CRONOGRAMA VALORIZADO DE EJECUCION DE OBRAPROYECTO : CONSTRUCCION Y MEJORAMIENTO DE PISTAS, VEREDAS, GRADERIAS Y MURO DE CONTENCION DE LAS AA.VV. LA CANTUTA, SELVA ALEGRE
Y ALTO PEDREGALDEPARTAMENTO : MOQUEGUAPROVINCIA : MARISCAL NIETODISTRITO : MOQUEGUA
Partida DESCRIPCION Parcial (S/.) MESES1 MES 2 MES 3 MES
01.00.00 OBRAS PROVISIONALES 3,845.44 3,845.44
02.00.00 TRABAJOS PRELIMINARES 29,431.56 11,772.62 11,772.62 5,886.31
03.00.00 MOVIMIENTO DE TIERRAS 80,583.00 80,583.00
04.00.00 OBRAS DE CONCRETO SIMPLE 289,728.99 173,837.39 115,891.60
05.00.00 OBRAS DE CONCRETO ARMADO 25,065.23 18,798.92 6,266.31
06.00.00 PAVIMENTOS 440,490.77 88,098.15 198,220.85 154,171.77
07.00.00 SARDINELES DE CONCRETO 274,098.45 109,639.38 164,459.07
08.00.00 CARPINTERIA METALICA 58,568.27 58,568.27
09.00.00 JARDINERIA 27,348.25 27,348.25
10.00.00 OBRAS COMPLEMENTARIAS 29,971.26 5,994.25 23,977.01
11.00.00 CONSERVACION DE MEDIO AMBIENTE 13,280.78 1,328.08 4,648.27 7,304.43
COSTO DIRECTO 1,272,412.00 469,104.07 578,353.85 224,954.08GASTOS DE DIRECCION TECNICA (6.00%) 76,344.72 28,146.24 34,701.23 13,497.24
SUPERVISION Y LIQUIDACION TECN Y FINAN. (3.00%) 38,172.36 14,073.12 17,350.62 6,748.62GASTOS ADMINISTRATIVOS (1.00%) 12,724.12 4,691.04 5,783.54 2,249.54
TOTAL PRESUPUESTO 1,399,653.20 516,014.48 636,189.24 247,449.48
PORCENTAJE DE AVANCE FISICO MENSUAL 36.87% 45.45% 17.68%PORCENTAJE DE AVANCE FISICO MENSUAL ACUMULADO 36.87% 82.32% 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRAPROYECTO : CONSTRUCCION Y MEJORAMIENTO DE PISTAS, VEREDAS, GRADERIAS Y MURO DE CONTENCION DE LAS AA.VV. LA CANTUTA, SELVA ALEGRE
Y ALTO PEDREGALDEPARTAMENTO : MOQUEGUAPROVINCIA : MARISCAL NIETODISTRITO : MOQUEGUA
3,845.44BIEN
29,431.56BIEN
80,583.00BIEN
289,728.99BIEN
25,065.23BIEN
440,490.77BIEN
274,098.45BIEN
58,568.27BIEN
27,348.25BIEN
29,971.26BIEN
13,280.78BIEN
1,272,412.00 BIEN76,344.72 BIEN38,172.36 BIEN12,724.12 BIEN
1,399,653.20 BIEN
CRONO