.- SUB - TOTAL (1+2) S/.

VALORZACION N°01 2655.04VALORZACION N°02 3274.46

4.- RETENCIONES (5% (3))S/.

VALORZACION N°01 132.75VALORZACION N°02 163.72

5.- PAGOS (2) - (3) S/.

VALORZACION N°01 2522.29VALORZACION N°02 3110.74

TOTAL S/. 5633.03

6.- DEVOLUCIONES (4)S/.

VALORZACION N°01 132.75VALORZACION N°02 163.72

TOTAL S/. 296.48

TOTAL PRESUPUESTO (5+6) S/. 5929.50