Ejemplo Formula Polinomica
-
Upload
alan-ramos -
Category
Documents
-
view
3 -
download
0
description
Transcript of Ejemplo Formula Polinomica
COSTOS Y PRESUPUESTOS
FORMULA POLINÓMICA
PROYECTO: CONSTRUCCION DE CIMIENTOS
PRESUPUESTO
HOJA DEL PRESUPUESTOUNIDAD METRADO COSTO P. COSTO T. S/.
1 OBRAS PRELIMINARES1.1 TRAZO Y REPLANTEO m2 420 S/. 0.64 S/. 268.35
2 MOVIMIENTO DE TIERRAS2.1 EXCAVACION EN MATERIAL SUELTO m3 130 S/. 16.48 S/. 2,142.402.2 EXCAVACION EN MATERIAL COMPACTO m2 80 S/. 24.72 S/. 1,977.602.3 ELIMINACION DE MATERIAL EXCEDENTE m3 283.5 S/. 8.84 S/. 2,504.92
3 ESTRUCTURAS3.1 VACIADO DE CONCRETO m3 210 S/. 200.65 S/. 42,136.533.2 CURADO m2 420 S/. 0.49 S/. 207.65
COSTO DIRECTO S/. 49,237.44GASTOS GENERALES 15 % C.D. S/. 7,385.62UTILIDAD 20% CD S/. 9,847.49SUBTOTAL S/. 66,470.55I.G.V. 19 % S/. 12,629.40PRESUPUESTO S/. S/. 79,099.95
ANALISIS DE COSTOS UNITARIOS
1.1 TRAZO Y REPLANTEORENDIMIENTO 500 m2/dia UNIDAD m2MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALTOPOGRAFO h.h 1 0.016 10.000 0.16OFICIAL h.h 1 0.016 8.000 0.128PEON h.h 2 0.032 6.000 0.192
0.48EQUIPONIVEL TOPOG. h.m. 1 0.016 8.403 0.134H.M. 0.030 0.480 0.014
0.149MATERIALESPINTURA ESMALTE gal 0.001 10.084 0.010
total 0.639
2.1 EXCAVACION EN MATERIAL SUELTORENDIMIENTO 3 m3/dia UNIDAD m3MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALPEON h.h 1 2.667 6.000 16.000
16.000EQUIPOH.M. 0.030 16.000 0.480MATERIALES
total 16.480
FACULTAD DE INGENIERIAS Y ARQUITECTURAESCUELA ACADEMICO PROFESIONAL DE INGENIERIA CIVIL
UAP
2.2 EXCAVACION EN MATERIAL COMPACTORENDIMIENTO 2 m3/dia UNIDAD m3MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALPEON h.h 1 4.000 6.000 24.000
24.000EQUIPOH.M. 0.030 24.000 0.720
0.720total 24.720
2.3 ELIMINACION DE MATERIAL EXCEDENTE D=5 kmRENDIMIENTO 850 m3/dia UNIDAD m3MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALOFICIAL h.h 1 0.009 8.000 0.075PEON h.h 1 0.009 6.000 0.056
0.132EQUIPOCARGADOR FRONTAL h.m. 1 0.009 168.067 1.582CAMION VOLQUETE 15 m3 h.m. 5 0.047 151.261 7.118H.M. 0.030 0.132 0.004
8.704total 8.836
3.1 VACIADO DE CONCRETO CICLOPEO 1:8 + 40% P.G.RENDIMIENTO 15 m3/dia UNIDAD m3MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALOPERARIO h.h 2 1.067 10.000 10.667OFICIAL h.h 3 1.600 8.000 12.800PEON h.h 10 5.333 6.000 32.000
55.467EQUIPOH.M. 0.030 55.467 1.664MEZCLADORA DE CONCRETO DE 9 -11P3 h.m 1 0.533 6.723 3.586
5.250MATERIALESCEMENTO PORTLAND TIPO I (42.5KG) bolsa 3.220 21.849 70.354HORMIGON m3 0.720 58.824 42.353PIEDRA GRANDE m3 0.540 50.420 27.227
total 200.650
3.2 CURADORENDIMIENTO 100 m2/dia UNIDAD m2MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALPEON h.h 1 0.080 6.000 0.480
0.480EQUIPOH.M. 0.030 0.480 0.014
total 0.494
FORMULA POLINOMICA
Descripción Recurso Unidad Parcial S/. % AGRUPAMIENTO COEFICIENTES I.U. % DE INCIDENCIAMano de Obra
TOPOGRAFO hh S/. 67.20 0.001 0.001
0.242 47 100.00%OPERARIO hh S/. 2,240.00 0.034 0.034
OFICIAL hh S/. 2,763.11 0.042 0.042
PEON hh S/. 11,018.25 0.166 0.166
S/. 16,088.56 0.242
Materiales
PINTURA ESMALTE gal S/. 4.24 0.000 0.222 21 100.00%CEMENTO PORTLAND TIPO I (42.5KG) bolsa S/. 14,774.29 0.222 0.222
HORMIGON m3 S/. 8,894.19 0.134 0.220 0.22038 60.87%
PIEDRA GRANDE m3 S/. 5,717.63 0.086 5 39.13%S/. 29,390.35
Equipos
HERRAMIENTAS MANUALES %MO S/. 482.66 0.007 0.007
0.057
37 12.84%NIVEL TOPOG. hm S/. 56.47 0.001 0.001 48 1.50%CARGADOR FRONTAL hm S/. 448.44 0.007 0.007 48 11.93%CAMION VOLQUETE 15 m3 hm S/. 2,018.00 0.030 0.030 48 53.69%MEZCLADORA DE CONCRETO DE 9 -11P3 hm S/. 752.98 0.011 0.011 48 20.03%
S/. 3,758.54 0.057
COSTO DIRECTO S/. 49,237.44
GASTOS GENERALES 15 % S/. 7,385.62 0.111 0.111 0.25939 42.86%
UTILIDAD 20 % S/. 9,847.49 0.148 0.148 39 57.14%SUB TOTAL S/. 66,470.55IGV 19% S/. 12,629.40TOTAL S/. 79,099.95SUMATORIA COEFICIENTES 1.000
COD ELEMENTO IU COEFICIENTE %JHM MANO DE OBRA INCLUYE LEYES SOCIALES 47 0.242 100.00%
C CEMENTO PORTLAND 21 0.222 100.00%
HHORMIGON 38
0.22060.87%
PIEDRA GRANDE 05 39.13%
E
HERRAMIENTAS MANUALES 37
0.057
12.84%NIVEL TOPOGRAFICO 48 1.50%CARGADOR FRONTAL 48 11.93%CAMION VOLQUETE 15 m3 48 53.69%
K = 0.242 JHMr + 0.222 Cr + 0.220 Hr + 0.057 Er + 0.259 GGUr JHMo Co Ho Eo GGUo
E
MEZCLADORA DE CONCRETO DE 9 -11P3 48
0.057
20.03%
GGUGASTOS GENERALES 39
0.25942.86%
UTILIDAD 39 57.14%